This document contains a schedule for the delivery of engine bases and related cost information for a federal contract opportunity with the Department of the Air Force Pacific Air Forces. The schedule outlines two CLINs for the delivery of engine bases, with the first delivery of 8 engine bases due no later than May 15, 2020 at no cost, and the second delivery of 12 engine bases due no later than August 15, 2020 at no cost. The total projected cost for the project is $0. The related federal contract opportunity is a solicitation with number FA5215-20-R-0006 for BAK-12 AAS engine bases. No response date or award date is included.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Atch 5--ITO 31 Jan 2020.docx | DOCX document | |
| Atch 2a) BAK-12 SOW - amendment 1 - 31 Jan 2020.docx | DOCX document | |
| Atch 1 - BAK 12 - Clauses & Provisions.docx | DOCX document | |
| Atch 2c) 201018919 Base Finish Macining Assy.pdf | ||
| Atch 2b) 201018916 Base Weld Assy.pdf | ||
| Atch 2a) BAK-12 SOW.docx | DOCX document | |
| Atch 4c) JALC_AVIATION_CSI_MGMT_HDBK_16MAR2011.pdf | ||
| Atch 4b) AFI20-106_Management_of_Aviation_Critical_Safey_Items.pdf | ||
| Final Solicitation FA521520R0006.docx | DOCX document | |
| Atch 5--ITO 7 Jan 2020.docx | DOCX document | |
| Atch 4a) 2019-11-19 BAK-12 and MAAS CSI determination.pdf | ||
| Atch 2d) 201019010 Top Drawing.pdf |
Show all 12
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| BAK-12 AAS Engine Bases | ||||
| Delivery NLT 15 May 2020 | ||||
| CLIN 0001 | Inspections | Cost | Units | Cost |
| Engine Bases | 8 | $ - 0 | ||
| Shipping | $ - 0 | |||
| Total | $ - 0 | |||
| Delivery NLT 15 Aug 2020 | ||||
| CLIN 0002 | Location | Cost | Units | Cost |
| Engine Bases | 12 | $ - 0 | ||
| Shipping | $ - 0 | |||
| Total | $ - 0 | |||
| Total | ||||
| Summary | Cost |
PROJECT COST $ - 0