This Memorandum for Record (MFR) addresses Request for Information (RFI) responses for Solicitation Number FA524025Q0062 for Medical Materiel Technician Services at Andersen Air Force Base, Guam. The contract covers a base period from 26 Sep 2025 - 25 Sep 2026 with five potential option periods extending through 25 Mar 2031, involving two full-time employees (FTEs) performing medical materiel services. Key clarifications include: the government will provide a forklift, Guam is considered a CONUS location, no SOFA/SPOTS/DBA requirements apply, and a completed DD254 and security clearance are required for contractor employees prior to start date.
Specific RFI responses address technical details such as performance locations within the INDOPACIFIC AOR (including Marianas, Japan, Philippines, and Australia), confirmation that key personnel are not part of the evaluation factor, and a correction to the Option 5 performance period hours (1040 hours for six months, not 2080 hours). The solicitation deadline will not be extended, and the Performance Work Statement (PWS) will be revised to clarify specific dates. The contract is issued by the Department of the Air Force, Headquarters 36th Wing (PACAF), and involves medical materiel technical services.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
HEADQUARTERS 36TH WING (PACAF)
ANDERSEN AIR FORCE BASE GUAM
17 September 2025
MEMORANDUM FOR RECORD
FROM: 36 CONS/PKB
SUBJECT: FA524025Q0062 Attachment 7 - Response to RFIs
REF: Solicitation Number - FA524025Q0062: 36 CONS - 36 MDG - Medical Materiel Technician Services
I. The purpose of this Memorandum for Record (MFR) is to provide responses to Request for
Information (RFI) received in response to the subject solicitation.
II. Request for Information:
1. Period of Performance (PoP) on the PWS states 12 months each period, but the breakdown is 11 months.
Answer: The specific dates of the PoP have been removed from Attachment 1 - Performance Work Statement (PWS) and a revised PWS will be posted. The tentative dates are as follows:
Base Period 26 Sep 2025 - 25 Sep 2026 Option Period 1 26 Sep 2026 - 25 Sep 2027 Option Period 2 26 Sep 2027 - 25 Sep 2028 Option Period 3 26 Sep 2028 - 25 Sep 2029 Option Period 4 26 Sep 2029 - 25 Sep 2030 Option Period 5 (6 Mon Extension) 26 Sep 2030 - 25 Mar 2031
2. Will there be an extension on the solicitation deadline?
Answer: No.
3. In Section 1.6.5 Place of Performance: “…may also be performed at another temporary location within the INDOPACIFIC AOR, including, but not limited to, the Marianas, Japan, Philippines, and Australia…” Are the contractor’s FTEs required to have a U.S.
Passport or a different passport (i.e., Red)? Will the TDY within the INDOPACIFIC AOR require SOFA, SPOTS, or DBA?
Answer: No, Guam is considered a CONUS location therefore, SOFA, SPOTS, or DBA will not be applicable.
4. In Section 1.6.9 Security Requirements: “…A completed DD254 and a valid security clearance are required prior to Contractor’s employees start date…” Please clarify that this requirement is part of the deliverable in Section 5, Technical Exhibit B?
Answer: No. It is not part of contractor deliverables.
5. In Section 1.6.11 Special Qualifications: Reference TO 13C7-34-2-1-WA-1: Is this a DAF regulation? If this is policy or standard operating procedure (SOP), will the government provide a copy?
Answer: Yes.
6. In Section 2.1.6 Key Personnel: To clarify, key personnel are not part of the evaluation factor. There is no other information provided addressing the FTEs as part of the evaluation factor.
Answer: Correct.
7. In Section 3.4. Equipment: Government Furnished Items and Services: A forklift is required for under the PWS. Please clarify whether the government will provide one or if it is the contractor's responsibility and will this include the maintenance, fueling, and incidental supplies to ensure the forklift is in working order?
Answer: The government will provide a forklift.
8. CLINS/Performance Period for Option 5: This is for a six-month extension, but the quantity states 2080 hours (a full 12 months?). Should this be 1040 hours for the six months for two FTEs?
Answer: Correct. Attachment 2 – Price Worksheet (Excel) is correct, and Attachment 2 – Price Worksheet (PDF) will be revised and reposted.
(END OF MFR)