SEE SCHEDULE ASHE 15-1063 & 1065

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this Amendment is to make changes as indicated below and in the follow ing pages:

- Section B/extended description of item 0001 and Section J/Attachment 1: Replace Technical Specif ications Revision #1 w ith Technical Specif ications Revision 2 for project ASHE 15-1063;

- Section L: Replace the Construction Cost Estimate Breakdow n w ith Construction Cost Estimate Breakdow n Revision 2 for project ASHE 15-1063;

- Section B/extended description of item 0002 and Section J/Attachment 2: Replace Technical Specif ications w ith Technical Specif ications Revision 1 for project ASHE 15-1065.

- Section L: Replace the Construction Cost Estimate Breakdow n w ith Construction Cost Estimate Breakdow n Revision 1 for project ASHE 15-1065;

1. CONTRACT ID CODE PAGE OF PAGES

J 1 10

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 20-Sep-2016

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA5682-16-R-0034

X 9B. DATED (SEE ITEM 11)

24-Aug-2016

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

20-Sep-2016

CODE

31 CONS LGC - FA5682

VIA PORDENONE 89/B, AREA "E" EDIF. 600

BASE AEREA DI AVIANO

AVIANO (PN) 33081

FA5682 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

FA5682-16-R-0034

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION A - SOLICITATION/CONTRACT FORM

The required response date/time has changed from 22-Sep-2016 04:00 PM to 26-Sep-2016 02:00 PM.

The offeror acceptance period has decreased by 4 from 8 to 4.

SECTION B - SUPPLIES OR SERVICES AND PRICES

CLIN 0001

The CLIN extended description has changed from:

THE CONTRACTOR SHALL FURNISH ALL LABOR, EQUIPMENT, MATERIALS, TRANSPORTATION,

SUPERVISION AND ANY OTHER NECESSARY WORK TO ACCOMPLISH THE PROJECT HEREIN

LISTED AT THE PRICE STATED BELOW AND STRICTLY IN ACCORDANCE WITH THE TERMS AND

CONDITIONS OF THIS CONTRACT INCLUDING THE FOLLOWING ATTACHED DOCUMENTS LISTED

IN SECTION J HEREIN: TECHNICAL SPECIFICATIONS FOR PROJECT ASHE 15-1063 SUSTAIN HVAC SYSTEM, BLDG 1173, AREA F, AVIANO AB, ITALY, REVISION #1 DATED JULY 2016 AND MARKED

TECHNICAL SPECIFICATIONS REVISION #1- 8 WRITTEN PAGES INCLUDING COVER PAGE AND

SCHEME B. ADDITIONAL REQUIREMENTS DATED 12 AUG 2016 - 4 WRITTEN PAGES

To:

THE CONTRACTOR SHALL FURNISH ALL LABOR, EQUIPMENT, MATERIALS, TRANSPORTATION,

SUPERVISION AND ANY OTHER NECESSARY WORK TO ACCOMPLISH THE PROJECT HEREIN

LISTED AT THE PRICE STATED BELOW AND STRICTLY IN ACCORDANCE WITH THE TERMS AND

CONDITIONS OF THIS CONTRACT INCLUDING THE FOLLOWING ATTACHED DOCUMENTS LISTED

IN SECTION J HEREIN: TECHNICAL SPECIFICATIONS FOR PROJECT ASHE 15-1063 SUSTAIN HVAC

SYSTEM, BLDG 1173, AREA F, AVIANO AB, ITALY, REVISION 2 DATED SEPTEMBER 2016 AND

MARKED TECHNICAL SPECIFICATIONS REVISION 2- 10 WRITTEN PAGES INCLUDING COVER PAGE, LAYOUT, DIAGRAM AND SCHEDULE OF MATERIALS SUBMITTALS B. ADDITIONAL

REQUIREMENTS DATED 12 AUG 2016 - 4 WRITTEN PAGES.

CLIN 0002

The CLIN extended description has changed from:

THE CONTRACTOR SHALL FURNISH ALL LABOR, EQUIPMENT, MATERIALS, TRANSPORTATION,

SUPERVISION AND ANY OTHER NECESSARY WORK TO ACCOMPLISH THE PROJECT HEREIN

LISTED AT THE PRICE STATED BELOW AND STRICTLY IN ACCORDANCE WITH THE TERMS AND

CONDITIONS OF THIS CONTRACT INCLUDING THE FOLLOWING ATTACHED DOCUMENTS:A.

TECHNICAL SPECIFICATIONS FOR ASHE 15-1065 SUSTAIN HVAC FAC. 1472, AREA F, AVIANO AB, ITALY, DATED JULY 2016 AND MARKED TECHNICAL SPECIFICATIONS- 7 WRITTEN PAGES

INCLUDING COVER PAGE AND DRAWINGS B. ADDITIONAL REQUIREMENTS DATED 12 AUG 2016 - 4

WRITTEN PAGES

To:

THE CONTRACTOR SHALL FURNISH ALL LABOR, EQUIPMENT, MATERIALS, TRANSPORTATION,

SUPERVISION AND ANY OTHER NECESSARY WORK TO ACCOMPLISH THE PROJECT HEREIN

LISTED AT THE PRICE STATED BELOW AND STRICTLY IN ACCORDANCE WITH THE TERMS AND

CONDITIONS OF THIS CONTRACT INCLUDING THE FOLLOWING ATTACHED DOCUMENTS:A.

TECHNICAL SPECIFICATIONS FOR ASHE 15-1065 SUSTAIN HVAC FAC. 1472, AREA F, AVIANO AB, ITALY, REVISION 1 DATED SEPTEMBER 2016 AND MARKED TECHNICAL SPECIFICATIONS

REVISION 1- 8 WRITTEN PAGES INCLUDING COVER PAGE, LAYOUTS AND SCHEDULE OF

MATERIALS SUBMITTALS B. ADDITIONAL REQUIREMENTS DATED 12 AUG 2016 - 4 WRITTEN

PAGES.

SECTION F - DELIVERIES OR PERFORMANCE

The following have been added by full text:

The Contractor MAY perform both projects, ASHE 15-1063 and ASHE 15-1065, simultaneously.

SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

The following have been modified:

LIST OF ATTACHMENTS – CONSTRUCTION CONTRACTS

The following documents are attachments to this document and are an integral part hereof:

a. Attachment 1:

Technical Specifications ASHE 15-1063 Sustain HVAC System, Bldg 1173, Area F, Aviano AB, Italy, Revision 2 dated September 2016 and marked Technical Specifications Revision 2

- 10 written pages including cover page, layout, diagram and Schedule of Material Submittals

b. Attachment 2:

Technical Specifications for ASHE 15-1065 Sustain HVAC Fac. 1472, Area F, Aviano AB, Italy Revision 1 dated Septemebr 2016 and marked Technical Specifications Revision 1

- 8 written pages including cover page, layouts and Schedule of Material Submittals

c. Attachment 3:

Additional Requirements, dated 12 August 2016, 4 pages

d. Attachment 4:

Master Technical Specifications for Construction Projects Aviano Air Base, Aviano, Italy, dated November

SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS

L-01 PROPOSAL PREPARATION INSTRUCTIONS

A. To assure timely and equitable evaluation of proposals, offerors must follow the instructions contained herein.

Offerors are required to meet all solicitation requirements, including terms and conditions, representations and certifications, and technical requirements, in addition to those identified as evaluation factors or subfactors.

Offerors must clearly identify any exception to the solicitation terms and conditions and provide complete accompanying rationale. The response shall consist of three (3) separate parts; Part I - Price Proposal, Part II - Technical Proposal, and Part III - Past Performance Information.

B. The contracting officer has determined there is a high probability of adequate price competition in this acquisition. Upon examination of the initial offers, the contracting officer will review this determination and if, in the contracting officer's opinion, adequate price competition exists no additional data will be requested and certification under FAR 15.406-2 will not be required. However, if at any time during this competition the contracting officer determines that adequate price competition no longer exists; offerors may be required to submit cost data to the extent necessary for the contracting officer to determine the reasonableness and affordability of the price.

C. Specific Instructions:

1. PART I – PRICE PROPOSAL - Submit original only

(a) Complete blocks 14, 15, 16, 19 (only if amendments are issued) and 20A through 20C of the RFP Section A, SF1442 In doing so, the offeror accedes to the contract terms and conditions as written in the RFP Sections A through K. These sections constitute the model contract.

(b) Insert proposed unit and extended prices in Section B for each Contract Line Item Number (CLIN) using the amount resulting from the completion of the Construction Cost Estimate breakdown forms, for project ASHE 15-1063 Revision 2 and for project ASHE 15-1065 Revision 1. The extended amount must equal the whole Euro unit price multiplied by the number of units.

(c) Complete the necessary fill-ins and certifications in Sections I through K, including Section J Attachment 3 “Additional Requirements”.

(d) The entire solicitation Sections A through M as well as the forms Construction Cost Estimate Breakdown, for project ASHE 15-1063 Revision 2 and for project ASHE 15-1065 Revision 1, shall be returned in their entirety.

2. PART II – TECHNICAL PROPOSAL - Limited to no more than 40 pages (excluding Government released documents which are not subject to any page limitation restriction). Submit original only.

(a) Subfactor1 – Qualification Certification: Submit current SOA certification for category OG11 and/or OS28 and classification adequate to cover offeror’s proposed amount for project performance.

(b) Subfactor 2 - Experience: Submit offeror’s experience with the same work/trades and complexity as the instant requirement. The offeror must submit evidence of at least two (2) contracts performed within the last five (5) years from the date of proposal that involved substantially the same work/trades and complexity as the instant requirement.

(c) Subfactor 3 – Legal Standing: Submit documentation that satisfies offeror capacity to comply with law requirements concerning payments and social insurance requirements: the acceptable documentation is represented by a copy of the “Documento Unico di Regolarita’ Contributiva (DURC)” for personnel (direct hire and/or self employed/subcontractors). This document must not be older than 120 calendar days from the date of the offer.

https://cs.eis.af.mil/airforcecontracting/knowledge_center/Documents/AFFARS_Library/5315/templates/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.Outlook/far/FAR15.DOC#b154062 http://www.gsa.gov/Portal/gsa/ep/formslibrary.do?viewType=DETAIL&formId=4E179AB32AF6652285256A260054D101

3. PART III – PAST PERFORMANCE INFORMATION - Limited to no more than 20 pages per contract listed. Only references for relevant past efforts/contracts are desired. Submit original only.

(a) Quality and Satisfaction Rating for Contracts Completed in the Past Five Years: Provide any information currently available (letters, metrics, customer surveys, independent surveys, etc.) which demonstrates customer satisfaction with overall job performance and quality of completed product for relevant past efforts/contracts (similar in scope and magnitude of effort and complexities this solicitation requires). In addition, explain corrective actions taken in the past, if any, for substandard performance and any current performance problems such as cost overruns, extended performance periods, numerous warranty calls, etc.

(b) Performance Surveys: The government will evaluate the quality and extent of offeror's performance deemed relevant to the requirements of this RFP. The government will use information submitted by the offeror and any other sources of information available to the Government to assess past performance. Provide a list of no more than TWO (2), of the most relevant contracts performed for Federal agencies and commercial customers within the last five (5) years. Relevant contracts include all projects performed for this type of work (SOA category OG11 and/or OS28) and magnitude of work performance. The evaluation of past performance information will not take into account past performance information regarding predecessor companies, key personnel who have relevant experience, or subcontractors that will perform major or critical aspects of the requirement when such information is relevant to the instant acquisition. Furnish the following information for each contract listed:

(i) Company/Division name

(ii) Product/Service

(iii) Contracting Agency/Customer

(iv) Contract Number

(iv) Contract Euro Value

(v) Period of Performance

(vii) Verified, up-to-date name, address, FAX & telephone number of the contracting officer

(viii) Comments regarding compliance with contract terms and conditions

(ix) Comments regarding any known performance deemed unacceptable to the customer, or not in accordance with the contract terms and conditions.

If a teaming arrangement is contemplated, provide complete information as to the arrangement, including any relevant and recent past performance information on previous teaming arrangements with same partner. If this is a first time joint effort, each party to the arrangement must provide a list of past relevant contracts.

(c) Subcontractor Consent: Past performance information pertaining to a subcontractor cannot be disclosed to the prime offeror without the subcontractor’s consent. Provide with the proposal a letter from all subcontractors that will perform major or critical aspects of the requirement, consenting to the release of their past performance information to the prime contractor.

D. Documents submitted in response to this RFP must be fully responsive to and consistent with the following:

1. Requirements of the RFP (CLINs & Technical Specifications) and government standards and regulations pertaining to the Technical Specifications.

2. Evaluation Factors for Award in Section M of this RFP.

3. Any limitation on the number of proposal pages. Pages exceeding the page limitations set forth in this

Section L will not be read or evaluated, and will be removed from the proposal.

4. Format for proposal Parts II and III shall be as follows:

(a) The proposals will be no bigger than A4 size paper except for fold-outs used for charts, tables, or diagrams, which may not exceed A3 size paper.

(b) A page is defined as one face of a sheet of paper containing information.

(c) Typing shall not be less than 12 pitch.

(d) Elaborate formats, bindings or color presentations are not desired or required.

52.215-20 REQUIREMENTS FOR CERTIFIED COST OR PRICING DATA OR INFORMATION OTHER

THAN CERTIFIED COST OR PRICING DATA (OCT 2010)—ALTERNATE IV (OCT 2010)

(a) Submission of certified cost or pricing data is not required.

(b) Provide data described below: COMPLETED CONSTRUCTION COST ESTIMATE BREAKDOWN FORMS.

(End of provision)

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a FIRM FIXED PRICE contract resulting from this solicitation.

(End of provision)

SECTION M - EVALUATION FACTORS FOR AWARD

Section M - Evaluation Factors for Award

M001. SOURCE SELECTION

a. Basis for Contract Award This is a Lowest Price Technically Acceptable (LPTA) source selection conducted in accordance with Federal Acquisition Regulation (FAR) 15, Contracting by Negotiation, as supplemented by the Defense Federal Acquisition Regulation Supplement (DFARS), the Air Force Federal Acquisition Regulation Supplement (AFFARS), DoD Source Selection Procedures, Appendix A, 04 March 2011 and Air Force Mandatory Procedures 5315.3 17 May 2016. These regulations are available electronically at the Air Force (AF) FARSite, http://farsite.hill.af.mil. The Government will select the proposal with the lowest evaluated price from among those meeting the acceptability standards for non-price factors. Contract(s) may be awarded to the offeror who is deemed responsible in accordance with the FAR Part 9.1, as supplemented, whose proposal conforms to the solicitation’s requirements (to include all stated terms, conditions, representations, certifications, and all other information required by Section L of this solicitation) and is judged, based on the evaluation factors and subfactors, to represent the lowest price technically acceptable proposal. While the Government will strive for maximum objectivity, the source selection process, by its nature, is subjective; and therefore, professional judgment is implicit throughout the entire process.

b. Number of Contracts to be Awarded The Government intends to award one contract for the performance of projects ASHE 15-1063 Sustain HVAC Fac.

1173, Area F, Aviano AB, Italy, Revision 2 & ASHE 15-1065 Sustain HVAC Fac. 1472, Area F, Aviano AB, Italy Revision 1.

c. Discussions If, during the evaluation period, it is determined to be in the best interest of the Government to hold discussions, offeror responses to Evaluation Notices (ENs) and the Final Proposal Revision (FPR) will be considered in making the source selection decision. If the offeror’s proposal has been evaluated as acceptable at the time discussions are closed, any changes or exceptions in the Final Proposal Revision are subject to evaluation and may introduce risk that the offeror’s proposal be determined unacceptable and ineligible for award.

d. Solicitation Requirements, Terms and Conditions Offerors are required to meet all solicitation requirements, such as terms and conditions, representations and certifications, and technical requirements, in addition to those identified as factors or subfactors. Failure to comply with the terms and conditions of the solicitation may result in the offeror being ineligible for award. Offerors must clearly identify any exception to the solicitation terms and conditions and must provide complete supporting rationale. The Government reserves the right to determine any such exceptions unacceptable.

M002 EVALUATION FACTORS

a. Evaluation Factors and Subfactors The following evaluation factors and subfactors will be used to evaluate each proposal. The Government will evaluate proposals for acceptability, but will not rank the proposals by the non-price factors or subfactors.

Factor 1: Technical Subfactor 1: Qualification certification Subfactor 2: Experience Subfactor 3: Legal Standing

Factor 2: Past Performance Factor 3: Price

b. Technical Factor The Government’s technical evaluation team shall evaluate the technical proposals on an acceptable or unacceptable basis, assigning one of the ratings described below for each subfactor. Any subfactor evaluated as “Unacceptable” will render the entire proposal unacceptable and, therefore, unawardable. Only those proposals determined to be technically acceptable, either initially or as a result of discussions, will be considered for award. However, the offeror is reminded that the Government reserves the right to award this effort based on the initial proposal, as received, without discussion.

The proposals shall be evaluated against the following technical subfactors:

Subfactor 1: Qualification certification Description: This subfactor evaluates offeror’s SOA certification for category OG11 and/or OS28 and classification adequate to cover offeror’s proposed amount for project performance.

Measure of Merit: This requirement is met when the offeror’s proposal provides a copy of a current SOA certification for category OG11 and/or OS28 and classification adequate to cover offeror’s proposed amount for project performance.

Subfactor 2: Experience

TABLE 1 - TECHNICAL RATINGS

Rating Description

Acceptable Proposal clearly meets the minimum requirements of the solicitation.

Unacceptable Proposal does not clearly meet the minimum requirements of the solicitation.

Description: This subfactor evaluates offeror’s experience with the same work/trades and complexity as the instant requirement.

Measure of Merit: This requirement is met when the offeror’s proposal includes evidence of at least two

(2) contracts performed within the last five (5) years from the date of proposal that involved substantially the same work/trades and complexity as the instant requirement. Contractor shall demonstrate to have successfully performed architectural/civil works and/or mechanical works having similar characteristics of the present project.

Subfactor 3: Legal Standing Description: This subfactor evaluates offerors capacity to comply with law requirements concerning payments and social insurance requirements.

Measure of Merit: This requirement is met when the offeror’s proposal includes a copy of the “Documento Unico di Regolarita’ Contributiva (DURC)” for personnel (direct hire and/or self-employed/subcontractors). This document must not be older than 120 calendar days from the date of the offer.

c. Past Performance Factor The Past Performance evaluation results in an assessment of the offeror’s probability of meeting the solicitation requirements. Offerors must receive a past performance rating of “Acceptable” to be eligible for award. Only the past performance effort which is related to the work the offeror is proposing to perform will contribute to the confidence assessment

(1) Ratings. The Past Performance factor will receive one of the ratings described below.

(2) Evaluation Process. The past performance evaluation considers each offeror’s demonstrated recent and relevant record of performance in supplying products and services that meet the solicitation requirements. In conducting the Past Performance evaluation, the Government reserves the right to use both the information provided in the offeror’s Past Performance proposal volume and information obtained from other sources available to the Government, to include, but not limited to: the Past Performance Information Retrieval System (PPIRS); Federal Awardee Performance and Integrity Information System (FAPIIS); Electronic Subcontract Reporting System (eSRS), or other databases; and interviews/questionnaires with Program Managers, Contracting Officers and Fee Determining Officials, the Defense Contract Management Agency (DCMA), and commercial sources.

(i) Recency Assessment

TABLE 2- PAST PERFORMANCE EVALUATION RATINGS

Rating Description

Acceptable

Based on the offeror’s performance record, the Government has a reasonable expectation that the offeror will successfully perform the required effort, or the offeror’s performance record is unknown. (Only the past performance effort which is related to the work the offeror is proposing to perform will contribute to the confidence assessment See note below.)

Unacceptable Based on the offeror’s performance record, the Government has no reasonable expectation that the offeror will be able to successfully perform the required effort.

Note: In the case of an offeror without a record of relevant past performance or for whom information on past performance is not available or so sparse that no meaningful past performance rating can be reasonably assigned, the offeror may not be evaluated favorably or unfavorably on past performance (see FAR 15.305(a)(2)(iv)).

Therefore, the offeror shall be determined to have unknown past performance. In the context of acceptability/unacceptability, “unknown” shall be considered “acceptable.”

An assessment of the past performance information will be made to determine if it is recent. To be recent, the effort must be ongoing or must have been performed during the past five (5) years from the date of issuance of this solicitation. Past performance information that fails this condition will not be evaluated.

(ii) Relevancy Assessment The Government will conduct an evaluation of all recent performance information obtained to determine whether the products provided/services performed under those contracts relate to the Technical subfactors and Price factor.

For each recent past performance citation reviewed, the relevance of the work performed will generally be assessed for the Technical subfactors and Price Factor (however, all aspects of performance that relate to this acquisition may be considered). Consideration will be given to all projects performed for this type of work (SOA category OG11 and/or OS28) and magnitude of work performance. A relevancy determination of the offeror’s past performance will be made based upon the aforementioned considerations, including joint venture partner(s) and major and critical subcontractor(s). In determining the relevancy of effort performed under individual past performance contracts, the government will only consider the specific effort or portion consistent with that proposed by the prime, subcontractor or teaming partner. The past performance information forms (PIFs) and information obtained from other sources will be used to establish the relevancy of past performance. The Government will use the following relevancy definitions when assessing recent, relevant contracts:

TABLE 3 – PAST PERFORMANCE RELEVANCY RATINGS

Rating Definition

RELEVANT Present/past performance effort involved similar scope and magnitude of effort and complexities this solicitation requires.

NOT RELEVANT Present/past performance effort involved little or none of the scope and magnitude of effort and complexities this solicitation requires.

(iii) Performance Quality Assessment The Government will consider the performance quality of recent, relevant efforts (how well the contractor performed on the contracts). For each recent, relevant past performance citation reviewed, the performance quality of the work performed will be assessed for the Technical subfactors and Price Factor (however, all aspects of performance that relate to this acquisition may be considered). The quality assessment may result in positive or adverse findings. Adverse is defined as past performance information that supports an unsatisfactory rating on any evaluation element or any unfavorable comment received from sources without a formal rating system. For adverse information identified, the evaluation will consider the number and severity of the problem(s), mitigating circumstances, and the effectiveness of corrective actions that have resulted in sustained improvements. Process changes will only be considered when objectively measurable improvements in performance have been demonstrated. The Government will use the following quality levels when assessing recent, relevant efforts:

TABLE 4 – PAST PERFORMANCE QUALITY ASSESSMENT

Quality Assessment/Color Description

SATISFACTORY (S)/GREEN During the contract period, contractor performance is substantially meeting (or substantially met) contract requirements. For any problems encountered, contractor took effective corrective action.

UNSATISFACTORY(U)/RED During the contract period, contractor performance is not meeting (or did not meet) some contract requirements. For problems encountered, corrective action appeared only marginally effective, not effective, or not fully implemented. Customer involvement was required.

NOT AVAILABLE(N)/WHITE Quality and/or performance information is not available.

(3) Assigning Ratings. As a result of the relevancy and performance quality assessments of the recent contracts evaluated, offerors will receive an integrated past performance rating at the factor level (see Table 2).

More recent performance will have a greater impact on the Past Performance rating than less recent effort.

d. Price Factor Offerors whose price is determined to be unreasonable, unbalanced, or unaffordable may not be considered for award.

(1) The offeror’s Price proposal will be evaluated for award purposes, based upon the total price proposed for basic requirements.

(2) Unbalanced Pricing: The Government will analyze proposals to determine whether they are unbalanced with respect to prices, and separately priced line items in accordance with FAR 15.404-1. An offer may be rejected if the contracting officer determines that the lack of balance poses an unacceptable risk to the Government.

(3) Affordability: The Government will evaluate whether each offeror’s Cost/Price proposal is affordable by comparing the total proposed price to the budgetary information included in the solicitation. The evaluation shall be made on the basis of a comparison between the total price and the total budgetary information included in the solicitation.

(End of Summary of Changes)

M001. SOURCE SELECTION
a. Basis for Contract Award
b. Number of Contracts to be Awarded
c. Discussions
d. Solicitation Requirements, Terms and Conditions
M002 EVALUATION FACTORS
a. Evaluation Factors and Subfactors
b. Technical Factor
c. Past Performance Factor
d. Price Factor