Questions and Answers

View the file

Other files

File Type Posted
FA520915P0076.pdf PDF
Appendix_c.pdf PDF
PWS_Amended_9_Mar_15.pdf PDF
FA5209-15-T-0047.pdf PDF
USAG-J_FORM_1795_Appendix_B.pdf PDF
Boiler_List_Appendix_A.pdf PDF
Pricing_Exhibit_for_Boiler_inspention.pdf PDF
FA5209-15-T-0047.pdf PDF
Boiler_Inspection_PWS_18_Feb.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NO. Section Paragraph Question Answer

Performance-base

Specification

Paragraph 1.1 "Inspection"

What inspection report do you use for the Unfired Pressure Vessels for the K type inspections.

There is a Unified Facilities Criteria (UFC 3-430-07, Operations and

Maintenance: Inspection and Certification of Boilers and Unfired Pressure

Vessels). Please utilize Figure E-2, page 53 of UFC 3-430-07, that is a form for Unfired Pressure Vessel Inspection Report.

(http://www.wbdg.org/ccb/DOD/UFC/ufc_3_430_07.pdf) for K type inspection. PWS para 1.2.1.2 will be revised by amendment 0001 accordingly.

Performance-base

Specification

Paragraph 1.1 "Inspection"

What Federal specification mandates the K type inspection. This inspection is not identified in the AR 420_01 specification.

In accordance with Unified Facilities Criteria (UFC 3-430-07) and the latest edition of the Code of Boiler and Pressure Vessel Inspectors (BPVI), Government developed the PWS including inspection types (A, C and K). We reviewed the aforementioned regulations, and determined that there is no need to change the type K inspection; therefore, no revision is made to the PWS.

Performance-base

Specification

Paragraph 1.1 "Inspection"

It is my recommendation that the UPV have internal inspections to see if the UPV is corroding from the inside out.

Your suggestion has been noted. However, we determined that there is no need to change the type K inspection; therefore, no revision is made to the PWS.

Question and Answer

9-Mar-15

FA5209-15-T-0047, Boiler and Unfired Pressure Vessel (UPV) Inspection Service at U.S. Army Garrison, Japan