PAST/PRESENT PERFORMANCE QUESTIONNAIRE (PPQ)

WHEN FILLED IN THIS DOCUMENT IS SOURCE SELECTION SENSITIVE INFORMATION IAW FAR 2.101 & 3.104

SECTION 1: CONTRACT IDENTIFICATION

A. Contractor: __________________________________________

B. Contractor Cage Code: _________________________________

C. Contract number: ______________________________________

D. Contract type: ______________________________

E. Was this a competitive contract? Yes _____ No _____

F. Period of performance: _________________________________________________________

G. Initial contract cost: $____________________________

H. Current/final contract cost: $_______________________________

I. Reasons for differences between initial contract cost and final contract costs: ____________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________________

J. Description of service provided:

SECTION 2: CUSTOMER OR AGENCY IDENTIFICATION

A. Customer or agency name: __________________________________________________________

B. Customer or agency description (if applicable): __________________________________________ C. Geographic description of services under this contract, i.e. local, nationwide, worldwide, other commands:

SECTION 3: EVALUATOR IDENTIFICATION

A. Evaluator's name: __________________________________________________________________

B. Evaluator's title: ___________________________________________________________________

C. Evaluator's phone/fax number: ________________________________________________________

D. Length of time (number of years/months) evaluator worked on subject contract: _________________

SECTION 4: EVALUATION

Please indicate your satisfaction with the contractor’s performance by placing an “X” in the appropriate block using the scale provided to the right of each question. This scale is defined as follows:

CODEPERFORMANCE RATING
BBLUE/EXCEPTIONAL - During the entire period, the contractor met and exceeded many of the requirements of the contract and consistently performed at a superior level. Performance was accomplished with very few minor problems, and the contractor took immediate and effective corrective actions for those problems that did occur.
PPURPLE/VERY GOOD - During the entire period, the contractor met and exceeded some of the requirements of the contract and consistently performed very well. Performance was accomplished with some minor problems, and the contractor took timely and effective corrective action for those problems that did occur.
GGREEN/SATISFACTORY - During the entire period, the contractor met the requirements of the contract and consistently performed at an acceptable level. Performance was accomplished with some problems, and the contractor took effective corrective action for those problems that did occur.
YYELLOW/MARGINAL – During the entire period, the contractor did not always meet some of the requirements of the contract and intervention was required to continue performance. There were instances where performance was at a less than acceptable level; performance was accomplished with some problems and some corrective actions appear only marginally effective or were not fully implemented.
RRED/UNSATISFACTORY – During the entire period, the contractor did not meet the requirements of the contract and performance was at an unacceptable level. There were a number of serious problems that required extensive oversight and involvement, and corrective actions were either ineffective or non-existent.
N/ANOT APPLICABLE - Unable to provide a rating. Contract did not include performance for this aspect, or information was not available. Do not know.
Past Performance Questions
B
P
G
Y
R
N/A

1. How well did the contractor meet the technical requirements of the specification?

2. How was the quality of technical data preparation efforts?

3. How adequate/effective were the contractor’s environmental safety procedures?

4. How effective was overall contract management (including ability to effectively lead, manage, control and deliver on time)?

5. How reasonable and cooperative was the contractor when dealing with program staff (including the ability to successfully resolve disagreements/disputes)?

6. How timely and effectively did the contractor resolve contract problems without extensive customer guidance?

7. How well did the contractor understand/comply with customer objectives and technical requirements?

8. How successfully did the contractor respond to emergency and/or surge situations?

9. How did the contractor manage quality/effectiveness of sub-contracted efforts?

10. How effective was the contractor’s material management (including Government Furnished Property or Material)?

11. How effective was the contractor’s acquisition management?

12. Of what benefit to the customer were contractor proposed alternative methods that reduced cost, improved maintainability or other factors?

13. To what degree did the contractor implement responsive/flexible processes to improve quality and timeliness of requirements?

14. How smoothly did the contractor transition resources and personnel?

15. How effective was the contractor in maintaining continuity of mission support while transitioning/phasing in resources and personnel to support other efforts?

16. How effectively was the contractor able to hire/apply a qualified workforce to this effort?

17. How effectively was the contractor able to retain a qualified workforce on this effort?

18. How accurately did the contractor forecast contract costs for base contract and any modifications?

19. How well did the contractor meet forecasted costs and perform within contract costs for base contract and any modifications?

20. How successfully did the contractor alert the Government of unforeseen costs before they occurred?

21. How sufficient and timely was the contractor’s cost reporting?

2. Please discuss every response for which you indicated B/E (Blue/Exceptional), Y/M (Yellow/Marginal) or R/U (Red/Unsatisfactory) in response to the questions above (use additional sheets, if necessary).

3. Government Contracts Only: Was this contract partially or completely terminated for default or convenience or are there any pending terminations?

Yes___Default___Convenience___Pending Terminations___
No ___

If yes, please explain (e.g., inability to meet cost, performance, or delivery schedules).

SECTION 5: NARRATIVE SUMMARY

Would you have any reservations about soliciting this contractor in the future or having them perform one of your critical and demanding programs?

Please provide any additional comments concerning this contractor’s performance, as desired.

Evaluator’s Signature Date

SUBCONTRACTOR CONSENT:

We are currently participating as: CIRCLE ONE ANSWER: member of a joint venture, subcontractor, teaming partner, or key person with the prime contractor identified above in response to the referenced Request for Proposal. We understand that the Government is placing increased emphasis on past performance in order to obtain best value in source selections. In order to facilitate the performance confidence assessment process, we are signing this consent form to allow you to discuss or performance information with the prime contractor during the source selection process.

________________________ (Signature) ________________________ (Name and Title) (Signature and Title of individual who has the authority to sign for and legally bind the company)

Thank you for your prompt response and assistance!

Please return this completed questionnaire to: SSgt Nicholas Bastiani or MSgt Gregory Johnson Mailing Address: 2310 Central Ave Bldg 2258 Eielson AFB, AK 99702 FAX to: 907-377-2547 E-Mail to: nicholas.bastiani@us.af.mil or gregory.johnson.30@us.af.mil

JA-3 Past Performance Questionnaire (11 April 2012)

FA5004-12-R-C003

Base Paving IDIQ

Other files

File Type Posted
Amendment FA5004-12-R-C003-0003 Conformed Copy.pdf PDF
Site Visit Q A - 12-R-C003 Base Paving IDIQ.pdf PDF
JA-1 Offer Schedule.xls.xlsx XLSX spreadsheet
Amendment FA5004-12-R-C003-0003.pdf PDF
TAB 10--AC Joint Detail.pdf PDF
TAB 1--EAFB fillable borrow Pit Review sheet.doc DOC document
TAB 8--Micro Surfacing Spec.pdf PDF
TAB 5 Spill Placard.ppt PPT presentation
TAB 9--Dow 888 Sealant info..pdf PDF
TAB 13--AF Form 3000.pdf PDF
TAB 4 Spill Reporting Plan.doc DOC document
TAB 2--AF Form 103.pdf PDF
TAB 12--AF Form66.xls XLS spreadsheet
TAB 6 CrackMaster 3405LM.pdf PDF
TAB 3 Concrete and Construction Debris Disposal Form.doc DOC document
TAB 11--Sidewalk Spillway Details.pdf PDF
TAB 7-- High Fracture D1 Base Course spec.pdf PDF
Amendment 02.pdf PDF
Amendment 01.pdf PDF
JA-6 Wage Determination- 25 May 2012.docx DOCX document
JA-4 - Past Performance Worksheet.docx DOCX document
JA-2 IDIQ Spec20 April 2012.docx DOCX document
JA-6 Wage Determination- Building and Heavy.docx DOCX document
JA-1 Offer Schedule.xls.xlsx XLSX spreadsheet
JA-5 - Financial Reference Sheet.docx DOCX document
FA5004-12-R-C003 Paving Solicitation 13 June.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .