SCHEDULE OF MATERIAL SUBMITTALS
View the file
Other files
| File | Type | Posted |
|---|---|---|
| ASJJ_16-1028_SOW_Revision_2_08_Jul_2016.pdf | ||
| AMENDMENT_FA5682-16-R-0016-0001.pdf | ||
| ADDITIONAL_REQUIREMENTS_29_JUNE_2016.doc | DOC document | |
| ASJJ_16-1028_SOW_REVISION__1.pdf | ||
| FA5682-16-R-0016.pdf | ||
| bldg407_Fancoils FA_autocad.pdf | ||
| ASJJ_16-1028_BLANK_Construction_Cost_Estimate.xlsx | XLSX spreadsheet | |
| ASJJ_16-1028_SOW_20_June_2016.doc | DOC document | |
| bldg407_Fancoils FA_autocad.pdf | ||
| ASJJ_16-1028_SCHEDULE_OF_MATERIAL_SUBMITTALS.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Material Submittals Schedule
| SCHEDULE OF MATERIAL SUBMITTALS | PROJECT NUMBER | PROJECT TITLE | SOLICITATION / CONTRACT NO. | ||||||||||||||
| ASJJ 16-1028 | SUSTAIN HVAC AND FIRE ALARM SYS bldg 407 BLDG 600 | ||||||||||||||||
| (To be completed by Project Architect or Engineer) | |||||||||||||||||
| NUMBER OF COPIES REQUIRED | |||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | DESIGN | SAMPLES | COLOR SELECTION | MANUFACTURER'S RECOMMENDATION | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | SCHEDULES, LISTINGS, REPORTS, PLANS | TECHNICAL DATA | TEST REPORTS | FIELD REPORTS | REQUIRED SUBMISSION DATE |
fergusog: Enter the due date from the Contractor (MM/DD/YY)
DATE RECEIVED IN CONTRACTING
fergusog: Enter the date received from the Contractor. (MM/DD/YY)
DATE TO CIVIL ENGINEERING
fergusog: Enter the date submittal was given to CE for review. (MM/DD/YY)
RETURN SUSPENSE DATE
fergusog: Enter the date the submittal is due back from CE
(MM/DD/YY)
SUBMITTAL NUMBERS
fergusog: Enter the Submittal Number
DATE CONTRACTOR NOTIFIED CONTRACTOR RESUBMITTAL
fergusog: Enter Resubmittal Number
FINAL APPROVAL
fergusog: Enter the submittal final approval date
(MM/DD/YY)
REMARKS
fergusog: Enter any comments pertaining to the submittal
APPROVED
fergusog: Enter date the Contractor was notified of submittal approval
(MM/DD/YY)
fergusog: Enter Resubmittal Number
DISAPPROVED
fergusog: Enter date the Contractor was notified of submittal disapproval
(MM/DD/YY)
fergusog: Enter the submittal final approval date
(MM/DD/YY)
fergusog: Enter any comments pertaining to the submittal
| BOILER & VENTILATION RMs | ||||||||
| 1 | 3.3 ELECT. DISTR. PANEL boiler room | 3 | 3 | 30 | ||||
| 2 | 3.4 BOILER | 3 | 3 | 3 | 30 | |||
| 3 | 3.5 PUMPS | 3 | 3 | 30 | ||||
| 4 | 3.6 SCHEMATIC OF CIRCUIT boiler rm | 3 | 3 | 30 | ||||
| 5 | 3.8 INVERTERS Ventilation rm | 3 | 3 | 3 | 30 | |||
| 6 | 3.9 FAN COIL | 3 | 3 | 3 | 30 | |||
| FIRE DETECTION SYSTEM | ||||||||
| 7 | 4.1 - 4.6 DESIGN PHASE | 3 | 3 | 3 | 3 | 3 | 30 | |
| 8 | 5.0 FIRE ALARM PANEL | 3 | 3 | 3 | 30 | |||
| 9 | 5.0 ADDITIONAL 24v TRANSFORMERS | 3 | 3 | 3 | 30 | |||
| 10 | 5.0 GALVAN. STEEL PIPE | 3 | 3 | 30 | ||||
| 11 | 5.0 WIRE 2X1.5 | 3 | 3 | 30 | ||||
| 12 | 5.0 SMOKE DETECTOR | 3 | 3 | 30 | ||||
| 13 | 5.0 OPT.ACOUST. REPEATER | 3 | 3 | 30 | ||||
| 14 | 5.0 HEAT DETECTOR | 3 | 3 | 30 | ||||
| 15 | 5.0 MANUAL PULL BOX | 3 | 3 | 30 | ||||
| 16 | 5.0 SMOKE DETECT. AIR DUCT | 3 | 3 | 30 | ||||
| 17 | OPT.ACOUST. 97dB SIREN | 3 | 3 | 30 |
| 1 |
| 2 |
| 3 |
| 4 |
| 5 |
| 6 |
| 7 |
| 8 |
| 9 |
| 10 |
| 11 |
| 12 |
Schedule of Material Submittals Template, Feb 05 (SAF/AQCP)
File details come from the government source that posted it. Updated .