This Statement of Work outlines warehouse relocation services required by the Department of the Air Force USAFE-AFAFRICA to move all items from Zemmer warehouse to Spangdahlem Air Base building 173. The scope includes relocating approximately 3,500 cubic meters (123,600 cubic feet) of materials, consisting of indoor items (forklifts, office furniture, shelves, workbenches, pallet jacks, and palletized items) and outdoor items (various sized forklifts, containers, large generators, aircraft palettes, barriers, and HUMVEEs).

The contractor must provide all labor, tools, parts, materials, and equipment, including a non-diesel powered forklift. Specialized tasks include disassembling and reinstalling both a Bruinzeel mobile shelving unit and a Viessmann walk-in refrigeration unit at the new location. Work must begin March 17, 2025, with operations restricted to Monday-Friday, 0730-1630. An Ozone Depleting Certification is required, and contractors must attend a mandatory site visit. Per the solicitation (FA560625Q2006), if contractors cannot meet the March 17 start date, they must propose their earliest possible start date, and site visit coordination is required by 0800 CET on February 20, 2025.

View the file

Other files for this federal contract opportunity

Other files attached to Zemmer Relocation, newest first.
File Type Posted
ZEMMER site visit questions_response.pdf PDF
SOW updated 24 FEB 25.pdf PDF
ZEMMER relo COMBO print 2.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Services Non-Personal: Contractor to provide all labor, tools, parts, materials, equipment, required to relocate all items from our Zemmer warehouse to Spangdahlem Air Base building 173.

Title of Project:

Relocate / move all items from Zemmer warehouse to Spangdahlem Air Base building 173.

Scope of Work:

1. All items located inside the warehouse (including forklifts, office furniture, shelves, workbenches, palett jacks, equipment items, and items on palettes) - about 1,800 cubic meters of volume = 63,600cubic feet.

2. All items located outside of the warehouse (including forklifts small and large, containers, large generators, aircraft palettes, barriers, HUMVEE’s, etc.) – about 1,700 cubic meters of volume = 60,000cubic feet.

3. Disassembling and re-installation of mobile shelving unit at the new location Made by: Bruinzeel storage systems. ( Rolling Shelves)

4. Disassembling and re-installation of walk-in refer unit at the new location Made by: Viessmann.

5. Provide non diesel-powered forklift to offload cargo move pallets inside the warehouse or to designated drop off area.

6. Move will need to begin 17 March 2025.

Work can only be performed during normal duty hours Monday – Friday 07:30 – 16:30.

Ozone Depleting Certification (ODC) required.

Mandatory site visit for bidders is required.