Project # ASHE 16-1030 ADD#1 Technical Specifications

DATE: JUNE 2017

31CES/CEMN 1

Date: JUNE 2017

U.S. AIR FORCE

31ST FIGHTER WING

31ST CES/CENM

AVIANO AIR BASE, ITALY

TECHNICAL SPECIFICATIONS FOR

ASHE 16-1030 REPAIR HVAC SYSTEM MULTI

AREA F, AVIANO AB, ITALY

ADDENDUM#1

Project # ASHE 16-1030 ADD#1 Technical Specifications

DATE: JUNE 2017

31CES/CEMN 2

1. Bldg 14671.

Paragraph “f” Pipeline, valves, Pressure and Temperature gauges .

• All valves must be heavy duty, total passage, PN50.

Qty: 6 Each

2. Bldg 1478 Upgrade DDC at Base Theatre & Post Office.

Paragraph b, Surge Protection devices (SPD).

Note: see attached reference Manual UFGS 23 09 23.13 20 BACnet DDC System for HVAC, Para 2.4.2, Surge and Transient Protection

• Furnishing and installation of SPD type 1, 2 and 3, type “DEHN Red Line” or equal approved.

Qty: 12 Each

3. Bldg 1204 Heavy Drop facility.

Paragraph c, Modification of existing Air Handling Unit (AHU1) with new cooled water coil

• Cooling capacity of new cooled water coil is 21 KW.