Construct Veterinarian Clinic Admin Annex Federal contract opportunity
Solicitation number
FA5270-17-B-0005
Issued by
Department of the Air Force Pacific Air Forces

About this file

Attachment 4 - OCR

View the file

Other files for this federal contract opportunity

Other files attached to Construct Veterinarian Clinic Admin Annex, newest first.
File Type Posted
Section-J_04_OCR_-_30_Aug_17.pdf PDF
FA5270-17-B-0005-0002.pdf PDF
FA5270-17-B-0005-0001.pdf PDF
Section-J_06_Soiling_Investigation_Report_Added_18_Jul_17.pdf PDF
Section-J_03_List_of_Drawings.pdf PDF
Section-J_05_LXEZ_11-8687_Drawings_Rev_18_Jul_17.pdf PDF
Section-J_02_AF_Form_66_27_Jan_17.pdf PDF
FA5270-17-B-0005_-_Construct_Vet_Clinic_Admin_Annex.pdf PDF
Section-J_01_Tech_Specs_Rev_18_Jul_17.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ATTACHMENT-4

OTHER CONTRACT REQUIREMENTS

Section J Attachment

Attachment 4

Other Contract Requirements:

OCR 1- PRE-FINAL AND FINAL INSPECTION

In accordance with FAR 52.211-10 (September 2000) the contractor is required to complete this project, ready for use, within the number of calendar days specified in the Task Order. To ensure adequate time to correct any deficiencies noted by the government during the final inspection, it is highly recommended that the contractor schedules such final inspection through the contract administrator at least seven (7) calendar days prior to the scheduled project completion date. The contractor is solely responsible for scheduling this inspection and is reminded that failure to complete the project ready for use in accordance with the contract terms and conditions may result in the assessment of liquidated damages as described in

FAR 52.211-12, Liquidated Damages - Construction. Occasionally, minor discrepancies may be detected during the final inspection that may be considered "punchlist" items. If only minor "punchlist" items are found, another inspection may not be required. However, all punchlist items must be corrected by the contractor, and verified by the project inspector, prior to expiration of the contract period unless otherwise authorized in writing by the contracting officer. The determination as to what constitutes a minor discrepancy rests solely with the contracting officer and nothing in this paragraph shall be construed as a waiver of the government's rights under any clause in this contract, including the right to assess liquidated damages as may be appropriate for failure to complete the project in accordance with the terms and conditions contained therein.

OCR 2- DESIGNATION OF GOVERNMENT INSPECTOR

The Base Civil Engineer or his authorized representative is designated as the representative of the contracting officer for the purpose of technical surveillance of workmanship and inspection of materials for work being performed under this contract. This designation in no way authorizes anyone other than the contracting officer to commit the Government to changes in the terms of the contract.

OCR 3- ISSUANCE OF NOTICE TO PROCEED

The United States Government will issue Notice to Proceed within 40 calendar days after contract award.

OCR 4- POST AWARD ADMINISTRATIVE INFORMATION

The contracting officer will provide to the contractor, a listing of the names of the Administrative

Contracting Officer, Contract Administrator, and Construction Inspector (also referred to as the

Contracting Officer’s Representative (COR) or Technical Representative of the Contracting Officer

(TRCO), their organizational codes and telephone numbers at the time of award or at the pre-construction conference. This provision in no way authorizes any person other than the contracting officer to commit the United States Government to changes in the terms or conditions of this contract. Reference Section I, DFARS 252.201-7000 entitled Contracting Officer’s Representative (DEC 1991).

PAYING OFFICE: Accounting and Finance

DFAS-BVNF/JA

Yokota Air Force Base

Fussa-shi

Tokyo, Japan 197-0001

OCR 5- U.S. DOLLAR VERSUS YEN EQUIVALENT

For the duration of this solicitation the contractor shall use the following exchange rate in determining the

Yen equivalent to referenced US dollar amounts in this solicitation provisions/contract clauses $1.00 =

JPY ¥122.4519 evaluation of the award. All referenced US dollar amounts in this solicitation provisions/contract clauses are modified to include "or Yen equivalent".

OCR 6- REQUIRED INSURANCE (IN ADDITION TO THAT REQUIRED BY JAPANESE

LAW)

a. The contractor shall procure and maintain during the entire period of his performance under this contract the following minimum insurance on each vehicle used by the contractor at the work site.

Type: Automobile Property Damage and Bodily Injuries

Amount: JPY3,000,000 for automobile property damage

JPY30,000,000 for bodily injuries

b. Prior to the commencement of work hereunder, the contractor shall furnish to the contracting officer a certificate or written statement of the above required insurance. The policies evidencing required insurance shall contain an endorsement to the effect that cancellation or any material change in the policies adversely affecting the interests of the US Government in such insurance shall not be effective for such period as may be prescribed by the laws of the country of Japan in which this contract is to be performed and in no event less than thirty (30) days after written notice thereof to the contracting officer.

c. The contractor agrees to insert the substance of this clause, including this paragraph (c) in all subcontracts hereunder.

OCR 7- CONCILIATION

Except as otherwise provided in this contract, any disagreement arising under this contract which is not resolved by the parties to this contract may be submitted to the United States - Japan Joint Committee for

Conciliation in accordance with Paragraph 10, Article XVIII, of the Status of Forces Agreement under

Article VI of this Treaty of Mutual Cooperation and Security between Japan and the United States of

America. Requests by the contractor for conciliation shall be made in accordance with the following procedures:

a. In the event the contractor desires conciliation after the decision of the contracting officer has been served upon him, he will first file his appeal from such findings of facts with the appropriate authority in accordance with the clause of this contract entitled “DISPUTES”, and within the time limits described therein before filing request for conciliation with the Joint Committee and then request the appellate authority under the clause of this contract entitled “DISPUTES”, to suspend its action on his appeal until such time as the Joint Committee has had an opportunity for effecting conciliation.

b. The request for conciliation will be submitted by the contractor through the nearest Defense Facilities

Administration Bureau, to the Contract Conciliation Panel of the Joint Committee. Upon the filing of the request with the Joint Committee, the contractor will immediately notify the contracting officer in writing that the request for conciliation has been filed.

c. In the event the disagreement submitted to the Joint Committee under subparagraph (b) above has been resolved through conciliation, it will be the responsibility of the contractor to notify the appellate authority designated in the clause of this contract entitled “DISPUTES”, of the settlement of the dispute and to withdraw his appeal.

d. In the event the contractor who has submitted a request for conciliation to the Joint Committee under subparagraph (b) above desires; notwithstanding tendency of his request for conciliation, that action by the appropriate authority under the clause of this contract entitled “DISPUTES” be resumed on his appeal, it is his responsibility to so request the said authority in writing. The Joint Committee shall be immediately informed by the contractor of his action taken hereunder.

e. No request for conciliation can be submitted to the Joint Committee in the case of a dispute upon which the final decision of the appropriate authority under the clause of this contract entitled

“DISPUTES” has been rendered. Pending the hearing of Conciliation Panel the contractor shall proceed diligently with the performance of the contract in accordance with the contracting officer’s decision. The provisions of this clause shall not prejudice any right which the parties to the contract may have to file in a civil suit.

OCR 8- PERFORMANCE BOND

A performance bond in the penal amount of one hundred percent (100%) of contract price or greater (or

Yen equivalent) price shall be submitted within 15 calendar days after the contract award date or prior to the receipt of the notice to proceed whichever comes first.

OCR 9- BASE DEFENSE ACT/WORKMAN’S COMPENSATION/WORK ON AN OVERSEAS

INSTALLATION

This contract includes FAR 52.228-3, Workers’ Compensation Insurance (Defense Base Act) (Apr 1984), and FAR 52.228-4, Worker’s Compensation and War-Hazard Insurance Overseas (Apr 1984). FAR

52.228-3 applies only if the contractor has United States’ citizen or national employees, regardless of whether they have SOFA status or a status of residence in Japan. FAR 52.228-4 applies if the contractor has non-United States’ citizen or national employees. One or both clauses may apply to the contractor.

OCR 10- EXEMPTION FROM JAPANESE CUSTOMS DUTIES AND TAXES PURSUANT TO

STATUS OF FORCES AGREEMENT

(a) Paragraph 2, Article XI of the Status of Forces Agreement between Japan and the United States, authorizes the United States entry into Japan free from Japanese customs duties and all other charges on materials, supplies, and equipment imported for the official use of the United States Armed Forces or for the exclusive use of such forces or ultimately to be incorporated into articles or facilities used by such forces.

(b) Paragraph 3, Article XII of said Status of Forces Agreement, authorizes the United States exemption from certain Japanese taxes for materials, supplies, equipment and services procured for official purpose in Japan by the United States Armed Forces or by authorized agencies of the United States Armed Forces.

Currently, these taxes are: (1) Gasoline tax and local road tax on gasoline; (2) Diesel oil tax; (3)

Liquefied petroleum tax, and (4) Consumption tax.

(c) If you are the successful offeror, the contracting officer or his authorized representative will issue customs or tax exemption certificate in accordance with procedures agreed upon between the Government of Japan and the United States of America. Tax exemption certificates for either a the end of each month or upon termination of the contract. These can be applied against future purchases of motor fuel. They will be issued only to you as the prime contractor, so, if you employ a subcontractor or supplier who uses motor fuel, you must purchase the motor fuel to secure the exemption.

(d) List below the customs duties or taxes which have been excluded from your proposal as required by the taxes clause. Contractor must claim all customs and tax exemptions to which the US Government is entitled.

Type of Commodity & Amount of Duty or

Percentage of Tax Tax Excluded in Yen

(1) Customs Duties __________________ _________________

(2) Taxes __________________ _________________

(a) Gasoline tax and local road tax on gasoline __________________ _________________

(b) Diesel oil tax __________________ _________________

(c) Liquefied petroleum tax __________________ _________________

(d) Consumption tax _________8%______ _________________

OCR 11- TAX EXEMPTION CERTIFICATE

The Contractor will submit requests for gasoline or diesel oil tax exemption certificates to the Contracting

Officer. This request will show the actual amount of gasoline or diesel oil used exclusively for the performance of this contract, with documentary evidence and detailed item breakdown to certify the accurate consumption of gasoline or diesel oil, or other necessary information and data as may be required. The Contracting Officer will issue to the Contractor a Tax Exemption Certificate for the actual amount of gasoline or diesel oil used exclusively for the performance of this contract. The Contractor shall claim all tax and customs exemptions as listed in OCR 10, titled, “EXEMPTION FROM

JAPANESE CUSTOMS DUTIES AND TAXES PURSUANT TO STATUS OF FORCES

AGREEMENT”.

OCR 12- JAPANESE ROAD LAWS

The Contractor shall comply with Japanese Road Laws while on U.S. military installations to specifically include:

Article 43, The Road Law (Japan) (prohibitive acts relative to roads). No person shall commit the following described acts:

Damaging the road, causing roads to be littered with debris, polluting the roads with debris or fall out from motor vehicles or otherwise defacing roads unreasonably or without due cause.

Article 43-2 (Measures to be taken to prevent cargo or things loaded on motor vehicles from falling out)

The agency managing a road may, when there is reasonable cause for him to feel that items or cargo being carried in or on a motor vehicle may fall out and damage, pollute, or otherwise deface the road in such manner as to hinder or obstruct the traffic, order the operator of the vehicle in question to take steps or measures necessary to prevent occurrence of such hindrance by stopping operation of the vehicle, correcting the method of loading or traveling, or operation of the vehicle.

OCR 13- REGISTRATION OF MOTOR VEHICLES

All company-owned and privately-owned motor vehicles required to be on U.S. Government facilities during the performance of this contract must be registered with Vehicle Registration, Camp Foster.

Necessary decals and/or permits will be issued and displayed on the vehicles in the manner as directed by the Vehicle Registration Officer. Vehicle decals shall be removed from vehicles and turned in to

Vehicles Registration, Camp Foster, at the end of the contract period or sooner when vehicles are no longer used in the performance of the contract or as directed by the Contracting Officer.

OCR 14 - PROPOSAL PREPARATION INSTRUCTIONS

A. To assure timely and equitable evaluation of proposals, offerors must follow the instructions contained herein. Offerors are required to meet all solicitation requirements, including terms and conditions, representations and certifications, and technical requirements.

Failure to meet a requirement may result in an offer being ineligible for award.

1. Complete blocks 14, 15, 19 (as appropriate), 20A, 20B, and 20C of the solicitation Section A, Standard Form 1442. In doing so, the offeror accedes to the contract terms and conditions as written in the Request for Proposal (RFP) Sections A through K. These sections constitute the model contract.

2. Insert proposed unit prices in Section B for Contract Line Item Numbers (CLIN) 0001. Indirect costs such as overhead, profit, etc., must be included in the price.

3. Complete the necessary fill-ins and certifications in Sections I through K. Section K shall be returned in its entirety. For any other sections, the offeror shall only submit the pages, if any, that require a fill-in.

Note: Check your pricing submission very carefully for mathematical and clerical errors prior to submission.

B. Documents submitted in response to this solicitation must be fully responsive to and consistent with the following:

1. Requirements of the solicitation CLIN, specifications and drawings, and government standards and regulations pertaining to the specifications and drawings.

2. Evaluation Factors for Award in Section M of this solicitation.

3. Any documents other than specified in Section L will not be read or evaluated, and will be removed from the proposal.

4. Format for bid shall be as follows:

a) A page is defined as one face of an 8 ½” x 11” sheet of paper containing information.

b) Typing shall not be less than 12 pitch.

C. Bid Submission:

1) Submit your bid to arrive NOT LATER THAN 08 May 2017 AT 14:00 hrs (2:00 pm), Japan

Standard Time.

2) All bids delivered in response to this solicitation shall reflect the following information on the address label:

a. Solicitation Number FA5270-17-B-0005.

b. The legend, "To be delivered unopened to the Contracting Officer", and

c. The volume and copy numbers contained in each box/envelope.

3) Submit your proposal to the following address:

MSgt Tom Poplin

18 Contracting Squadron / LGCC

Unit 5199, Bldg 95

APO, AP 96368 (Okinawa, Japan)

OCR 15- MAGNITUDE OF CONSTRUCTION PROJECTS

The magnitude of the estimate for this project is between $500,000.00 and $1,000,000.00.

OCR 16- CONTRACT PERFORMANCE IN JAPAN

This project will be performed in its entirety in the country of Japan. The successful offeror must be licensed and registered to perform work in the country of Japan.

OCR 17- ADDITIONAL INFORMATION CONCERNING THE ACQUISITION OF INQUIRY

OF DUNS NUMBERS IN JAPAN

Contractors need to be aware that the Japanese Dun and Bradstreet will assess a fee for Duns Number inquiry or obtaining a new assignment effective 1 April 03.

For more information see the following Web site: http://www.dnb.co.jp or send an e-mail to: jp-gunsrequest@dnb.com

CONST–M-7400 BASIS FOR CONTRACT AWARD (JUN 2006):

http://www.dnb.co.jp/ mailto:jp-gunsrequest@dnb.com

OCR 18 - BASIS FOR CONTRACT AWARD

Award will be made to the lowest responsible bidder, whose bid is responsive to the terms of the

Invitation for Bids (IFB), considering only price and price-related factors included in the IFB, and;

It is the best interest of the Government to award a contract resulting from this IFB; and

Sufficient funds are available at the time of award.

Bid must be submitted in compliance with the terms and conditions of the IFB or be considered non-responsive.

Only one contract will be awarded.

(End of Provision)