Addendum_No._2_RFP_No._FA5205-13-R-0005.pdf

PDF 2 MB Posted

Attached to
QKKA 11-1200P2, Repair Airfield Lighting System, Misawa AB, Japan
Solicitation number
FA5205-13-R-0005
Issued by

About this file

Addendum No. 2 RFP No. FA5205-13-R-0005

View the file

Other files

Show all 20

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 5 to RFP No. FA5205-13-R-0015

ADDENDUM NO. 2

FOR

PROJECT No. QKKA 11-1200P2, REPAIR AIRFIELD LIGHTING SYSTEM, MISAWA AB, JAPAN

14 Feb 13

Project drawings and specifications are amended to provide the following changes. Area-1 Drawing No.

E-412 and E-414 and Area-4 Drawing No. E-404 and E-406, and Area-3 Specifications– Section 01 11 00 are replaced with Revised 14 Feb 13, and as-built drawings for existing pavement sections for taxiway shoulders are provided, as attached.

AREA 1.

1) △2 a, DWG #E-412 (Intersection between TW B & TW C1):

A construction note number ○21 is deleted.

2) △2 b. DWG #E-412 (TW B1):

A construction note number ○25 is changed to ○24 .

3) △2 c. DWG #E-412 (TW B between TWC1 & TWC2):

A line between asphalt pavement shoulder area and sodding area is indicated.

4) △2 d. DWG #E-414 (TW B between TW C2 & TW C3):

A line between asphalt pavement shoulder area and sodding area is indicated.

5) △2 i. DWG #E-414 (TW B between TW C2 & C3):

A construction note number ○18 is deleted.

AREA 4.

6) △2 e. DWG #E-404 (4 locations around the intersection between TW D1 & TW C):

A construction note number ○19 is changed to ○18 .

7) △2 f. DWG #E-406 (2 locations in TW C between TW C2 & C3):

A construction note number ○19 is changed to ○18 .

8) △2 g. DWG #E-406 (4 locations in TW C between TW C2 & C3):

A construction note numbers ○18 is deleted.

9) △2 h. DWG #E-406 (TW C between TW C2 & C3):

A construction note number ○23 is deleted.

AREA 3.

10) Specifications – Section 01 11 00, para. 1.4.3.a.v.:

Attachment 5 to RFP No. FA5205-13-R-0015

The entire description is changed to “Update airfield lighting control and monitoring system including software in accordance with the manufacturer’s instructions.”.

11) Specifications – Section 01 11 00, para. 1.4.3.b.iii.:

Following description is added to an additional sub-paragraph “iii”:

“Update airfield lighting control and monitoring system including software in accordance with the manufacturer’s instructions.”

12) Specifications – Section 01 11 00, para. 1.4.3.d.:

The entire description is changed to “Update airfield lighting control and monitoring system including software in accordance with the manufacturer’s instructions.”.

All Areas.

13) Section Details of Existing Pavement Shoulders at Taxiways:

As-built drawings for section details of existing asphalt pavement shoulders at Taxiway Alpha and Bravo, and Taxiway Charlie and Delta are provided for removal and restoration work at each area.

(End of Addendum)

6 Attachments:

Atch 1. Area-1 DWG No. E-412, Revised 14 Feb 13, 1 sheet.

Atch 2. Area-1 DWG No. E-414, Revised 14 Feb 13, 1 sheet.

Atch 3. Area-4 DWG No. E-404, Revised 14 Feb 13, 1 sheet.

Atch 4. Area-4 DWG No. E-406, Revised 14 Feb 13, 1 sheet.

Atch 5. Area-3 Specifications - Section 01 11 00, Revised 14 Feb 13, 11 pages.

Atch 6. As-built Drawings for Section Details of Existing Asphalt Pavement Shoulders at Taxiways, 2 sheets.

AECOM

999 TOWN & COUNTRY ROAD

ORANGE, CALIFORNIA 92868

T: 714.567.2400

F: 714.567.2441 www.aecom.com

1299574152U Typewritten Text

1299574152U Typewritten Text

1299574152U Typewritten Text

1299574152U Typewritten Text

1299574152U Typewritten Text

1299574152U Typewritten Text

1299574152U Typewritten Text

1299574152U Typewritten Text

1299574152U Typewritten Text

1299574152U Typewritten Text

1299574152U Typewritten Text

AECOM

999 TOWN & COUNTRY ROAD

ORANGE, CALIFORNIA 92868

T: 714.567.2400

F: 714.567.2441 www.aecom.com

AECOM

999 TOWN & COUNTRY ROAD

ORANGE, CALIFORNIA 92868

T: 714.567.2400

AECOM

999 TOWN & COUNTRY ROAD

ORANGE, CALIFORNIA 92868

T: 714.567.2400

REPR Airfield Lighting Systems MISAWA AIR BASE

Section 01 11 00 Page 1

Revised 14 Feb 13 Addendum No. 2

SECTION 01 11 00

SUMMARY OF WORK

01/08

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM E 2114 (2008) Standard Terminology for

Sustainability Relative to the Performance of

Buildings

1.2 DEFINITIONS

Definitions pertaining to sustainable development are as defined in ASTM E

2114, Section 01 57 20.00 10 ENVIRONMENTAL PROTECTION, and as specified.

a. "Environmentally preferable products" have a lesser or reduced effect on the environment in comparison to conventional products and services. This comparison may consider raw materials acquisition, production, manufacturing, packaging, distribution, reuse, operation, maintenance, or disposal of the product.

b. "Indoor environmental quality" is the physical characteristics of the building interior that impact occupants, including air quality, illumination, acoustics, occupant control, thermal comfort, daylighting, and views.

c. "Operational performance" is the functional behavior of the building as a whole or of the building components.

d. "Sustainability" is the balance of environmental, economic, and societal considerations.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Upon receipt of Government Furnished Equipment, the Contractor shall submit records in accordance with paragraph entitled, "Government Furnished Property," of this section.

Submit the following items to the Contracting Officer:

file:///D:/01%2057%2020.00%2010.doc file:///D:/01%2033%2000.doc

Section 01 11 00 Page 2

Utility Outage Requests

Utility Connection Requests

Borrow Permits

Excavation Permits

Welding Permits

1.4 WORK COVERED BY CONTRACT DOCUMENTS

1.4.1 Scope

The work covered by these construction documents consists of furnishing all supervision, labor, equipment, and materials necessary to perform all operations required to complete ready for use, all in accordance with these specifications and the applicable drawings, for the Project QKKA 11-1200P4

(Area 3) Repair Airfield Lighting System, Misawa Air Base, Japan.

1.4.2 Location

The project is located within Building 1115, Building 1116, Control Tower and airfield area at the Misawa Air Base, Japan.

1.4.3 Project Description

The work to be performed in connection with the project includes, but is not limited to the following:

The work to be performed in connection with the project includes, but is not limited to the following:

a. Existing Lighting Vault 1115

i. Replace existing emergency generator and ATS.

ii. Replace existing electrical distribution equipment.

iii. Replace existing CCR's with switchgear type CCR's.

iv. Re-use and new ACE panels and circuit selector switches.

v. Update airfield lighting control and monitoring system including software in accordance with the manufacturer’s instructions.

vi. Provide temporary power and emergency generator during reconnection.

vii. Disconnecting of existing transformers.

viii. Removal and disposal of existing equipment.

ix. Modifications to the vault's floor, ceiling, interior and exterior walls to accept new exhaust fans and associated mechanical and electrical equipments.

x. Replace existing transformers

b. Existing Lighting Vault 1116

i. Replace existing CCR's with switchgear type CCR's.

ii. New and Re-use ACE panels and circuit selector switches.

Section 01 11 00 Page 3

iii. Update airfield lighting control and monitoring system including software in accordance with the manufacturer’s instructions.

c. Existing Airfield Lighting System

Remove existing airfield lighting cables and install new airfield lighting cables.

d. Control Tower

Update airfield lighting control and monitoring system including software in accordance with the manufacturer’s instructions.

1.4.4 Phasing Of Work

a. The work is divided into two distinct phases and sub-phases.

b. The construction phasing requires night time work and day time work

(except as noted on the phasing drawings).

c. Each phase of the work requires additional construction sequencing and coordination with the Base Airfield Management.

1.4.5 Airfield Lighting Expert

The contractor shall appoint an Airfield Lighting Expert to ensure compliance with UFC 3-535-01 & UFC 3-535-02. The Airfield Lighting Expert must have a minimum 5 year’s experience as an Airfield Lighting manufacturer’s Engineer or a minimum 5 year’s experience with US Air Force

Runway Lighting projects for material, shop drawing approvals and construction advice. Material and shop drawing submittals are required for

Airfield Lighting Expert’s approval signature.

1.5 WORK RESCHEDULING

1.5.1 Exterior construction work during Winter Period

Period from 15 December through 15 March in the following year, dates specified inclusive, is defined as "Winter Period" for the purpose of construction contracts to be performed in Misawa Air Base, Japan. During such period, the contractor shall obtain approval from Contracting Officer prior to performing exterior construction work such as excavation, backfill, asphalt/concrete placement, paint, etc.

1.5.1.1 Work Permitted during winter period

Replacement of existing generator system, transformer (interior), CCR's ACE panels, selector switches with wiring system and field cables with new, and modification/upgrade of vault's and airfield lighting control/monitoring system.

Section 01 11 00 Page 4

1.5.2 Availability of Work Site and Working Hours

a. The contractor shall provide a notice to the Contracting Officer at least fourteen (14) days prior to commencement of the on-site work in order for coordination with the using activity. The work site will be made available to the Contractor as follows:

(1) Five days a week, Monday through Friday except U.S. legal holidays

(2) Working Hours: 2200 hours to 0600 hours

(3) Working Hours for Vault 1115 and 1116: 0730 hours to 1630 hours

(Required to keep Airfield Operation from 06:00 thru 22:00).

The above working days and hours may be extended by the Contracting Officer upon the Contractor's request, on the stipulation that work requiring inspection by the Government or work unable to be inspected by the

Government on the following day shall not be performed during the extended days and hours.

b. U.S. Legal Holidays. If a U.S. holiday falls on Saturday, the preceding Friday will be observed as a U.S. holiday; and if a U.S.

holiday falls on Sunday, the following Monday will be observed as a

U.S. holiday. The following is a list of U.S. holidays:

New Year's Day

1st of January

Birthday of Martin Luther King Jr. 3rd Monday of January

President's Day 3rd Monday of February

Memorial Day Last Monday of May

Independence Day 4th of July

Labor Day 1st Monday of September

Columbus Day 2nd Monday of October

Veteran's Day 11th November

Thanksgiving Day 4th Thursday of November

Christmas Day 25th December

c. Should Misawa AFB be put under security alert or exercise, and the contractor is restricted from accessing the work site. The Construction contract period will be adjusted accordingly by the Contracting Officer.

Contracting Officer shall notify the contractor of unavailability of the work site.

1.6 PROJECT ENVIRONMENTAL GOALS

Section 01 11 00 Page 5

Contractor shall distribute copies of the Environmental Goals to each subcontractor and the Contracting Officer. The overall goal for design, construction, and operation is to produce a building that meets the functional program needs and incorporates the principles of sustainability.

Specifically:

a. Preserve and restore the site ecosystem and biodiversity; avoid site degradation and erosion. Minimize offsite environmental impact.

b. Use the minimum amount of energy, water, and materials feasible to meet the design intent. Select energy and water efficient equipment and strategies.

c. Use environmentally preferable products and decrease toxicity level of materials used.

d. Use renewable energy and material resources.

e. Optimize operational performance (through commissioning efforts) in order to ensure energy efficient equipment operates as intended.

Consider the durability, maintainability, and flexibility of building systems.

f. Manage construction site and storage of materials to ensure no negative impact on the indoor environmental quality of the building.

g. Reduce construction waste through reuse, recycling, and supplier take-back.

1.7 OCCUPANCY OF PREMISES

Building(s) will be occupied during performance of work under this

Contract. Occupancy notifications will be posted in a prominent location in the work area.

Before work is started, the Contractor shall arrange with the Contracting

Officer’s representative (COR) a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.8 EXISTING WORK

In addition to "FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements":

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.

1.9 ON-SITE PERMITS

Section 01 11 00 Page 6

1.9.1 Work Clearance Permit (AF Form 103)

Coordination with the Contracting Officer's Representative (COR) 30 days in advance is required for the issuance of work-clearance permit (AF Form 103) along with requests for the establishment of a field office, erection of portable toilet facilities, excavations, parking blocks, etc. prior to commencement of work.

1.9.2 Utility Outage Requests and Utility Connection Requests

The Contractor shall verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated or specified to be removed. But indicated in locations to be transversed by piping, ducts, and other work to be installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

Work shall be scheduled to hold outages to a minimum.

Utility outages and connections required during the prosecution of work that affect existing systems shall be arranged for at the convenience of the

Government.

Contractor shall not be entitled to additional payment for utility outages and connections required to be performed outside the regular work hours.

Coordination with the Contracting Officer's Representative (COR) 30 days in advance is required for the issuance of work-clearance permit (AF Form 103) along with requests for utility outages and connections. Each request shall state the system involved, area involved, approximate duration of outage, and the nature of work involved.

1.9.3 Base Civil Engineering Work and Welding Permits

Base Civil Engineering Work Permits - The contractor is responsible for obtaining a coordinated and approved Base Civil Engineering Work Clearance

Request (AF IMT 103) before any site work begins. Coordination with the

Contracting Officer's Representative (COR) 30 days in advance is required for open flam work or welding.

Welding Permit - The Contractor shall submit a request for open flame work

("Hot Work Permit) to the Base Fire Department for approval prior to commencing any open flame or welding operations. A Base Fire Department representative will visit the work site prior to commencement of the work and the Contractor shall demonstrate the work to be performed and precautions to be taken to prevent a fire. Open flame work will not begin without approval of the Contracting Officer's Representative (open flame and welding permit) or until the Fire Department arrives at work site if required.

1.10 LOCATION OF UNDERGROUND FACILITIES

Verify the elevations of existing piping, utilities, and any type of underground obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by

Section 01 11 00 Page 7 piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.11 SALVAGE MATERIAL AND EQUIPMENT

Items designated by the Contracting Officer to be salvaged shall remain the property of the Government.

Scrap metal shall be turned over to DRMO by contractor at no cost to

Government.

The salvaged property shall be segregated, itemized, delivered, and off-loaded at the Government designated storage area located within 10 kilometers of the construction site.

Contractor shall maintain property control records for material or equipment designated as salvage. Contractor's system of property control may be used if approved by the Contracting Officer. Contractor shall be responsible for storage and protection of salvaged materials and equipment until disposition by the Contracting Officer.

1.12 REQUIREMENTS AT AIRFIELD

1.12.1 Construction Waiver

The contractor shall be prepared waiver document package (UFC 3-260-01, Section 14) 3 months prior to US government, project engineer, 35CES/CEPM to obtain a construction waiver for men and equipment.

Obtain a construction waiver 3 months minimum prior to the construction start date with map of hauling route, working hours and places.

1.12.2 Entry Authorization

Obtain 35OSS/CC approval of Entry Authorization List in the controlled area during construction period. It takes about 3 weeks for approval process of

EAL.

1.12.3 Communication/Radio Requirements

The contractor needs radios for communication with the Air Control Tower

(ATC) during the performance of contract on the airfield. The contractor propose 35CES/CECP Engineering LMR Manager's to use government's radio transceivers battery powered portable radios within 30 calendar days after receipt of Notice to Proceed (NTP).

Access to the airfield worksite shall be accomplished through coordination with airfield management. Contractor is required to remain in voice contact with the airfield traffic controller (control tower) at all times.

Permission must be granted, by the control tower, prior to movement of any kind across airfield runways, taxiways, and clear zones. Transceivers shall remain accountable, on-base in locked storage, when not being used.

1.12.4 Airfield Driving Training

Section 01 11 00 Page 8

All workers operating a vehicle on the Airfield will receive Flight line

Drivers Training in English/Japanese and be certified by Airfield Management prior to operating vehicles on the Airfield. All workers/sub-contractors must comply with 36 FWI 13-202. Contractor must obtain POV passes from

Airfield (AFLD) management prior to driving a vehicle onto the AFLD.

The contractor can conduct survey and construction occurring within

Controlled Movement Area (CMA) after completion of Airfield Driver’s

Briefing conducted by 35OSS/OSAM (one hour briefing for all workers) for each project or be escorted. Minimum three foremen should acquire the

Airfield Driver’s License for one project site if it required. The three day’s Airfield Driving Training is required to get Airfield Driving certification.

1.12.5 Daily Site Clean-up

The contractor shall inspect the worksite and perform any necessary clean-up prior to departure at the end of the work day. Clean-up shall also be performed periodically throughout the work day to allow for expedient evacuation of the runway. No equipment will be allowed to remain on the airfield without prior coordination and approval of the Airfield Manager, 35

OSS/OGSAM, 226-4430/2833.

Prior to opening the runway and taxiway the Contractor shall conduct a safety inspection of the work area to determine that all personnel and equipment have been removed from the runway, that all potential Foreign

Object Debris (FOD) have been removed, and that the runway and taxiway are ready for air operations. The Contractor shall cooperate with the Base

Operations staff at all times, and shall correct any deficiencies prior to opening the runway and taxiway.

1.12.6 Equipment

All machines, tools, and equipment used in the performance of the work shall be approved, maintained in satisfactory operating condition, and no taller than fifteen (15) feet in height. All heavy equipment shall be able to meet runway evacuation requirements.

1.12.7 Night Operations

Normal aircraft flight operations hours are from 0600 to 2200 hours, 7 days per week. The Contractor may request working hour changes through the

Contracting Officer or his/her authorized representative. Requests shall be made 7 days in advance of the desired change. When night operations are to be conducted by the Contractor, all necessary lighting will be furnished by the contractor at no cost to the Government. Lighting will be shaded or directed so as not to interfere with aircraft or control tower operations.

1.12.8 Workday Notification

The contractor shall notify Base Airfield Management, 35OSS/OSA, 226-3180 of the location and duration of work prior to work each day. The contractor shall notify Base Airfield Management when departing airfield at the end of the working day.

1.12.9 Runway Evacuation Requirement

Section 01 11 00 Page 9

a. Alert Aircraft Launches: Runway must be cleared within five (5) minutes of notification. Equipment/personnel must be positioned on the shoulder of the runway, outside the runway lights.

b. Aircraft Approach/Landing/Departure: The contractor's equipment and personnel must be cleared off the runway and at the hold short line of the adjoining taxiway within ten (10) minutes of notification.

c. In-flight Emergency: Immediate equipment/personnel evacuation is required. This will not be an "Exercise" situation.

d. Personnel must park equipment with a height of 3 meter or higher 50 meter away from taxiway or runway then leave the work site immediately upon advice from Control Tower.

e. Prior to opening the runway the Contractor shall conduct a safety inspection of the work area to determine that all personnel and equipment have been removed from the runway, that all potential Foreign Object Debris

(FOD) have been removed, and that the runway is ready for air operations.

The Contractor shall cooperate with the Base Operations staff at all times, and shall correct any deficiencies prior to opening the runway.

1.12.10 Airfield Work Requirement

a. Taxiways can be used to access and to leave work site after obtaining permission from the Control Tower through radio communication.

b. Runway is off limits at all times.

c. The workers will not be able to work closer than 100ft of the runway unless specified in the temporary construction waiver. Coordination will need to be accomplished at least two days in advance to ensure proper coordination with the control tower.

d. Work will be authorized to be accomplished on both ends of the runway at the same time.

e. Personnel Protection: All personnel at site are required to wear ear protection from aircraft noise.

f. Marked and/or flagged for high daytime visibility and, if appropriate, lighted for nighttime operations.

1.12.11 Haul Routes

The Contractor will be required to use the haul routes identified by the

Contracting Officer’s representative (COR). The Contractor shall maintain the haul routes and shall keep the dust under control by wetting the surface as required. Sweeping and cleaning of pavements will be done as necessary to remove spillage resulting from hauling operations. After all hauling and construction has been completed, the Contractor will restore the earth areas used for haul routes and construction activities to original condition by fine grading, shaping, compacting and sodding and shall clean and sweep all paved areas as required. Any pavement damage as a result of hauling operations under this contract shall be promptly repaired by the Contractor, as approved by the Contracting Officer. The cost of maintenance and repair

Section 01 11 00 Page 10 of the haul routes shall be considered as a subsidiary obligation of the

Contractor.

Prior to entering an active taxiway the Contractor shall conduct a thorough

FOD check as required and remove all potential Foreign Object Debris (FOD) from vehicle tires.

1.12.12 Verification of Dimensions

The contract drawings show the extent and general arrangement of work to be done. The contractor must visit the site and become thoroughly familiar with all details of the work and working conditions and verify all dimensions in the field. Advise the Contracting Officer of any discrepancies before performing work.

1.12.13 Suspension of Power

The contractor shall request approval from the Contracting Officer or his authorized representative 14 days prior to the suspension of electrical power in coordination with all relative activities through AF Form 103.

The electrical power outage of the existing Airfield Lighting System will be permitted between 2200 and 0600 hours, non-operational hours.

1.12.14 Availability and Use of Utility Services

a. Water and Electricity will be available at the work site or in the vicinity of the work site. All reasonably required amounts of such utility services will be furnished to the Contractor without charge.

b. Water and Electricity is/are not available in the airfield.

There is no source for such utility services in the vicinity of the work site. Therefore, the Contractor shall provide all required utility services using the most suitable and safety equipment furnished by the Contractor.

c. Water and Electricity is/are available at Vault 1115/1116.

1.12.15 Availability of Sanitary Facilities

Toilet facilities are: * available * not available for Contractor's use.

1.13 Material Approval Submittals

The material approval submittals listed in Schedule of Contractor's

Submittals shall be submitted to the Contracting Officer for approval in accordance with the Contract Clause of this contract and instructions indicated in AF Form 3000 within 30 calendar days after the date of award of the contract after receipt of Notice to Proceed (NTP) of the individual

TOs, but before starting installation of any materials. Items listed in the schedule are principal materials only. This listing does not in any way limit the responsibility of the contractor to submit any materials specified in the technical provision of this contract when called for by the Contracting Officer.

Section 01 11 00 Page 11

1.14 Temporary facilities

The contractor shall provide temporary office/storage as required for his/her operations. Work clearance permit shall be obtained by coordinating

AF Form 103 with the relative activities for location of temporary facilities prior to erection. Paints, solvents and other flammable materials shall not be stored in the project building. The contractor may have telephone installed in his field office for his use in connection with this project Subject to approval of the Contracting Officer or his designated representative. All expenses related to the installation and use of such telephone will be borne by the contractor.

1.15 Final/BOD Inspection

Final/BOD inspection will be performed Monday through Friday excluding holidays, between 0800 through 1600 hours, subject to the flight operation at the airfield. The contractor shall submit a request for Final/BOD inspection in writing, at least 48 hours prior to his desired day and time.

After considering flight operation and other factors involved in the operation of airfield, the day and time of Final/BOD inspection will be determined by the Government and notified the contractor at least eight (8) hours prior to such determined day and time.

1.16 Confined Spaces

The Contractor shall coordinate entries into permit-required confined spaces with 35 CES/CEF (Fire Department). Contractor will provide time/date, location, duration of work, and type of work to be performed to

Fire Department. Contractor will notify Fire Department at completion of the entry.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.*

-- End of Section --

Section Details of Existing Asphalt Pavement Shoulder at Taxiway Alpha and Bravo

1299574152U Typewritten Text

1299574152U Typewritten Text

1299574152U Typewritten Text Attachment 6 to RFP No. FA5205-13-R-0005

1299574152U Typewritten Text

1299574152U Typewritten Text

1299574152U Typewritten Text Section Details of Existing Asphalt Pavement Shoulder at Taxiway Charlie and Delta

1299574152U Typewritten Text

1299574152U Typewritten Text

1299574152U Typewritten Text Attachment 6 to RFP No. FA5205-13-R-0005

1299574152U Typewritten Text

Addendum No. 2
Area-1 DWG No. E-412
Area-1 DWG No. E-414
Area-4 DWG No. E-404
Area-4 DWG No. E-406
Area-3 Spec-Sec 011100
Section Details for Existing Pavement at Taxiway Alpha & Bravo
Section Details for Existing Pavement at Taxiway Charlie & Delta

File details come from the government source that posted it. Updated .