ASHE_13-1020_Addendum__2.doc
DOC document 35 KB Posted
- Solicitation number
- FA5682-15-R-0010
About this file
Project ASHE 13-1020_Addendum 2
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation_FA5682-15-R-0010_Amendment_0001.doc | DOC document | |
| SF_1442_ADDITIONAL_REQUIREMENTS_June_2015.doc | DOC document | |
| Solicitation_FA5682-15-R-0010_(Repair_Storm_Water_Run-Off_Fac._1010).doc | DOC document | |
| ASHE_13-1020_Addendum__1.doc | DOC document | |
| ASHE_13-1020_100__dwgs.pdf | ||
| Master_Technical_Specifications.zip | ZIP file | |
| ASHE_13-1020_100__Specs_Eng.PDF | ||
| ASHE_13-1020_Const_Cost_Estimate.xls | XLS spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT ASHE 13-1020
UPGRADE STORM WATER RUN-OFF SYSTEM
AT NORTH MAINTENANCE FAC. 1010, AREA F
AVIANO AIR BASE
AVIANO, ITALY
ADDENDUM # 2
SECTION AC1 – SCOPE OF PROJECT AND APPLICABLE CONDITIONS
· AC1-03 Submittal of Materials. Master Specification number is hereby changed to read 01100 (not 01100/R).
· AC1-10 Work Site Conditions
Paragraph a. Content is hereby changed to read: “Work areas: Project area is the North Maintenance Area, a surface of about 32,400 sq.m. including Fac. 1010 (Base’s main vehicle maintenance shop), Fac. 1046 (Power production/barrier maintenance), Fac. 1036 (Heavy equipment horizontal and wide thruway/parking area southwest of facility), Fac. 1032 (HAZMART) and Fac. 1035 (Hazardous Material Storage BSE)”.
Paragraph b. Content is hereby changed to read: “Not Applicable”.
· AC1-11 Airfield Safety Training. Content is hereby changed to read: “Not Applicable”.
· AC1-20 Procedures and Work Phases. Content is hereby changed to read: “Prior to starting any work the Contractor shall submit a Work Plan for approval by the Contracting Officer. At least three work phases will be identified through coordination with Facility Managers and 31st CES personnel”.
SCHEDULE OF WORK ITEMS, A – STORM WATER DRAINAGE NETWORK – NEW WORKS
PART IIA – Civil Works
· Item 12. The following is hereby added: “As-Built drawings shall be geo-referenced”.
SCHEDULE OF WORK ITEMS, C – DRAINAGE FIELDS – DEMOLITION WORKS
PART IC – Demolitions
· Item 3. 7th dash is hereby changed to read: “Remediation of contaminated soil (maximum 2m³ for each drywell)”.
· Item 4. 4th dash is hereby changed to read: “Remediation of contaminated soil (maximum 6m³ for each oil water separator)”.
Project # ASHE 13-1020
Addendum #2 DATE: July 2015