This document summarizes a solicitation for electrical upgrades at two military sites in Alaska. The United States Air Force seeks contractors to expand power infrastructure at the Donnelly Training Area and former Gerstle River Operations Site, including installing a distribution network from existing grid lines and providing transformers and power services. Bids are due by September 12, 2022 for the firm fixed price contract valued between $1 million and $5 million. Only small businesses may apply for this total set-aside opportunity. Questions are due by August 17th, with responses published as amendments on SAM.gov where the full solicitation is also available. Contractors must register in SAM to be eligible for award.
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Replacement of Canopies B2200 RFI's and Responses Document
Project #: FTQW 22-0506 Solicitation# FA500422B0012 Project Name: DTA & YTA Electrical Improvements Date: 7 September 2022
ITEM # Reference Document Questions Reference
Document Government Response Response Date
EXAMPLE Statement of Work (SOW) EX:
1 PWS
The Delivery dates for the DTA sites is called out for 15 Oct 22. Section F - Deliveries or Performance. Provide 385 days for all bid line items. Transformers and fiberoptic cables all have a very long lead times, which would make it impossible to meet the 15Oct 22 date.
Delviery dates will not be able to be determined until after the engineering and product approval have been received. Please clasify the completion time frame extension process for the DTA bid items.
The Government understands the delays on large transformers and other related items. The contractor shall proposae a completion date in 2023.
2 Solicitation Request a 2-week extension on the bid date to allow time to source the transformer and engineering support for the project design requirements.
There will be an extension to the solicitation that will be included as an amendment on SAM.gov
3 PWS
Figure 8 for the GROS site layout shows the intended route of the new power lines to feed the 500KVA transfornmer. The drawing is not showing the completed route to the GVEA power lines along the Alaska Highway and does not include a drawing to scale shown. Can you provide a complete scaled drawing showing the entire length of the line installation or provide an estimated length to be used for bidding this scope of work?
The GROS site is going to be removed from the solicitation due to condition of the site at this time. Addition of the Yukon Training Area (YTA) will be added to the solicitation with an additional SOW.
4 PWS
Were there any questions asked pertaining to the underground primary being direct buried or in a specific type of conduit. See commnets on next page.
5 PWS
What are the approximate distances for the powerline runs at the DTA?
North Entrance (64.0099418, -145.6787730) to North Pad(64.0125876,- 145.6681328): 1954ft South Entrance (64.008275, -145.677708) to South Pad(64.011313,-145.668669):
1537 ft West Entrance(64.011313, - 145.679513) to West Pad(64.010232,-145.688940): 1540 ft 33Mile Loop Road Distance(64.025266, -145.697010): 6916 ft
6 SOO
In addendum 2 pg 5/58 under requirements it identifies what appears to be the overhead line scope of work. For clarification on the bid scope of work between the GVA 25kv OH line and the GROS site. (11) new poles, (7) new cross arms, (6) miles x 3 OH conductors. Any additional poles, cross arms and wire would be added as a change order?
The YTA-SOO has been added to this solicitation. The GROS site has been removed from the scope of work at this time and may be reconsidered in a separate solicitation at a later date. The YTA can be accessed through Johnson Rd in Salcha, Alaska behind Eielson AFB. The Government intends to award as a firm fixed price contract. Any questions after contract award in regards to differing site conditions will be submitted to the Government as an RFI. The Government will either give clarification or process a change in accordance with contract terms.
1 of 1 9/7/2022
Question 4 (Answer):
Direct buried should be fine except for sections where the lines cross roads. Road crossing sections should meet the below standards as taken from the dirt work contract:
3.5 Buried utility lines: There are several buried utility lines in the construction area. The contractor will need to ensure that they are protected during construction.
a. The 59th Signal Battalion owns a direct buried copper cable following the west side of 33-mile loop, which crosses the intended path of new roadways to the West Ops site. Where a newly constructed roadway crosses this cable, the cable will need to be excavated (by hand or hydrovac) and sleeved with a split 4" conduit and concrete encased 6 feet beyond the edges of the road.
For future expansion (and/or bringing services to the new pads), the conduit should contain (2) 1.25" innerducts. An additional, empty 4" conduit is also requested for future expansion. The ends of the conduits should be capped to prevent infiltration and marked with a 3M EMS ball marker and Brady stake.
b. AT&T owns a direct buried fiber cable following the east side of 33-mile loop, which crosses the intended path of new roadways to the Mx site, North, and South OPS sites. Where newly constructed roadway crosses this cable, they will need to get with AT&T to determine AT&T's requirement (it will likely be the same or similar to ours). In addition to AT&T's requirement, 59th requests a 4" conduit concrete encased 6 feet beyond the edges of the road, and containing (3) 1.25" innerducts. The ends of the conduit should be capped to prevent infiltration and marked with a 3M EMS ball marker and Brady stake.
c. Concrete used for encasement needs to be of appropriate grade for the heavy trucks intended. At minimum, it should be 3000 psi with a minimum coverage of 3 inches of concrete below, above and on all sides of the conduit. Recommend requiring the installer to use vibration when setting the concrete to ensure adequate fill - this is a lesson we have learned with failed concrete installation.