FA524023R0019 Amendment 002 Q A.pdf
PDF 1 MB Posted
- Attached to
- 36 CES HVAC Direct Digital Controls (DDC) Upgrade for 644 CBCS Federal contract opportunity
- Solicitation number
- FA524023R0019
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FA524023R0019 Amendment 003 Q A.pdf | ||
| FA524023R0019 Amendment 003 Combined Synopsis Solicitation.pdf | ||
| Amendment 001 - Site Visit Details and Instructions.pdf | ||
| FA524023R0019 Attachment 1 - Performance Work Statement (PWS).pdf | ||
| FA524023R0019 Attachment 3 - Wage Determination 2015-5693.pdf | ||
| FA524023R0019 Attachment 5 - Evaluation Criteria.pdf | ||
| FA524023R0019 Attachment 7 - Past Performance Fact Sheet.pdf | ||
| FA524023R0019 Attachment 2 - Mandatory Pricing Sheet.xlsx | XLSX spreadsheet | |
| FA524023R0019 Attachment 6 - Clauses and Provisions.pdf | ||
| FA524023R0019 Attachment 8 - Past Performance Questionnaire.pdf | ||
| FA524023R0019 Combined Synopsis Solicitation.pdf | ||
| FA524023R0019 Attachment 4 - Additional Instructions to Offerors.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA524023R0019 - HVAC DDC SYSTEMS UPGRADE for 644 CBCS 09 June 2023 Amendment 002 – Site Visit Q&A
Q1: Is the CAT 6 cable the appropriate cable used?
A1: It is preferred.
Q2: Are there any issues with compatibility?
A2: whoever wins the solicitation will need to provide one vendor equipment for all of the sites such as Alerton, Johnson Controls, or Carrier. The controllers themselves are not interoperable as far as communication goes so the winner of solicitation will have to work the solution on a case-by-case basis depending on what exists at that facility.
Q3: What is the intent of the contract?
A3: Intent of the contract is to standardize/modernize our DDC systems to all one vendor, have updated operating systems, and managed switches for all sites.
Q4: Are there existing Ups?
A4: Yes, but they won’t be required within this new construct as the laptops that act as the DDC workstation will be located at the HVAC shop vs within the mechanical rooms.
Q5: Is there a preferred brand of switches – IE 4000 vs CISCO 4000?
A5: Any authorized switch would work, however dependent on the size of the switch, some may be easier to fit into the DDC cabinet. For example, if we tried to install a full sized 24/48 port switch into these cabinets, they would not fit which means an entirely new closure would be required. If the industrial 4000 series is used, it would be a much closer match to size within the cabinet.
Q6: Are there any downtime concerns?
A6: No concerns because they run in hand. Normal duty hours still apply.
Q7: How involved is cybersecurity and who will apply it?
A7: Robbie Hayes will be the CIO for the project. The project should follow the below guidance as all USAF Control system projects follow:
• UFGS-25 05 11, Cybersecurity for Facility-Related Control Systems
• UFC 4-010-06, Cybersecurity of Facility-Related Control Systems