(Amend 0001) Attachment 1 - PWS 21 Aug 20.pdf

PDF 2 MB Posted

Attached to
Annual preventative Maintenance and Repair of Generator and ATS
Solicitation number
FA527020Q0028
Issued by

About this file

This performance work statement outlines annual preventative maintenance and inspection services required for generators, automatic transfer switches, and associated equipment at an Army installation in Okinawa, Japan. The contractor must provide corrosion control, develop preventative maintenance and inspection schedules, and submit annual maintenance reports. Specific tasks include annual inspections and preventative maintenance of 22 automatic transfer switches and four generator systems. The contractor must also perform on-site repairs and provide repair parts and supplies. The period of performance is one base year and four option years. The contractor must follow all applicable safety and technical standards and provide government-furnished property, equipment, and services as specified.

This federal contract opportunity posting seeks quotations for the annual preventative maintenance and repair of generators and automatic transfer switches for U.S. Army installations in Okinawa, Japan. The requirement is for a single-award requirements contract with a period of performance from September 2020 to August 2025. Interested parties should refer to SAM.gov to obtain the full request for quotation.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PERFORMANCE WORK STATEMENT (PWS)

Buckner Power Generation and Distribution Support

8-21-2020

Part 1

General Information

1. Description of Services: This is a services contract to provide annual preventative maintenance and inspection for the Foster Annex (Buckner) Generators, Automatic Transfer Switches (ATS) in support of the 78th Signal Battalion (78 SB) mission.

The contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform maintenance / inspections services of generators and ATSs for the 78 SB as defined in this Performance Work Statement

1.1. Background: The Buckner/Foster Annex communication site has a robust power distribution system that requires annual preventative maintenance and technical support to maintenance system integrity for the 78th Signals Critical facility. The 78 SB provides critical communication services to the US Army, Marine Corps, Navy and other agencies in Okinawa and mainland Japan in support of United States Forces Japan (USFJ).

1.2 Scope: Contractor provides a once a year maintenance / inspection on Generator and ATSs for the Buckner Communications site Okinawa. Services include preventative maintenance, routine maintenance. the contractor shall provide the commercial expertise, manpower and capabilities to maintain, install and modify mission support power equipment.

1.3 Quality Control Plan: Contractor will perform all maintenance per industry standards or manufactures standards/specifications. Such specification and standards will provide to government and Contracting Office to ensure maintenance is performed correctly. Contractor will be required to provide government a comprehensive maintenance report detailing all work performed, the results, recommended actions, current system health, and recommended equipment replacement for each and every piece of equipment worked on. The contractor shall develop and maintain an effective quality control program to ensure services are performed in accordance with this PWS. The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s quality control program is the means by which he assures himself that his work complies with the requirement of the contract. The QCP will be delivered within fifteen (30) days after contract award. Three

(3) copies of a comprehensive written QCP shall be submitted to the KO and COR within five (5) working days when changes are made thereafter. After acceptance of the quality control plan the contractor will receive the contracting officer’s acceptance in writing of any proposed change to his QC system.

1.4 Quality Assurance: The government will evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan. This plan is primarily focused on what the Government will do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).

1.4.1 Deficiencies: The Government reserves the right to refuse final acceptance until all deficiencies have been resolved (per all stated requirements). The Government will review all QA results and prepare a list of deficiencies, if any. The deficiency list shall include any problem(s) detected/identified during testing and/or inspections conducted by either the Contractor or the government, or both.

1.5 Period of Performance: The period of performance shall be for one (1) Base Year of twelve

(12) months and four (4) 12-month option years. The Period of Performance reads as follows:

Base Year 29 Sept 2020 thru 28 Sept 2021 Option Year I 29 Sept 2021 thru 28 Sept 2022 Option Year II Option Year III Option Year IV

29 Sept 2022 thru 29 Sept 2023 thru

28 Sept 2023 28 Sept 2024

1.6 General Information

1.6.1 Recognized Holidays:

New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Thanksgiving Day Independence Day Christmas Day

1.6.2. Hours of Operation: Generally, the contractors shall be conducting business between the hours of 0800hrs thru 1700hrs except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. However, Authorized Service Interruptions (ASIs) and service orders may require the contractor to perform work or reduce risk during nonstandard work hours, these hours will be coordinated with the COR prior to executing or servicing the order.

1.6.3. Place of Performance: The work to be performed under this contract shall be performed at Buckner Communications site.

78th Signal Battalion, UNIT 35152 Buckner Communication Site, FPO AP 96374-5152

Futenma, Ginowan-shi Okinawa, Japan 901-2317

1.6.4. Type of Contract: The government will award a requirements based contract.

1.6.5. Security Requirements. A secret-level security clearance is not required; however, the contractor is required to comply with the physical security as provided below.

Contractor and all associated sub-contractor’s employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office.

Contractors will provide a completed OMB 0703-0061, Company letter Memo for Pick up, and all require documents for background checks to the COR 45 prior to their visit. Please reach out to the COR for Samples/forms needed for the base access.

1.6.6. Contracting Officer Representative (COR). There will be 1-2 (CORs) will be assigned by separate letter. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is authorized to perform the following functions:

• Assure that the Contractor performs the technical requirements of the contract by performing required inspections in connection with contract performance.

• Maintain written and oral communications with the Contractor concerning technical aspects of the contract.

• Monitor Contractor's performance and notify both the Contracting Officer and Contractor of any deficiencies.

• Coordinate availability of government furnished property, and provide site entry of Contractor personnel.

A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.

1.6.7. Special Qualifications:

1.6.7.1. The prime contractor shall have a minimum of five (5) years of experience within the last ten (10) years in the maintenance and repair of Auxiliary Diesel Power Generation and Automatic transfer switches

1.6.7.2. Electricians, Technicians, and Engineers. Electricians, Technicians, and engineers shall have a minimum of three (3) years of professional work experience within the last five (5) years in the following fields:

• Generation Maintenance, repairs, and operations

• ATS Maintenance, repairs, and operations

• Electrical safety compliance

1.6.8 General Reporting and Responsibility:

Contractor will provide updates to any change in work scope as a result of new discoveries not know at the time this contract was written. All changed will be communicated to appropriate personnel as soon as a change is required.

Contractors will be responsible for any damages to equipment, property, and materials as a result of poor handling or improper work methods. Such damages are to be reported to appropriate personnel in a timely fashion.

Contractor shall document and log daily work completed and provide daily status reports to appropriate personnel.

1.7 Safety Requirements: In performing work under this contract, the contractor shall:

1.7.1 Conform to the safety requirements contained in the contract for all activities related to the accomplishment of the work.

1.7.2 Perform work in a safe manner as required by OSHA 2206, General Industry, Occupational Safety and Health Standards (29 CFR 1910) and Japan Environmental Governing Standards by U.S. Forces Japan.

1.7.3 Provide protection to government property in preventing damage during the period of time the property is under the control or in possession of the contractor.

1.7.4 Include a clause in all subcontractor’s contracts to require subcontractors to comply with the Safety provisions of this contract as applicable.

1.7.5 Report promptly (within one hour), 24 hours a day, seven (7) days a week, 365 days a year, to the Contracting Officer or COR, all available facts relating to each instance of damage to government property and/or injury to either contractor or government personnel.

1.7.6 In the event of an accident/mishap, take reasonable and prudent actions to establish control of the accident/mishap scene, prevent further injury to persons or property, and preserve evidence Until released by the accident/mishap investigative authority with the verbal and/or written concurrence of the Contract Officer.

1.7.7. If the government elects to conduct an investigation of the accident/mishap, cooperate fully and assist any government representative in the conduct of the investigation until the investigation is completed.

1.7.8. Include a clause in each applicable subcontract requiring the subcontractor’s cooperation and assistance with the accident reporting and investigation.

1.7.9. DA form 285, US Army Accident Report, shall be completed and submitted to HQs, 1st

Signal Brigade, and ATTN: NETC-SKC-SA, Unit #15271, and APO AP 96205-0044 within five (5) working days after the occurrence of the accident. All blocks of the report shall be completed to include the descriptive narrative. Cost of damage and/or injuries shall be included in the report.

1.8 Enforcing Safety Regulations.

1.8.1. Providing annual training to all personnel on the safe practices and skills to include First Aid and Cardio pulmonary Resuscitation (CPR).

1.8.2 Establishing a fire prevention program at each work site location and ensure each employee is familiar with operating fire suppression equipment.

1.8.3 Ensuring a bilingual (Japanese and English) Safety Standard Operating Procedures (SOP) is available at all operational work sites. Contract supervisors shall ensure that all personnel read and understand the Safety SOP.

1.8.4. Posting bilingual (Japanese and English) accident prevention signs and symbols at designated and known physical hazard areas. Reference DA PAM 385-10 for design specifications and safety color-coding.

1.8.5. All contractor personnel working in maintenance holes shall have a certificate of training for confined space entry and confined space rescue.

1.8.6. All contractor personnel performing direct labor for any delivery order shall have a valid Cardiopulmonary resuscitation (CPR) and First Aid certificate.

PART 2

DEFINITIONS & ACRONYMS

2. Definitions and Acronyms:

2.1. Definitions:

2.1.1. Contractor. A supplier or vendor having a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.

2.1.2. Contracting Officer. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note:

The only individual who can legally bind the government.

2.1.3. Contracting Officer's Representative (COR). An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment will be in writing and will state the scope of authority and limitations. This individual has authority to provide technical assistance to the Contractor as long as that assistance is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.4. Defective Service. A service output that does not meet the standard of performance associated with the Performance Work Statement.

2.1.5. Deliverable. Anything that can be physically delivered but may include non-physical things such as meeting minutes.

2.1.6. Quality Assurance. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.7. Quality Assurance Surveillance Plan (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.8. Quality Control. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

2.1.9. Subcontractor. One that enters into a contract with a prime contractor. The Government does not have private of contract with the subcontractor.

2.1.10. Work Day. The number of hours per day the Contractor provides services in accordance with the contract.

2.1.12. Work Week. Is defined as Monday through Friday, unless specified otherwise.

2.2. Acronyms:

ANSI American National Standards Institute ATS Automatic Transfer Switch AR Army Regulation CFR Code of Federal Regulations COR Contracting Officer Representative COTR Contracting Officer's Technical Representative DA Department of the Army DOD Department of Defense EM Engineering Manual FAR Federal Acquisition Regulation GFI Ground Fault Interrupt IEEE Institute of Electrical and Electronics Engineers KO Contracting Officer NEC National Electrical Code NEMA National Electrical Manufacturers Association NEMA MG National Electrical Manufacturers Association Motor and NFPA National Fire Protection Association OCI Organizational Conflict of Interest OCONUS Outside Continental United States (includes Alaska and Hawaii) OSHA Occupational Safety and Health Administration

PM Preventative Maintenance POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program TM Technical Manual

PART 3

GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES

3. GOVERNMENT FURNISHED ITEMS AND SERVICES: Not Applicable

PART 4

CONTRACTOR FURNISHED ITEMS AND SERVICES

4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:

4.1 General: The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this PWS.

4.2 Secret Facility Clearance: Not applicable.

4.3. Materials: Contractor will be responsible to supply/procure all materials needed to fulfill the Preventative maintenance tasks mention within section 5 of this PWS

4.4. Equipment: Contractor will supply all safety equipment, tools, repair equipment, and diagnostic equipment required to fulfill the all the tasks mention in section 5 of this contract.

PART 5

SPECIFIC TASKS

5 Specific Tasks.

5.1 Annual Maintenance/Inspection Report. The contractor shall provide a comprehensive report after annual maintenance is completed. The Report shall include all results of inspections, repairs, upgrades, lab results, modifications, testing, and all other work performed within this PWS. The annual report will be delivered to the COR electronically within 45 days after Annual inspections/maintenance has been completed.

Any emergent work performed will be captured under a separate report and will be delivered to the COR within 14 days after emergent work has been completed.

Annual report should include recommendations for future maintenance & equipment overhauls for each piece of equipment inspected. Those recommendations will NOT be funded or executed under this PWS. Recommendation will be reviewed by the COR and will be determined when/if they will be funded and perused by the Govt.

5.2 Work Schedule. Shall be coordinated with the COR. In general, should conform to government work days and hours, but certain work may require equipment outages which may only be approved on weekends and off hours. Such hour shall be work out with the COR.

5.3. Annual Preventive Maintenance Schedule. If travel is required, Contractor shall coordinate with COR prior to booking/reserving any travel, hotels, or rental cars to ensure the planned period to conduct Annual PMs will not conflict with current mission needs of the Buckner Communications site. U.S Government will not be responsible for travel costs if contractor fails to coordinate or contact COR prior booking.

To minimize operation disruptions at Buckner Communication site, contractors shall Provide a draft preventative maintenance schedule within 45 days or earlier to the COR prior to the first day of work starting to ensure the equipment is authorized to be taken down from site leadership.

5.3.1 Power Outages. All work will need to minimize site power outages.

Depending on the solution selected, temporary power feeds may need to be installed to accomplish this requirement. Outages should be kept to a minimum with a bulk of the work completed upfront (prep work) to lessen any downtime. When a power outage is required, the contractor will notify COR of anticipated power outages 45 days in advance as site personnel require 45 days to process requests for power outages.

5.4. National Electric Code (NEC) Compliance. All work should comply with National Fire Protection Association (NFPA) 70 and NEC 70E safety guidelines. If modifications are required to noncompliant equipment, that equipment will be reconfigured in accordance with National Fire Protection Association (NFPA) 70 2020.

5.5. Corrosion Control. During all installation, maintenance or troubleshooting of systems, items of equipment, and components. Contractor shall treat for corrosion, rusting, and other types of deterioration. Contractor shall ensure that corrosion controls are used on all affected surfaces to include, cleaning, priming, rust inhibitors, painting, sealing, and any other actions required to maintain surfaces in the original conditions as much as possible. When necessary, systems connected to the telecommunications systems such as corroded enclosures, buses, lugs, etc. can be replaced with new equipment to protect against corrosion and moisture.

5.6. Technical Note. Service and repair manuals may or may not exist in hard copy format. In required case, the contractor engage manufacturer to access versions of operator and service manuals, if available follow procedures outlined in PWS.

5.7. Deficiency Reporting. When equipment or systems defects are found, they shall be reported, in writing, to the designated Site/Facility Manager and COR within a work day.

5.8. Life Cycle Replacement and system equipment health. Contractors shall provide current health and replacement recommendations on all of the equipment’s they performed annual PMs on. This recommendation shall be captured in the comprehensive report so that COR can easily identify when certain equipment should be replaced in the future.

5.9. Annual ATS Maintenance.

5.9.1. During every Annual PM and Inspection, all ATSs will be inspected for proper functions. Proper connections, wire quality, controller functionality and shall have a PM conducted in accordance with manufacture recommendations.

Contractors will perform the following on all ATS on Buckner Communications Site:

• Inspect for Damage, Overheating, signs of arcing

• Inspect and testing of mechanical health

• Removal, inspection and testing of automatic portion of ATS and Lubricate as required

• Remove Phase Barriers/Arch Chutes and inspect

• Vacuum, brush and clean ATS and mitigate/repair corrosion per section 5.5

• Check Conductor Tightness

• Complete thermography Inspection under operational load

• Inspect Control Wiring

• Recommend replacement schedule

• Inspection of Main Contacts

• Inspection of Arcing Contact

• Inspections of Aux Contacts

• Inspection of Motors and Coils

• Inspection of Linkage, Mechanics

• Inspection/replacement of System Backup Battery

• Complete full functionality testing and operation

5.10 Annual Generator Maintenance

5.10.1. During every inspection/exercise, perform visual, operational checks, and PMs of the generators and all of its supporting components and equipment.

Contractors will perform but is not limited to the following on the four (4) 1MW Generators and all of their supporting components on Buckner Communications Site:

• Inspect for Damage, Overheating, signs of wear

• Inspection and testing of mechanical health

• Bearing, and other mechanical parts lubricates as required

• Vacuum, brush and clean, and mitigate/repair corrosion

• Check Conductor Tightness in generator housing

• Inspection of all conductors for brittle, cracked, or damaged wires/cables.

• Complete thermography Inspection under operational load

• Inspect Control Wiring

• Recommend replacement schedule

• Inspection of the air, and exhaust system

• Inspection of the Turbo systems

• Inspection of Generator windings

• Inspection of Stator

• Inspections of Aux and control Contacts

• Inspection of fuel pumps, alternators,

• Inspection for corrosion per section 5.5

• Inspection of System Battery

• Complete full functionality testing and operation

• Based on inspection results, provide recommendations of Overhauls and future maintenance requirements.

5.10.2. Review maintenance logs and log all alarm indications and warnings. Check the display panel for any abnormal functions of the system and remedy any issues.

5.10.3. Check for evidence of wet stacking or any other internal damages to the generator systems.

5.10.4. When present, check the generator service disconnect panel for any abnormal operations.

5.10.5. Inspections and tests must include those items contained in the manufacturer’s operational manual maintenance practices.

5.10.6. During every inspection/exercise, the air system including turbos will be inspected and maintained to determine proper air flow is available to both the engine intake and the exhaust systems and functioning properly. The air filter will be changed on schedule or if inspection determines it needs replaced based on manufacture guidance.

5.10.7. During the annual inspection/exercise, the fuel system (starting after the day tank) on each of the four (4) Generator/Motor sets including hoses, filters and pumps, will be thoroughly inspected and any damages/deficiencies reported to the COR.

5.10.8. During annual inspection/exercise, the generator starting system will be maintained and battery voltages will be measured and the battery health assessed. Battery chargers will be checked for proper functioning and setting. If no specific testing and inspections are prescribed for the batteries, then, measurements of cell voltage, specific gravity, cell temperature, sediment levels, electrolyte level and the torque settings on connecting cables and hold-down fixtures.

5.10.9. During annual inspection/exercise, the generator coolant and cooling system will be maintained in accordance with manufacture recommendations. System flushing/testing and coolant replacement should follow the manufacture schedule or sooner if an inspection determines replacement is required based on manufacture guidance.

5.10.10 During every annual inspection the generator(s) will include testing and diagnoses of the generator system health via manufactures and industries best practices.

Testing shall include insulation windings testing (meggering), exciter/alternator testing, Phase balancing, detailed thermography imaging of key generator components under at least 60% rated load, generator winding isolation testing, and generator stator inspections.

5.10.11 Annually contractor shall sample all generator fluids such as fuel, oil, and coolant for laboratory analysis on each of the 4 Generators sets. Laboratory testing of those fluids shall be completed by qualified laboratory. If laboratory results yield off-normal results, contractor will provide a recommended action plan. Results, recommended actions, and system health based fluid analysis results shall be including in the comprehensive report as mention in

5.11. Repair Parts and Supplies. All parts required in the performance of this contract will be provided by the contractor, with the governments consent. Parts shall be charged to approval parts CLIN. All repair parts shall have prior COR approval. U.S Government is not responsible for any payments if the contractor proceeds work without prior approval from the COR.

COR: Approval of total line item cost estimated below than Micro Purchase Threshold(MPT) in accordance with fiscal year yen rate. The contractor shall provide, in writing, a cost proposal to include a description of suggested repairs, parts required, labor costs, and method of repair to the COR. All parts shall include shipping cost. No overhead, general and administrative and profit shall be included for reimbursable items. Upon approval of cost estimate by the COR, the contractor shall perform the repair and make it fully operational. The COR shall notify to the CO at 18CONS of the approved cost estimate.CO: Approval of total line item cost estimated equal or above MPT in accordance with fiscal year yen rate. The contractor shall provide at least three quotes to the CO thru COR. The contractor shall provide, in writing, a cost proposal to include a description of suggested repairs, parts required, labor costs and method of repair to the CO at 18CONS. Upon approval of cost estimate by the CO, the contractor shall perform the repair and make it fully operational.

5.11.1. Unserviceable Parts. Unserviceable replaced parts will be disposed by the Contractor. For the items determined by the COR to have turn in value, these parts will be delivered to the Government by the Contractor as directed by the COR.

5.12. On-site Repairs.

5.12.1. The contractor shall respond within 24 hours of notification from COR for all on site repairs. Repairs include diagnose, repairs, temporary repairs, back to service testing, and coarse of actions.

5.12.2. The Contractor will be notified by the COR of the malfunctions and type of work required to include any special instructions or date deemed necessary for the required work.

PART 6

APPLICABLE PUBLICATIONS

6.0 Applicable Publications (Current Editions)

6.1. The Contractor shall abide by all applicable regulations, publications, manuals, and local policies and procedures.

Publications Title National Fire Protection Agency (NFPA) 70 National Electrical Code 2020 NFPA 70E Standard for Electrical Safety in the Workplace

Engineering Manual (EM) 385-l-1 Safety and Health Requirements Army Regulation (AR) 385-10 The Army Safety Program AR 200-1 Environmental Protection and Enhancement AR 385-40 Accident Reporting and Records Title 29 Code of Federal Regulations U.S. Department of Labor, Occupational Safety and Health Administration(OSHA)Standards

- Part 1926.62 For Construction

UFC 3-520-01 INTERIOR ELECTRICAL SYSTEMS

UFC 3-501-01 ELECTRICAL ENGINEERING

UFC 3-580-01 TELECOMMUNICATIONS INTERIOR

INFRASTRUCTURE PLANNING AND DESIGN

TM 5-692 Technical Manual- Maintenance of Mechanical and Electrical Equipment at Command, Control, Communications, Computers, Intelligence, Surveillance and Reconnaissance (C4ISR) Facilities April 2001

DISA Circular 350-195-2* Defense Information Systems Agency Circular 350-195-2 Tests and Evaluations of Auxiliary Electrical Power Systems

NETCOM Regulation 750 Battery Management Program

NETCOM Regulation 420-1 Site Power Coordinator Program

PART 7

ATTACHMENT/TECHNICAL EXHIBIT LISTING

7. Attachment/Technical Exhibit List:

7.1. Attachment 1/Technical Exhibit 1 – Deliverables Schedule

TECHNICAL EXHIBIT 1

DELIVERABLES SCHEDULE

Deliverable Frequency # of Copies Medium/Format Submit To Quality Control Plan (QCP).

PWS 1.3

Once a year Digital E-mail using MS Office Products

COR/KO

Preventive Maintenance Schedule. PWS 5.3

Once a Year Digital E-mail using MS Office Products

COR/KO

Annual Maintenance Report. PWS 5.1

Once a Year Digital E-mail using MS Office Products

COR/KO

7.2 Performance Requirements Summary

7.2.1. The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.

Performance Objective

PWS Paragraph Reference

Performance Threshold

PRS#1 Provide Corrosion Control for equipment serviced

(Ref: PWS para 5.5) Requirements shall be met for 100% of the equipment serviced

PRS#2 Preventative Maintenance Schedule

(Ref: PWS para 5.3) Preventative Maintenance schedule is delivered to COR 45 day in advance of work starting.

Must meet 100% of the time.

PRS#3 Annual Report (Ref: PWS para 5.1) Report delivered to COR within 45 days after Annual maintenance tasks have been completed.

Must meet 100% of the time exception will be made if waiting on Laboratory analysis results for complete reporting.

PRS#4 Annual inspection and preventative Maintenance of the (22) CAT ATS Units

(14) ATS600

(4) ATS1200

(2) ATS 1600

(Ref: PWS para 5.10) Annual inspections, annual preventative maintenance, and results of inspections/maintenance will be complete to 100%

PRS#5 Annual Inspection and preventative maintenance on four (4) CAT Generators systems

(Ref: PWS para 5.11) Annual inspections, annual preventative maintenance, and results of inspections/maintenance will be complete to 100%

PRS#6 Repair parts and supplies

(Ref: PWS para 5.11) 100% completion each time unless special or long lead order parts are needed to repair equipment.

PRS#6 On-site Repair

(Ref: PWS para 5.12) 100% completion each time unless equipment repairs are determined not of value by COR and Government pursues replacement by separate contract or service.

7.3 Equipment Listing.

7.3.1. Caterpillar Generator Sets Model 3508

Serial Numbers:

CNB01321

CNB01322

CNB01323

CNB01331

7.3.2. Automatic Transfer Switches:

Manufacturer Switch ID Ampere Rating Quantity

Caterpillar ATS600 600 14 Caterpillar ATS1200 1200 4 Caterpillar ATS1600 1600 2

8. Attachments and Documents

**Hard Copy of ATS Operations Manual Per request**

Pictures of the Equipment, ATS & Generator Motor Set

PWS Paragraph Reference