RFIs-FA502526RB006.xlsx

XLSX spreadsheet 421 KB Posted

Attached to
Matsushima JASDF Base Storage Shelter
Solicitation number
FA502526RB006
Issued by

About this file

This file contains government responses to Requests for Information (RFIs) submitted by contractors for solicitation FA502526RB006, a design-build construction project at Matsushima Japan Air Self-Defense Force (JASDF) Base. The project requires construction of four membrane warehouse structures with associated utilities, security fencing, and climate control systems. Key technical clarifications address airfield height restrictions (maximum 25 meters for structures under Civil Aeronautics Act transitional surface restrictions), building code compliance under Japanese regulations, electrical system requirements (100 KVA transformer with 6,600V primary connection), HVAC specifications (maintaining 40°F minimum and 60% relative humidity throughout facilities), and drainage/stormwater management through oil-water separator and u-drain systems. The government confirmed that a bid bond is not required, and contractors may propose design alternatives (such as reduced eave heights of 7-8 meters instead of 9 meters, concrete floor slabs, or insulated metal wall panels) subject to approval.

Critical administrative requirements include: Prime Contractor must hold valid Japanese Construction License at proposal submission (mandatory, non-delegable requirement); all proposals must acknowledge Amendment 0 on SF 1442 block 19; updated site plans will be released with RFI responses; operations and maintenance manuals must be provided in both English and Japanese; early procurement submittals for long-lead items (membrane structures, structural steel, transformer, fire-alarm equipment, motorized gates) are permitted immediately after award at contractor's sole risk; and 150-day construction performance period applies to all work including utility tie-ins. Warranty requirements specify 10-year manufacturer warranties for membrane fabric and structural steel, 2-5 year warranties for doors depending on type, 1-5 year warranties for HVAC equipment, and 1-year standard commercial warranties for electrical equipment. The government will install conduit for secondary electrical and storm drainage, construct the stormwater retention pond, and provide as-built drawings post-award; the contractor is responsible for all other utility installations including primary electrical conduit, cable, transformer, and water line work.

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Matsushima RFIs

ProjectReference (Sect/Para/Page)RFIGovernment Response
Matsushima -
PMWH26-3531SF1442, Block 13.bRegarding SF1442, Block 13.b, which states "an offer guarantee is required": does this refer to a bid bond required at the time of bid submission? If so, the Solicitation does not appear to include any information on the required bid bond amount or other details. What type of bid bond should we prepare?

Also, is a bid bond actually required for this solicitation in the first place? If so, where should the original bond documents be sent by mail? (We assume the bond would not be valid as a scanned copy, even though all other proposal documents are to be submitted electronically.) Should it be sent to Yokota, Guam, or Matsushima? A bid bond/guarantee is not required for this solicitation.

We cannot change the solicitation form, due to our internal programs when creating them. This correction will be included as an amendment to the solicitation on SAM.gov

Matsushima -
PMWH26-3531SOW 11.c PermitsPlease clarify whether any airfield height restrictions (JASDF), crane operating height limits, or airfield obstruction clearance requirements apply to this project site. If applicable, please provide the maximum allowable height for temporary construction equipment and the completed structures (noting the specified minimum 9M/30FT eave height).Minimum eave hieght updated to 7M/23FT. To the right is the imaginary airfield height limits around the construction site. During design, JASDF will have to verify the structure. The details are still under review, and we will provide further information once available. Please note that the verification process typically takes approximately one month to complete.

Regarding crane operation, under the transitional surface restrictions stipulated by the Civil Aeronautics Act, the maximum allowable height of structures is 25 meters or less.In this case, please ensure that a red obstruction light and a daytime obstacle marker flag are installed at the top of the crane.

SOW 11.c Permits In addition to the height and crane restrictions addressed in Question 1 above, please confirm whether the project site itself is located within any airfield imaginary surface, runway clear zone, accident potential zone, or other airfield-related restricted/controlled area, and if so, identify any resulting construction restrictions (e.g., permitted construction hours, equipment staging limits, or additional coordination requirements). The project is located within an airfield imaginary surface, as seen on the image attached to the right. The maximum allowable height of structures is 25 meters of less.

・Regarding the Runway Clearance Zone The runway shoulder line is located at 150 meters.

・Regarding the Potential Aircraft Accident Area This area is the same as the runway shoulder line described above.

・Regarding Whether the Site Is Located Within Any Other Airport-Related Restricted or Controlled Areas JASDF are currently verifying this information and will provide an update once the confirmation process is complete.

SOW 11 Permits / Japanese Building CodeRegarding the Building Confirmation Application (Kenchiku Kakunin Shinsei): Since Matsushima Air Base is a JASDF (Japan Air Self-Defense Force) installation, please confirm whether this project will require a Building Confirmation Application or other administrative procedures under Japanese domestic law.As Matsushima is solely a JASDF base, any local, regional, or national regulations and codes apply. If there are any conflicting regulations within the contract that references US regulations, the Japanese regulation will take precedence. So, this project will require a Building Confirmation Application and any other applicable procedures under Japanese domestic law. We recommend consulting with the Building Guidance Division (or the relevant building authority) at the local municipal office regarding the specific building structure and its intended use. Similarly, we recommend consulting with the jurisdictional fire department regarding any applicable fire safety requirements and procedures.
Matsushima -
PMWH26-3531SOW 15.k ElectricalSOW paragraph 15.k requires new underground electrical service to each of the four buildings from one new 100 KVA transformer fed from the closest available primary connection point. Please confirm the following:
1. Whether an existing single-line diagram, electrical utility plan, load information, or available-capacity study can be provided.Updated site plans are provided showing primary and secondary electrical layout.

・Regarding Utility Load Capacity As we do not have detailed information regarding the total utility service load requirements within the U.S. area, we believe that the contractor responsible for procuring the transformer should be provided with the load information for the relevant equipment and facilities. Based on that information, they can coordinate the design and determine whether the planned capacity will be sufficient or insufficient.

・Regarding Cubicle Design Capacity In general, the cubicle is designed in accordance with the manufacturer's standard specifications to accommodate the required electrical load capacity.

・Regarding the Specifications of the New Cubicle Before placing the order for the new cubicle, JASDF would like to review the manufacturer's drawings and technical specifications. During the design period, the US Government will forward this information to JASDF.

・Regarding Single-Phase Power Requirements Depending on the specifications of the air-conditioning equipment, a separate single-phase transformer may be required if a 100 V single-phase power supply is needed for the air-conditioning control system or for warehouse lighting.

・Regarding the Use of a Scott Transformer If a Scott transformer is adopted instead of a standard single-phase transformer, it may be necessary to increase the capacity of the three-phase transformer accordingly.

Site Visit Clarification / Sink and Water SupplySink Installation and Water Supply: At the site visit, the Government explained that a sink is planned to be installed as one of the utility fixtures within the membrane warehouse fence line, with potable water to be drawn from a nearby water supply line. However, the current SOW and drawings do not include any requirements for the sink, water supply equipment, or water supply/drainage piping. Please also provide the planned incoming point(s) for all other new underground utilities (communications, water, and sewer, as applicable) to be extended to this project site, including the routing corridor from the nearest existing main to the facility. Please confirm whether an SOW or drawing revision (Amendment) reflecting this sink/water-supply requirement is planned to be issued.Updated site plans and SOW is provided detailing additional utility tie-ins and distribution. Communications requirements have been removed.
Site Visit Clarification / Oil Water SeparatorRegarding Installation of an OWS (Oil/Water Separator): At the site visit, the Government explained that an OWS (Oil/Water Separator) is planned to be installed outside the membrane warehouse fence line. However, the current SOW does not appear to include any reference to an OWS. Please confirm whether an SOW or drawing revision (Amendment) reflecting this item is planned to be issued.Updated site plans and SOW is provided including OWS and location.
Matsushima -
PMWH26-3531SOW 12.a Field Verification / SOW 13If unknown underground utilities or structures are encountered during construction, or if utility relocation becomes necessary, will such work be considered a change to the contract (e.g., contract modification or equitable adjustment), or shall it be included in the Contractor's base proposal?A situation such as this would result in "unforseen site conditions" and would require a modification to the contract. The government would request a proposal from the company to account for any additional work, when needed.
SOW 7 Geotechnical Engineering DataDoes the Government possess any existing geotechnical reports, soil boring logs, groundwater information, or foundation investigation data for the project vicinity that can be shared for proposal preparation?We do not have official geotechnical reports or soil boring logs but will provide the testing that USAF personnel have conducted into the as-builts for the pad. Groundwater is about 1 meter below ground-level.
SOW 15.b / SOW 7 Ground Conditions and Floor StructureRegarding Ground Conditions and the Warehouse Interior Floor Structure: The SOW requires the Contractor to perform a Geotechnical Subsurface Investigation. During the site visit, the Government explained that grading work within the fence line is already underway, with asphalt paving planned; however, based on site observations, the ground appeared to be relatively soft/weak. In addition, SOW paragraph 15.b states that new concrete strip footings will replace the existing asphalt pavement only along the footing footprint, leaving the remaining asphalt in place as the interior/exterior surface. Under this approach, only the strip-footing areas would have the existing asphalt removed, while the remaining warehouse interior and exterior floor areas would continue to use the existing asphalt pavement as-is. The Contractor is concerned that this approach may result in (1) pavement deformation or damage from future movement of heavy loads/equipment in and out of the warehouse, (2) moisture rising up through the asphalt, and (3) an increased long-term maintenance burden. Accordingly, the Contractor recommends that (1) the asphalt pavement within the warehouse interior be fully removed and the necessary geotechnical investigation and soil resistivity testing be performed, and (2) the warehouse interior floor be constructed as a concrete slab designed for the anticipated traffic loading. Please advise the Government's position on this recommendation.For Matsushima, Contractors may propose and bid with work to replace the warehouse flooring with concrete slabs and geotechnical investigations performed. The Government does not require this.
Matsushima -
PMWH26-3531SOW 4.e / SOW 6 Contaminated SoilSOW paragraph 4.e notes that the existing site is located within a previous natural disaster location and sea water inundation area. Please clarify:

1. Is any additional geotechnical testing, soil remediation, or corrosion-protection design for buried utilities and foundations anticipated as a result of this prior inundation, beyond standard UFC 3-220-01 requirements?

2. Consistent with SOW paragraph 6.a, please confirm that the Contractor is not required to assume any contamination or debris related to this prior event in the base bid proposal, and that disposal/remediation of any such material actually discovered during excavation will be treated as a change to the contract scope. 1. Corrosion and water protection is required for electrical utilities as the groundwater level is at a depth of roughly one (1) meter.

2. Correct, any disposal/remediation of contaminated material or debris will be treated as a change to the contract scope.

SOW 15.l Lightning Protection SystemRegarding the Lightning Protection System referenced in SOW paragraph 15.l, please confirm whether air terminals, down conductors, and grounding are to be integrated with the structure's steel frame or provided as a separate system.The Contractor may propose either method per the design they develop provided they meet all requirements in the SOW.
SOW 15.t Heating, Cooling and VentilationSOW paragraph 15.t requires climate control maintaining at least 40°F and no more than 60% relative humidity throughout the year, together with minimum two wall-mounted exhaust fans and interlocked motorized intake dampers for the large open storage bay. Please clarify:

1. Is mechanical cooling and heating required to maintain the 40°F/60% RH criteria throughout the full area of each building, or only in specific enclosed/conditioned spaces? Given the intended use of the building, the Contractor believes mechanical HVAC equipment may have limited practical effectiveness in this application — please advise the Government's view on this point.

2. Will the exhaust fans, intake louvers, and motorized dampers described in paragraph 15.t.3 be considered sufficient to satisfy the ventilation requirement for the storage bay, or is additional mechanical cooling/heating also required for that bay?

3. Please identify any enclosed rooms (e.g., office areas referenced in paragraph 15.r) requiring separate/independent climate control. 1. Climate conditions must be maintened throughout the entire facility for all four (4) tents. The intent behind climate control is to prevent corrosion and freezing for items stored within.

2. The Government confirms that humidity control is the governing requirement. Warehouses must remain above 40°F and below 60% relative humidity, and any mechanical measures necessary to maintain ≤60% RH shall be used. A maximum indoor temperature is not required, and mechanical cooling is not specifically mandated. Cooling shall only be incorporated if needed to achieve and sustain the humidity requirement under Matsushima summer conditions.

3. There are no enclosed or seperated rooms.

Matsushima -
PMWH26-3531SOW 15.o Climate ControlSOW paragraph 15.o requires R-30 roof insulation and R-19 wall insulation, or alternatively a double-membrane system, provided the required thermal performance is maintained. Please confirm:

1. Is the required thermal performance to be achieved defined by the 40°F/60% RH criteria of paragraph 15.t, or by a separate thermal performance metric (e.g., U-value/R-value)?

2. What data or calculations (e.g., comparative U-value/energy analysis) are required to demonstrate that a double-membrane alternative provides equivalent or better thermal performance for Government approval?The Government confirms that the R‑30 roof and R‑19 wall insulation values are not mandatory. A double‑membrane system is acceptable provided it achieves the required overall thermal performance necessary to maintain interior conditions, with humidity control (≤60% RH) being the primary governing factor. Any mechanical or envelope measures— including a double‑membrane assembly—must be capable of maintaining above 40°F and below 60% RH under Misawa conditions. No specific maximum U‑value or minimum effective R‑value is mandated beyond achieving this performance requirement.
SOW 15.e.1 Membrane Structure Eave HeightThe SOW requires membrane warehouses with a 9-meter eave height. However, if the building height could be reduced to the extent operationally acceptable, this would be advantageous in terms of structural design, constructability, and construction cost. Accordingly, the Contractor respectfully requests that the Government reconsider whether a reduced eave height of 7 or 8 meters would be acceptable.A 7 or 8 meter eave height is acceptable.
SOW 2.b Storm GutterSOW paragraph 2.b confirms that the new warehouses include building storm gutter systems. Please confirm the final discharge point/destination for the storm gutter and roof drainage system (e.g., connection to an existing storm drain system, infiltration, or discharge to grade), and provide the applicable stormwater design criteria to be used for sizing the gutters and downspouts. Please also note that the membrane warehouse type to be provided by the Contractor does not include gutters or downspouts as a standard feature; please advise whether this is acceptable, or whether a gutter/downspout system must be specifically incorporated into the design.Storm water collected on the pad and warehouses must discharge to the central u-drains and pass through the OWS. Rainwater runoff must not cause drainage nuisances, erosion or pooling off the pad other than the installed detention pond, and must not drain off base. If the contractor can demonstrate that water coming off the warehouses will flow to the u-drains and through the OWS, then a gutter/downspout system is only required over doorways to prevent water or ice accumulation from creating hazards.
Matsushima -
PMWH26-3531SOW 15.p Fence and GatesSOW paragraph 15.p requires two 6M (20FT) wide vehicle gates, two personnel gates, and a 2.1M (7FT) high security fence with 3-strand barbed wire, outriggers and additional supporting equipment/materials. Please confirm:

1. Whether the vehicle gates are to be manually operated or motorized/automated.

2. The required fence fabric type (e.g., chain-link mesh size and gauge), post material, and finish/color.

3. Whether the gates and fence must match an existing Matsushima Air Base standard fence type/color, and if so, please identify the applicable specification.

4. Whether any electronic access-control, card-reader, or intrusion-detection provisions are required at the gates under this contract.The Government confirms the following requirements for the SOW 15.p security fence and gates: Vehicle Gates – Manually operated. No motorized or automated gate operators are required. Fence Type – Chain‑link fabric, sized and gauged per Matsushima Air Base standard, with standard posts and finishes used across the installation. Fence Standard – Gates and fencing shall match the existing Matsushima AB standard type and color. The contractor shall follow the base‑standard specification provided during design coordination. Access Control – No electronic access‑control, card‑reader, or intrusion‑detection systems are required under this contract.
SOW 15.r.3 Interior / CommunicationsSOW paragraph 15.r.3 requires internal COM dedicated J-boxes 'as needed to support the office area' along with associated interior conduit runs. Please provide the anticipated office/administrative area size or layout (if defined) so that the required number and location of COM J-boxes, conduit runs, and the quad electrical receptacle circuit referenced in the same paragraph can be reasonably estimated for pricing purposes.The Government confirms that no internal communications (COM) requirements apply at Matsushima, and therefore no office‑area COM J‑boxes, interior COM conduit runs, or quad‑receptacle COM circuits are required under this contract. Paragraph 15(r)(3) does not trigger any office‑area communications build‑out because no office space is included in the warehouse concept and Matsushima AB has no COM requirement for these facilities.
SOW 18.a / 18.b AttachmentsSOW paragraph 18.a notes that the Project Location and Area Site Plans (Concept Drawings) will be provided at the RFP stage, and paragraph 18.b notes that previously constructed/design as-built drawings will be provided after award. Please confirm the anticipated timing for release of both attachments, and provide the final building footprint layout, gate locations, transformer location, and lighting layout — including any items instructed during the site visit/explanation meeting — to be reflected in the Contractor's design and proposal.Updated site plans will be released with these RFI responses.
Matsushima -
PMWH26-3531SOW 15.b and 15.n Main Utility Tie-inSOW paragraphs 15.b and 15.n state that if the main utilities are not in place prior to completion of the facility, the Contractor shall return after the main utilities are constructed to perform utility tie-ins. Please clarify:

1. Please provide the full scope and details of the main utilities that are outside this contract.

2. Please also advise the anticipated completion date of the main utilities.

3. Will the Contractor be entitled to an equitable adjustment for remobilization, additional supervision, and schedule impacts associated with returning to perform the utility tie-ins?

4. Will the utility tie-in work be included within this contract's 150-day construction performance period, or will it be performed under a separate authorization after completion of the main utility work? 1. The updated SOW reflects Contractor-installed primary electrical conduit and cable, secondary electrical cable, transformer, and water line installation as detailed in the site plans. The Government will only be installing conduit for secondary electrical and storm drainage utilities.

2. The Contractor is responsible for installing utilities listed in the SOW. Government installed utilities will be complete prior to award.

3. The contractor should include all required utility work in their bid. If there are any unforseen circumstances, equitable adjusments will be negotiated with the Government.

4. All work is within the contract's 150-day construction performance period.

Matsushima -
PMWH26-3531-Are the four electric roll-up doors to be installed across four separate tent warehouses? Does this mean a total of 16 doors are required (4 doors × 4 warehouses)?Yes, there will be four (4) electrical doors (sliding or roll-up) for each tent warehouse, for a total of sixteen (16) main entrance doors. There are also four (4) personnel doors per tent for a total of sixteen (16) personnel doors. Total electrical and personnel doors are thirty-two (32).
-What are the specifications for the four 200mm doors? Does "200mm" refer to the thickness? These are doors that people cannot pass through—is that acceptable?The 200mm dimensions are for bollards at each sliding/roll-up door. The personnel doors can be a standard, off-the-shelf size complete with a steel frame.
Matsushima -
PMWH26-3531Can the four warehouses be designed with identical layouts and systems to simplify fabrication and maintenance?Simplification to reduce cost and maintenance is welcome. Electrical tie-ins will be different depending on the side of the pad, but the design can be mirrored.
Can the Government confirm whether any deviations from the concept layout shown in the drawings are acceptable if they improve constructability while maintaining all functional requirements?Yes, the Contractor can recommend deviations from the concept layout if it improves constructability while meeting requiring. The Government will review and provide acceptance or refusal of the deviation.
Is there any anticipated future expansion that should be considered during design?There is no anticipated future expansion
Are there any known groundwater conditions or high-water-table concerns due to the site's proximity to the coast?The groundwater is roughly one (1) meter deep.
Can the Government provide any existing utility records before proposal submission?It is the responsibility of the Contractor to test and verify the location of existing utilities. There are known high-voltage, airfield lighting, and communications utilities along the main JASDF road that the project ties into. Utility verification may be done through various methods, such as non-destructive surface scanning with electromagnetic locators or ground-penetrating radar, or carefull digging for utility markers or tracer wires. JASDF will not turn off the electrical utilities running along the road.
Matsushima -
PMWH26-3531Is unexploded ordnance clearance already completed for the project area?Unexploded ordnance is not expected in or near the project area.
Are utility potholing and GPR investigations permitted immediately after award?Yes, with local base coordination and approval
Can the Government confirm that equivalent membrane manufacturers outside Japan are acceptable provided they meet all structural and performance requirements?The Government prefers Japanese manufacturers for maintainability, local support and ability of the structure to match the rest of the base and local area.
Is MSAJ certification mandatory, or will equivalent internationally recognized certifications be accepted?The Contractor can propose equivalent certifications for Government review and approval.
Is there any preferred membrane thickness or fabric weight?As long as the designed membrane shelter can meet all requirements, the Contractor can propose the membrane thickness and fabric weight.
Is there any required minimum design life for the membrane system?In accordance with standard commercial practices, the following warranty periods will be used.

Membrane Fabric: A minimum 10-year manufacturer's warranty is required. The warranty must cover UV degradation, fabric discoloration, and seam integrity under normal weather conditions.

Structural Steel: A minimum 10-year structural warranty is required. The steel framework must be able to withstand coastal environments, and the warranty must cover structural failure and structural degradation beyond normal weathering.

Roll-Up/Sliding Doors: A minimum 2-year commercial warranty (or manufacturer’s standard warranty, whichever is greater) is required for a roll-up door, covering the mechanical door assembly, tracking, and the motorized operator.

A 5-year warranty is required for a sliding door.

HVAC Equipment: A minimum 1-year parts and labor warranty for the entire system, with a 5-year warranty on the compressor, is required.

Electrical Equipment: A minimum 1-year standard commercial warranty is required for all electrical distribution components, transformers, and switchgear.

Matsushima -
PMWH26-3531Can insulated metal wall panels be incorporated below the membrane where beneficial?Yes, insulated metal wall panels may be incorporated below the membrane where beneficial. The Contractor shall submit reasoning for any changes or additions to the Government for review and approval through the design phase.
Is the specified minimum 9-meter eave height measured to the underside of the structural frame or to the membrane?The updated minimum eave height of 7M is measured from the bottom of the eave strut or the lowest point where the sidewall meets the roof membrane.

Due the eave height, the actual vertical clearance inside the building (clear height to the underside of the lowest structural beam or haunch) is reduced by the depth of the structural steel member, therfore the Contractor must submit a sectional drawing showing both the Eave Height and the Effective Clear Height for approval by the Government.

What minimum roof live load should be used if Japanese codes provide multiple options?The most stringent roof live load for the Miyagi region shall be used.
Is the Contractor free to select the foundation system based on the geotechnical investigation?Yes, the Contractor can recommend a foundation system based on the geotechnical investigation
Can the existing asphalt remain beneath the warehouse except within footing excavation limits or does the whole warehouse require concrete slab?The existing pavement shall remain within the warehouse except within the footing excavation limits
Is maintaining 40°F the the only and minimum requirement, or should there be indoor design temperature used during summer?The Government confirms that humidity control is the governing requirement. Warehouses must remain above 40°F and below 60% relative humidity, and any mechanical measures necessary to maintain ≤60% RH shall be used. A maximum indoor temperature is not required, and mechanical cooling is not specifically mandated. Cooling shall only be incorporated if needed to achieve and sustain the humidity requirement under Matsushima summer conditions.
Matsushima -
PMWH26-3531Is redundancy required for HVAC equipment?Redundancy is not required for HVAC equipment
What primary voltage, cable size and cable type is available at the connection point? Can we please get the picture of the inside of manhole of the connection point?・Regarding the Connection Point (Existing Manhole East of the Control Tower)

Voltage: 6,600 V Cable Size and Type: 6kV-CET22 (it is believed to be the E-T type, although this should be confirmed) Preferred Size of New Conduit: We would prefer either FEP65 or FEP80 conduit; however, the final conduit size will depend on the Contractor's design.

Photographs of the Interior of the Manhole at the Connection Point: Since the manhole must first be drained before photographs can be taken, obtaining the photos will require some time. JASDF are planning to carry out the drainage work on August 24, and therefore expect to be able to provide a response, including the photographs, on August 25.

Will utility shutdowns be permitted if required for transformer installation and if so, for how long and how advance do we have to push the notice? ・Regarding Power Outage Periods Power outages are generally scheduled on weekends between 0815 and 1600 hours.

・Regarding Advance Notification Providing notification to the US Government and JASDF two months in advance.

・Regarding the Power Outage Work Plan At that time, the Contractor must submit a Power Outage Work Plan to the US Government to submit to the base's Electrical Chief Engineer (or Electrical Safety Manager) for review.

This will allow JASDF to verify that the planned work procedures and safety measures are adequate and do not present any concerns.

Are arc-flash studies required?Yes
Is emergency power required for any building systems?Emergency power is not required for any building systems
Is any Fire Protection system required?Fire detection and notification is required
Matsushima -
PMWH26-3531Can excavated material be reused or stored onsite if laboratory testing confirms suitability?Yes, excavated material can be reused or stored onsite if laboratory testing confirms suitability and there is adequate laydown space.
Does the Government anticipate contaminated groundwater despite stating contaminated soil is not expected?The Government does not anticipate contaminated groundwater.
What is the expected processing time for base access passes after award?Long-term passes should be submitted two weeks prior to desired use.
Will weekend work be permitted?Contractors must submit an overtime work request to the Government representative to then forward to JASDF. As it is a request it may be denied.
Will night work be permitted if requested?Contractors must submit an overtime work request to the Government representative to then forward to JASDF. As it is a request it may be denied.
Can contractor use the same laydown and staging areas as are used at the moment from Government?It may be used. However, please ensure that the required base access procedures are completed in advance.
Matsushima -
PMWH26-3531Will early procurement submittals be accepted?The Government will allow separate, early-procurement submittals for long-lead items (specifically the membrane structures, structural steel, transformer, fire-alarm equipment, and motorized gates) immediately after award. However, all early procurement is conducted at the Contractor's sole financial and schedule risk. Any subsequent changes to the approved 100% design that impact these procured items shall be corrected at the Contractor's expense, with no adjustment to the contract price or performance period.
Can procurement of long-lead membrane structures begin immediately after contract award, prior to the 65% design approval? Specifically, would the Government allow the Contractor to submit the membrane structure submittal separately and in advance of the 65% design package to avoid procurement delays?The Government will allow separate, early-procurement submittals for long-lead items (specifically the membrane structures, structural steel, transformer, fire-alarm equipment, and motorized gates) immediately after award. However, all early procurement is conducted at the Contractor's sole financial and schedule risk. Any subsequent changes to the approved 100% design that impact these procured items shall be corrected at the Contractor's expense, with no adjustment to the contract price or performance period.
If Government review exceeds the specified review period, will contract time be extended?For any government delays, the contractor may request an extension and request for equitable adjustment where necessary.
What warranty period is required for:

Membrane fabric Structural steel Roll-up doors HVAC equipment Electrical equipment In accordance with standard commercial practices, the following warranty periods will be used.

Membrane Fabric: A minimum 10-year manufacturer's warranty is required. The warranty must cover UV degradation, fabric discoloration, and seam integrity under normal weather conditions.

Structural Steel: A minimum 10-year structural warranty is required. The steel framework must be able to withstand coastal environments, and the warranty must cover structural failure and structural degradation beyond normal weathering.

Roll-Up/Sliding Doors: A minimum 2-year commercial warranty (or manufacturer’s standard warranty, whichever is greater) is required for a roll-up door, covering the mechanical door assembly, tracking, and the motorized operator.

A 5-year warranty is required for a sliding door.

HVAC Equipment: A minimum 1-year parts and labor warranty for the entire system, with a 5-year warranty on the compressor, is required.

Electrical Equipment: A minimum 1-year standard commercial warranty is required for all electrical distribution components, transformers, and switchgear.

Are BIM models required as part of the final deliverables?No, the Government does not need BIM models.
Are operation and maintenance manuals required in both English and Japanese?Yes , operation and maintenance manuals must be in both English and Japanese
Matsushima -
PMWH26-3531Can the Government provide us with dwg. files of exising layout?Yes, the government will provide as-builts and design files in dwg. files after award.
Shall the newly installed 100kVA Transfromer include main breaker and 4 sub breakers – one for each warehouse.That is an acceptable quantity, but the Contractor may propose alternative configurations during the design period.
As discussed on the site vist, we shall install additional conudit going from connection power point manhole to the transformer. What size should that conduit be?Preferred Size of New Conduit: We would prefer either FEP65 or FEP80 conduit; however, the final conduit size will depend on the Contractor's design.

The electrical system parameters for this project shall be based on the existing Japanese standard distribution used at Matsushima, to support long‑term maintainability. The Government will provide the available primary voltage, phase, frequency (50 Hz), fault current, grounding arrangement, and required secondary utilization voltages during design coordination. All warehouse electrical design shall match the Matsushima‑standard system to the maximum practical extent, ensuring compatibility with existing infrastructure and simplifying maintenance over the life of the facility.

The Government will already install the conduits going from manhole close to Transformer to each warehouse – 3 conduits size 4” per building? Can you please send us the as-builts from government installation on this project. Will the basin be installed by the governmentThe Government will install three (3) conduits each per warehouse, each at a diameter of 4" and as-builts will be provided upon completion of troop construction. The stormwater retention pond will be constructed by the government. The electrical manhole will be installed by the contractor.
To install the oil water separator please provide us with the drainage size so we can properly size oil water separator.The OWS will receive water from the government installed u-drains and release water into an open v-ditch. The u-drain sizes are 33cm wide, 29cm tall and 60cm long. OWS sizing shall be based off a one-in-10-year rain for the region or able to process about 56 liters per second of storwater runoff for the pad.
The SoW calls for two (2) wide vehicle gates and two (2) personnel gates, we would kindly ask the governemt to mark the location of them on the drawings.The location of the vehicle and personnel gates are on the access with personnel gates to either side of the main vehicle gates, as marked in the site plans.
Matsushima -
PMWH26-3531Based on the drawings, approximately 350 meters of new fencing is required. Please confirm whether the only applicable requirement is to provide a 2.1 m (7 ft) high security fence topped with three strands of barbed wire, or whether any additional material, coating, fabrication, installation, or security requirements apply. Additionally, may the fence be manufactured outside Japan?Fence Type – Chain‑link fabric, sized and gauged per Matsushima Air Base standard, with standard posts and finishes used across the installation. Fence Standard – Gates and fencing shall match the existing Matsushima AB standard type and color. The contractor shall follow the base‑standard specification provided during design coordination. Access Control – No electronic access‑control, card‑reader, or intrusion‑detection systems are required under this contract.

The Government prefers the fence be manufactured within Japan, but the Contractor may prospose materials manufactured outside Japan for Government review and approval.

Please confirm that all the gates (personnel and vehicle) shall be man operated only?The perimeter gates shall be manually operated.
Is there to be expected to install light fixtures on the fence as well or only on the membrane structures’ exterior at each door opening location with the fixtures downward facing.For Site lighting, eight (8) metal halide, 400 watt, aluminum pole, 20' high are required.
We understand that the intent is to install new strip footings only along the warehouse footing footprints, while leaving the existing asphalt pavement as the interior and exterior surface. However, the existing asphalt is sloped, and it is essential that the warehouses be installed level. This will create elevation differences between the interior asphalt surface, the strip footings, and the roll-up door entrances. Therefore, additional concrete transitions or ramps will be required at the roll-up doors. Please confirm whether the Government would accept, as an alternative solution, the installation of a level concrete slab across the entire footprint of each warehouse, together with the necessary concrete transitions or ramps connecting the slab to the existing asphalt at the roll-up doors. A full concrete slab would provide a suitable level and stable base for the warehouses.
Drawings are attached for reference ----------------->The Contractor can propose additional concrete work, but the Government is not requiring it.
Matsushima -
PMWH26-3531During the site visit, it was discussed that a water supply line of up to 1 inch would be connected to the existing water line near the site, with the new connection installed downstream of the flow meter. Please clarify whether the flow meter and tee connection are included in the Contractor’s scope or will be provided and installed by the Government. Additionally, please indicate the exact desired location of the water supply point/faucet at the site.The flow meter and tee connection are included in the Contractor's scope of work. The location is detailed in the updated site plans.

image1.jpeg image2.jpeg