Questions and Answers 11-T-0127.doc

DOC document 38 KB Posted

Attached to
CO-GENERATION PLANT MAINTENANCE
Solicitation number
FA5209-11-T-0127
Issued by

About this file

Questions and Answers

View the file

Other files

File Type Posted
Pre-proposal Conference Minutes —
Co-Generation Solicitation.rtf RTF text file
ATTENDANCE SHEET-cogeneration plant.doc DOC document
A2-Maint —
A456(Minimum Requirement).xls XLS spreadsheet
A1-Maint —
PWS FINAL SOLICITATION RFQ 1 Aug 11.doc DOC document
A3-(Maintenance Schedule) RFQ.xls XLS spreadsheet
B1 Maintenance Report —
Notice to Offeror.doc DOC document
A-6 Market Research questionnaire —
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions and Answers for RFQ No. FA5209-11-T-0127 Followings questions were received after the pre-proposal conference from prospective offerors.

The government’s answers are attached.

1
Question
Can a prime contractor without the relevant past performance history submit a bid on this solicitation if they have a subcontractor with the necessary past performance history?
Answer
Please see FAR 52.212-2 (page 13 of RFQ) (a)(2)(ii). Especially, statement

"Past performance regarding predecessor companies, key personnel who have relevant experience, or subcontractors that will perform major or critical aspects of the requirement may be evaluated. Past performance information pertaining to a subconotractor cannot be disclosed to the prime offeror without the subcontractor's consent. Provide with the proposal a letter from all subcontractors that will perform major or critical aspects of the requirement, consenting to the release of their past performance information to the prime contractor".

Answer to No.1: Yes, prime contractor without the required past performance history may submit a bid on this solicitation if they have a subcontractor with the necessary past performance history. However, prime contractor shall provide the contractor manager who have good understanding of the requirement pertaining to this contract (para 1.5.2.3. of the PWS) even though the prime contractor does not have the relevant past performance history.

2
Question
Reference PWS para 1.5.10. - Will storage space be provided for the parts (annual maintenance) and materials?
Answer
Yes. We can lend some extra space in the co-generation plant area to the

contractor. But it is space for materials only during overhaul and quarterly maintenance. There will not be a shed and/or warehouse provided for storage of materials. We are not sure at this point whether the space will be indoor or outdoor of the co-generation plant. Storage site will be decided by detail coordination with plant operator and COR after the contract award but before the start-up of the performance.

3
Question
Reference PWS para 1.5.11. - Will office space be provided, and if so, how much of spaces?
Answer
The contractor can use the conference area (include desks and chairs)

for office space and toilet in the plant as a joint use during the quarterly maintenance and annual maintenance services. Therefore the contractor shall clean these areas when used.

4
Question
All line items from 0001 thru 4002 shall be priced?
Answer
Yes, all line items shall be priced.
5
Question
How many gas engine shall be overhauled per year?
Answer
Please see Appendix A3 for scheudle of overhaul. Appendix A3 shows one (1) gas engine overhauled per year.