About this file

Project ASHE 13-1020_Addendum 2

View the file

Other files

File Type Posted
Solicitation_FA5682-15-R-0010_Amendment_0001.doc DOC document
SF_1442_ADDITIONAL_REQUIREMENTS_June_2015.doc DOC document
Solicitation_FA5682-15-R-0010_(Repair_Storm_Water_Run-Off_Fac._1010).doc DOC document
ASHE_13-1020_Addendum__1.doc DOC document
ASHE_13-1020_100__dwgs.pdf PDF
Master_Technical_Specifications.zip ZIP file
ASHE_13-1020_100__Specs_Eng.PDF PDF
ASHE_13-1020_Const_Cost_Estimate.xls XLS spreadsheet

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT ASHE 13-1020

UPGRADE STORM WATER RUN-OFF SYSTEM

AT NORTH MAINTENANCE FAC. 1010, AREA F

AVIANO AIR BASE

AVIANO, ITALY

ADDENDUM # 2

SECTION AC1 – SCOPE OF PROJECT AND APPLICABLE CONDITIONS

· AC1-03 Submittal of Materials. Master Specification number is hereby changed to read 01100 (not 01100/R).

· AC1-10 Work Site Conditions

Paragraph a. Content is hereby changed to read: “Work areas: Project area is the North Maintenance Area, a surface of about 32,400 sq.m. including Fac. 1010 (Base’s main vehicle maintenance shop), Fac. 1046 (Power production/barrier maintenance), Fac. 1036 (Heavy equipment horizontal and wide thruway/parking area southwest of facility), Fac. 1032 (HAZMART) and Fac. 1035 (Hazardous Material Storage BSE)”.

Paragraph b. Content is hereby changed to read: “Not Applicable”.

· AC1-11 Airfield Safety Training. Content is hereby changed to read: “Not Applicable”.

· AC1-20 Procedures and Work Phases. Content is hereby changed to read: “Prior to starting any work the Contractor shall submit a Work Plan for approval by the Contracting Officer. At least three work phases will be identified through coordination with Facility Managers and 31st CES personnel”.

SCHEDULE OF WORK ITEMS, A – STORM WATER DRAINAGE NETWORK – NEW WORKS

PART IIA – Civil Works

· Item 12. The following is hereby added: “As-Built drawings shall be geo-referenced”.

SCHEDULE OF WORK ITEMS, C – DRAINAGE FIELDS – DEMOLITION WORKS

PART IC – Demolitions

· Item 3. 7th dash is hereby changed to read: “Remediation of contaminated soil (maximum 2m³ for each drywell)”.

· Item 4. 4th dash is hereby changed to read: “Remediation of contaminated soil (maximum 6m³ for each oil water separator)”.

Project # ASHE 13-1020

Addendum #2 DATE: July 2015