Atch_11_-_01_14_00.pdf
PDF 16 KB Posted
- Attached to
- Repair CHPP Ash Handling System Controls Federal contract opportunity
- Solicitation number
- FA500419BA015
About this file
Amendment 0001 - Attachment 11 - Spec 01 14 00
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Solicitation_Amendment_-_FA500419BA0150002.pdf | ||
| Atch_1_-_Specification_with_Sequence_of_Operations,_I-O_List,_&_Data_Sheets.pdf | ||
| Solicitation_Amendment_FA500419BA0150002_SF_30.pdf | ||
| Atch_9_-_Partial_Design_Analysis.pdf | ||
| Atch_8_-_Q&A_Responses.pdf | ||
| Atch_13_-_01_73_29.pdf | ||
| Atch_10_-_BoD_Rosemount_Level_Transmitters.pdf | ||
| Atch_14_-_02_41_00.pdf | ||
| Atch_16_-_Sequence_of_Operations,_I-O_List,_&_Data_Sheets.pdf | ||
| Atch_15_-_40_95_00.pdf | ||
| Atch_7_-_Wage_Determination_(Revised).pdf | ||
| Atch_12_-_01_50_00.pdf | ||
| Solicitation_Amendment_FA500419BA0150001_SF_30.pdf | ||
| Solicitation_Amendment_-_FA500419BA0150001.pdf | ||
| MFR_for_FBO.pdf | ||
| Solicitation_-_FA500419BA015.pdf |
Show all 16
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CHPP REPAIR ASH HANDLING CONTROL SYSTEM SECTION 01 14 00
FTQW 12-1008
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 14 00
WORK RESTRICTIONS
11/11
PART 1 GENERAL
1.1 SPECIAL SCHEDULING REQUIREMENTS
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
1.2.1.1 No Smoking Policy
1.2.2 Working Hours
1.2.3 Work Outside Regular Hours
1.3 ACCESS TO CONTROLLED AREAS
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 14 00 Page 1
SECTION 01 14 00
WORK RESTRICTIONS
11/11
PART 1 GENERAL
1.1 SPECIAL SCHEDULING REQUIREMENTS
a. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work. Specific items of work to which this requirement applies include:
(1) Based on operation needs, up to two boilers at a time will be provided to the contractor to install control systems for the associated fly ash and bottom ash controls. Existing control systems must be maintained in operational condition until replaced controls have demonstrated performance. 4 boilers must be available at all times. 1-2 weeks per boiler are anticipated to be out of service. On-site construction to be performed 01 May - 30 September 2019.
(2) Bottom Ash Silo controls are completely redundant. Only one system can be down at a time for control replacement. New system must demonstrate adequate performance before other system can be replaced. Two weeks are anticipated for silo control replacement.
(3) Fly ash silo unloading controls require complete shut down for replacement. The fly ash can be routed to the Bottom Ash silo through use of a bypass (coordinate with plant). The fly ash silo can be down for 4 days for control replacement. Separate 4 day shutdowns can be done for the fly ash. The silo must be emptied before work starts by the base personnel.
(4) Bottom Ash unloading controls require complete shut down for replacement. The bottom ash can fill the silo for up to 4 days depending on load. Controls shall be removed, replaced and tested within 4 days.
b. The Eielson Central Heat and Power Plant will remain in operation during the entire construction period. The Contractor must conduct his operations so as to cause the least possible interference with normal operations of the activity.
1.2 CONTRACTOR ACCESS AND USE OF PREMISES
1.2.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.
SECTION 01 14 00 Page 2
1.2.1.1 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.
1.2.2 Working Hours
Coordinate working hours with plant , excluding Government holidays.
1.2.3 Work Outside Regular Hours
Work outside regular working hours requires coordination with plant and Contracting Officer approval. Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer.
1.3 ACCESS TO CONTROLLED AREAS
The Contractor shall comply with all Eielson AFB security and access to controlled area procedures and requirements when and if necessary access is absolutely necessary. Initial procedures and requirements will be provided to the Contractor at the Pre-Construction Conference.
PART 2 PRODUCTS
Not Used.
PART 3 EXECUTION
Not Used.
-- End of Section --
SECTION 01 14 00 Page 3
| WORK RESTRICTIONS |
| 01 14 00 - WORK RESTRICTIONS |
| PART 1 GENERAL |
| 1.1 SPECIAL SCHEDULING REQUIREMENTS |
| 1.2 CONTRACTOR ACCESS AND USE OF PREMISES |
| 1.2.1 Activity Regulations |
| 1.2.1.1 No Smoking Policy |
| 1.2.2 Working Hours |
| 1.2.3 Work Outside Regular Hours |
1.3 ACCESS TO CONTROLLED AREAS