FA5004-12-R-C001 JA-1 Statement of Work
View the file
Other files for this federal contract opportunity
Show all 13
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA5004-12-R-C001
Attachment 1
JA-1 Specifications (Statement of Work) Page 1 of 31
STATEMENT OF WORK
FOR
SIMPLIFIED ACQUISITION OF BASE ENGINEER
REQUIREMENTS
Solicitation No: FA5004-12-R-C001
Contract No:
03 NOVEMBER 2011
Prepared by 354th Civil Engineer Squadron
Programs Flight
Eielson AFB, Alaska
JA-1 Specifications (Statement of Work) Page 2 of 31
Table of Contents
Paragraph Title
1 Description
2 Unit Price Book
3 Technical Design Support Capabilities
4 Offers
5 Standard vs Non-standard Work Hours
6 Economic Price Adjustment
7 Contract Start-up Period
8 Contractor Provided Materials
9 Task Order Procedures
10 Performance of Work by the Contractor
11 Final Inspections and Acceptance
12 Government-Furnished Equipment/Materials
13 Security Requirements
14 General Information
15 Work by the Government
16 Scheduling Work
17 Utilities, Work Related
18 As-Built Drawings and Real Property Updates
19 Government-Provided As-Builts
20 Environmental Protection
21 Construction Site Maintenance
22 Grounds Maintenance
23 Construction Signs
24 Barriers and Enclosures
25 Noise Control
26 Equipment On the Site
27 Access Roads and Trucking
28 Elevators
29 Safety & Health
30 Recording & Preserving Historical and Archeological Finds
31 Office Location
32 Professional Registration and Certifications
33 Communications
34 Government Liability for Loss or Damage to Contractor Property
35 Construction Requirements
36 Data for Warranty/Guarantee Items
37 Quality Control
38 Waste/Borrow Pit for Clear AS
Attachments:
1. Example Project
2. Environmental Compliance Requirements Checklist
JA-1 Specifications (Statement of Work) Page 3 of 31
1. DESCRIPTION:
1.1 The contract is for a broad range of maintenance, repair, and minor construction work on real property at Eielson AFB, Alaska; and Clear AFS, Alaska. The work is required to support the operations of the Base Civil Engineer, 354 Civil Engineer Squadron (CES) and the Civil Engineer, 13 SWS, Clear AS.
1.2 The contract will be an indefinite delivery indefinite quantity (IDIQ) type contract and will require a wide variety of individual construction tasks as described in the Technical
Specifications.
1.3 The firm, fixed price for line items of each individual construction task shall be taken from the most current RS Means Facilities Construction Cost Data. Line items shall be selected that most accurately and completely represent the work being accomplished in a task order scope. The government and contractor shall use e4Clicks Professional Project estimator system or equal as described in section 8.3 to develop proposals.
1.4 During the contract period, the SABER project manager will identify specific requirements on individual task orders and generate a conceptual scope of work
(approximately 15% design). The contracting office will issue task orders to the contractor for accomplishing the identified work. The contractor shall be required to furnish all equipment, materials, and personnel necessary to complete designs, accomplish construction, and manage the task orders in the time period and to the quality required in the contract.
1.5 The contractor shall prepare a proposal to include a complete scope of work, design, construction drawings, schedules, and cost estimate. The Technical Specifications shall be used as the minimum standard for building code compliance, quality and general requirements applicable to every project. The pricing database will be used as the basis for establishing the value of the work. In preparing the proposal, the contractor shall research existing record drawings and independently conduct as many site visits as necessary to have a satisfactory knowledge of the site conditions that can affect the work or its cost. The contractor's proposal must be complete and supported by necessary documentation to indicate adequate engineering, planning and cost estimating has been performed to accomplish the requirement. Documentation required in the proposal includes: basis of design; engineering calculations supporting design approach; detailed scope of work; scaled sketches or drawings reflecting floor plans, elevations, sections, construction details, equipment layout, finish schedules; construction or performance time schedules; material submittal schedules; cost estimates identifying tasks and calculations supporting quantities of materials required to perform each task.
Construction schedules will be based on a notice to proceed date given by the government.
1.6 Work will require expertise in various trades to include, but not be limited to, carpentry, road repair, roofing, excavation, interior renovation, electrical, plumbing, HVAC, sheet
JA-1 Specifications (Statement of Work) Page 4 of 31 metal, welding, painting, demolition, concrete masonry, arctic engineering, asbestos and lead based paint surveys and abatement, and soil remediation.
1.7 Upon issuance of a task order, the contractor will diligently complete all work within the time frames specified in the task order. The contractor shall perform all necessary quality control functions to ensure the work is executed in compliance with the terms of the task order and this contract.
1.8 The contractor shall be required to maintain management offices on Eielson AFB and work closely with 354 CES personnel in identifying specific requirements to successfully accomplish each task order.
2. UNIT PRICE BOOK:
2.1 The SABER office will use the most current R.S. Means Facilities Construction Cost
Data as the Unit Price Book for this contract. To ensure effective cost estimations for individual SABER projects, the government and contractor shall use e4Clicks
Professional Project estimator system or equal as described in section 8.3.
2.2 There will be two types of construction projects on Eielson AFB, renovation/remodeling or new construction. In order to make the cost estimating more accurate, the Facilities
Construction Cost Data, Repair and Remodeling Cost Data, or Facilities Maintenance and
Repair Cost Data price books will be allowed to be used for renovation, repair, or remodeling projects. If a project is new construction, individual division books will be used.
2.3 The contractor shall be required to update the database on each computer at the beginning of each calendar year. Updates shall incorporate all of the latest updates from R.S.
MEANS for individual line items, and it shall be localized for the Fairbanks, AK area.
3. TECHNICAL DESIGN SUPPORT CAPABILITIES:
3.1 The contactor must have engineers or master craftsmen available on an “as needed” basis that are capable of design in civil, structural, mechanical, and electrical. They must be experienced with building codes, safety regulations, and environmental protection requirements associated with construction. Also, they must have technical support to handle architectural and drafting services that are familiar with standard drafting conventions. The contractor should expect to produce any supporting technical calculations or any other data required by the contracting officer in order that the government may verify the accuracy and validity of the contractor design. The contractor must submit basic plans/schematic drawings for all mechanical and electrical systems being installed (i.e. fire suppression, HVAC, electrical system panels). The contracting officer’s representative shall be the determining authority as to what data is needed from the contractor on individual task orders. The data required may vary with each task order.
JA-1 Specifications (Statement of Work) Page 5 of 31
3.2 The contractor shall have a dedicated draftsman whose sole responsibilities are preparing design and as-builts. They shall not fulfill project management responsibilities.
3.3 Drafting technicians shall have training in an accredited drafting program and at least of 2 years applied experience in generating and modifying construction drawings using
AutoCAD software.
3.4 Computer Aided Design (CAD) Drawing Formats and Standards
3.4.1 All drawings will A/E/C CADD Standard published by the CADD/GIS Technology
Center for Facilities, Infrastructure and Environment for all computer-aided drafting and design-generated “as-built” drawings. The standard is published at https://cadbim.usace.army.mil.
3.4.2 Drawings shall be in the same format as the Eielson AFB standard which is currently the
AutoCAD 2008 or 2010 Drawing File (.DWG) format.
3.4.3 Drawing sets for individual projects shall include a cover sheet, or sheets, with the following information: 1) Eielson project number and name, and “PACIFIC AIR
FORCES, 354
th
Civil Engineer Squadron, Eielson AFB, Alaska” in large lettering; 2)
Base Map, indicating project location; 3) Project Site Plan; and 4) Drawing Schedule.
3.4.4 A title block on each drawing sheet shall include the following information: 1) Project
Title; 2) Eielson Project Number; 3) Drawing Title; 4) Sheet Reference Number; 5) Sheet
[#] of [total number of sheets in the set]; 6) “354 Civil Engineer Squadron, Eielson AFB, Alaska”; 7) Drawing date; 8) blocks for Designer’s name, Draftsman’s name, Air Force
Project Manager’s name and Eielson’s Chief Engineer’s name; 9) space to list drawing revisions; 10) space for the designer’s professional stamp; and 11) the Design Firm’s name or logo.
3.4.5 No non-standard fonts or shape files shall be used.
3.4.6 The United States National CAD Standard is the format that will be used on formats and standards for features inside buildings, vaults, or other structures. The standard is published at http://www.nationalcadstandard.org.
3.5 Drawing Quality Assurance/Quality Control
3.5.1 The contractor shall insure that any and all products provided to the Government have received careful and complete QA/QC.
3.5.2 The Government will immediately return for remedial action (at the Contractor’s expense) any products that do not meet these specifications.
3.5.3 Before a file is placed on the delivery digital media, the following procedures shall be performed:
https://cadbim.usace.army.mil/ http://www.nationalcadstandard.org/
JA-1 Specifications (Statement of Work) Page 6 of 31
3.5.3.1 Remove all extraneous graphics outside the border area and set the active parameters to a standard setting or those in the Government-furnished seed file.
3.5.3.2 X-refs shall be bound, without device or directory specifications, to the drawings that reference them.
3.5.3.3 All digital files shall be delivered to the Government uncompressed.
3.5.3.4 Include all files, both graphic and nongraphic, required for the project (i.e., color tables, pen tables, font libraries, symbol libraries, user command files, plot configuration files, AML plot routines, etc.). Applicable plotstyle (.ctb) files shall be provided with the drawings.
3.5.3.5 Each finished CADD drawing or map shall have its own separate plot file.
3.5.3.6 Make sure that all support files such as those listed above are in the same directory and that refers to those files do not include device or directory specifications.
3.5.3.7 Include any standard sheets (i.e., abbreviation sheets, standard symbol sheets, etc.)
necessary for a complete project.
3.5.3.8 Document any fonts, tables, symbols, cells/blocks, line styles/types, details, reference drawings, etc., developed by the contractor. The contractor shall obtain Government approval before using anything other than the Government's standards.
3.6 Contractor Guidelines for Formatting GIS Files: If any GIS files are to be created and turned over to the government, the contractor must contact 354 CES/CEPT for additional guidelines that must be followed.
4. OFFERS:
4.1 Each offeror must submit two percentage factors, or coefficients, for each location in order to be considered acceptable. The first coefficient is to be applied to the work anticipated to be accomplished during standard working hours (0730 hrs to 1630 hrs, Monday through Friday, excluding holidays). The second coefficient will be applied to the work anticipated to be accomplished on a nonstandard basis. It is estimated that five
(5) percent of the work required under the contract will be accomplished on a non-standard basis. These coefficients shall be submitted on the Pricing Offer Schedule. All of the work anticipated to be accomplished under the contract will be performed on
Eielson AFB (using the Eielson AFB coefficients) or Clear AFS (using the Clear AFS coefficients).
4.2 The offeror’s coefficient shall be “net” (e.g., 1.00), a percentage “decrease from” (e.g., 0.95), or a percentage “increase to” (e.g., 1.20) the unit prices listed in the Unit Price
JA-1 Specifications (Statement of Work) Page 7 of 31
Book. Offerors who submit separate coefficients for the individual tasks will be considered nonresponsive and the offer will be rejected.
4.3 The offeror’s price coefficient must contain all the offeror’s contract costs including, but not limited to, mobilization, demobilization, overhead, profit, bond premiums, insurance, project drawings, materials testing, and all contingencies in connection therewith.
Offeror must provide a breakdown of the components that make up their coefficient to include items mentioned earlier in this paragraph and any mark ups on direct labor. No allowance shall be made later for any other costs incurred.
4.4 Any change in the applicable minimum hourly rates of wages during the contract period shall not affect the unit price to be paid by the government for work performed under the contract.
5. STANDARD VS NONSTANDARD WORK HOURS:
5.1 Standard Working Hours: The contractor shall be prepared to pursue the contracted tasks during the standard working period of 0730 hrs to 1630 hrs, Monday through Friday, excluding federal holidays. The contractor may elect to work hours other than normal duty hours provided that:
5.1.1 The requirement is submitted in writing at least three workdays in advance.
5.1.2 The contracting officer approves the request.
5.1.3 Work on weekends or federal holidays that the contractor chooses to do will be considered standard hours
5.2 Non Standard Working Hours: Work required by the government at other than standard duty hours will be considered nonstandard working hours. Other than standard working hours shall be calculated by the unit price sum specified in the RS Means Facilities
Construction Cost Data multiplied by the coefficient for non-standard hours.
6. ECONOMIC PRICE ADJUSTMENTS:
6.1 Previous SABER contracts utilized a Unit Price Book (UPB) in which all line item costs remained the same throughout the life of the contract. This required an economic price adjustment to the contractor’s coefficient for each option year. Because this contract will utilize a MEANS database that is updated each succeeding option period to reflect economic adjustments, the contractor’s coefficient shall remain constant throughout the life of this contract, including all exercised option periods.
7. CONTRACT START-UP PERIOD:
JA-1 Specifications (Statement of Work) Page 8 of 31
The first 30 calendar days following contract award will be designated a start-up period, after which the contractor shall have all equipment and personnel in place to fully execute the requirements of this contract. The contractor will be allowed the first 30 calendar days of the start-up period to mobilize without being notified by contracting of a performance requirement.
8. CONTRACTOR PROVIDED MATERIALS:
8.1 All contractor provided materials shall become the sole property of the Government.
8.2 Technical Library: The contractor shall, within 30 calendar days following contract award, provide two copies of the following publications to 354 CES/CEPM and one copy to 354 CONS/LGCA (unless noted otherwise), and shall provide updates as published at no additional cost to the government.
8.2.1 R. S. Means Pricing Guides:
8.2.1.1 Assemblies Cost Data
8.2.1.2 Building Construction Cost Data
8.2.1.3 Electrical Cost Data. Not required for 354 CONS.
8.2.1.4 Facilities Construction Cost Data
8.2.1.5 Mechanical Cost Data. Not required for 354 CONS.
8.2.1.6 Plumbing Cost Data. Not required for 354 CONS.
8.2.1.7 Square Foot Costs
8.2.2 R. S. Means Estimating Handbook. Not required for 354 CONS.
8.2.3 R. S. Means Illustrated Construction Dictionary. Not required for 354 CONS.
8.3 Software Programs, Licenses, and Upgrades: The contractor shall, within 30 calendar days following contract award, provide 10 licenses, install and troubleshoot the most current version of the following software to 354 CES and shall provide upgrades, as published, at no additional cost to the government. The software shall be licensed for both network common use and stand alone personal computer. Receipt of updated software and/or RS MEANS information each year does no obligate the government to exercise any contract option years.
8.3.1 Project Estimating and Manager Software by 4Clicks Solutions, LLC, or equal to include:
8.3.1.1 e4Clicks Professional Project Estimator or equal.
JA-1 Specifications (Statement of Work) Page 9 of 31
8.3.1.2 R. S. Means Facility Construction Cost Data/e4Clicks Database or equal.
8.3.2 The contractor shall be required to update the database on each computer at the beginning of each calendar year. Updates shall incorporate all of the latest updates from R.S.
MEANS for individual line items and it shall be localized for the Fairbanks, AK area.
8.4 Contractor Provided Services: The contractor shall provide a 2-day initial training course to government personnel not to exceed 15 persons per class for software identified in 8.3, at no additional cost to the government. Additionally, refresher training will take place once per year for government personnel, not to exceed 10 per class, at no additional cost to the government. The training will be conducted by a trainer that is approved by the estimating software company.
9. TASK ORDER PROCEDURES:
9.1 As the need exists for performance under the terms of this contract, the contracting officer or his authorized representative will notify the contractor of a performance requirement or Statement of Objectives (SOO), to include any lead base paint or asbestos survey for the project area.
9.2 The contractor shall have permanent, full time representation at Eielson AFB to receive such notification for work.
9.3 The SABER project manager will submit a Statement of Work in the Statement of
Objectives to the contracting officer who will then forward the SABER contractor the request for proposal. Upon receipt of this notification, the contractor shall respond to the needs of the government by scheduling a site visit within three workdays. The site visit will be conducted in the company of the contractor, contracting personnel, the end user or facility manager, and the SABER project manager at the proposed work site. If the project is complex and the specific disciplines are needed at the meeting, other base agencies (fire department, safety, communications, etc.) may also be invited to attend.
9.4 Once the site visit is complete, the contractor shall accomplish their proposal and return it to the contracting officer by the suspense date reflected on the request. The suspense date will be based on Magnitude, Complexity, and Urgency of the project. Contracting
Officer’s representative will determine a suspense date of three, five, or ten workdays, taking these factors into consideration. The contractor shall have enough staff to ensure proposals are completed within the established suspense dates.
9.5 The contractor shall identify the pre-priced line items that address the requirement and quantities thereof. The appropriate database listed in section 8 shall serve as the basis for establishing the value of work to be performed on a unit price basis. The contractor shall then submit a proposal for accomplishment of the task, which shall include a print out from the cost estimating software stating specific quantities. If the line item varies
JA-1 Specifications (Statement of Work) Page 10 of 31 slightly from the description described in the Means, notes shall be added in the notes section of the printout to clarify the use of line items.
9.6 The contractor shall submit three independent quotes for non-prepriced items deemed necessary for the completion of work under a task order. The estimate is then compared to an independent government estimate provided by SABER personnel. Non-prepriced items of work to be included in an individual requirement must be presented by the contractor in a proposal format comparable to those of pre-priced items. These non-prepriced items shall not be multiplied by the coefficient for a total unit price; they shall be negotiated at full cost prices. If the non-prepriced item is to be added to the Unit Price
Book, the price shall be divided by the coefficient and added to the contract for future use as a supplement to the RS Means guide.
9.7 The contractor’s proposal must be supported by adequate documentation to demonstrate that thorough engineering and planning necessary to complete the task order have been accomplished. Examples of minimal documentation expected in the proposal include:
surveying, AutoCAD drawings, calculations, catalog cuts, specifications, architectural renderings, etc. The contractor’s proposal must not contain additional overhead, profit, bond premiums, insurance, and all other costs including, but not limited to, compliance with environmental laws, tax laws, protection or moving of government property and engineering services, as these allowances are included in the established coefficients.
The contractor will give the completed proposal to contracting who will then forward the proposal to the SABER project manager. Upon receipt of the contractor’s proposal, the government will accomplish a technical evaluation of the proposal. If the SABER project manager has questions about the contractor’s proposal, the contract administrator may call a fact-finding meeting in order to clarify government questions and misunderstandings in the pre-priced line items.
9.8 A negotiation meeting will be scheduled by contracting to discuss and negotiate all variances in quantities, line items, non-prepriced items, start date, and performance times.
Contracting, the contractor, and a SABER project manager will be present.
9.9 After negotiations have been completed and if funding is available, a contracting officer will then issue a task order using DD Form 1155. The notice to proceed date will be based on the contractor’s construction schedule in coordination with the end users. If full funding is not available, the contractor will be paid according to negotiated amounts for the level of magnitude and complexity of the proposal.
9.10 The negotiated price for the project will be good for 90 calendar days, unless otherwise negotiated with the Contracting Officer.
9.11 Actual construction on the site will not occur until an AF Form 103 (Base Civil
Engineering Work Clearance Request) has been completed and the government has received the construction start request letter and approved the start date.
JA-1 Specifications (Statement of Work) Page 11 of 31
9.12 The contractor, subcontractors, contracting, SABER project manager, building manager, and other pertinent base officials (i.e. Safety, Security Forces, Communications) will have a pre-construction meeting to discuss specific issues for the task order.
9.13 The contractor shall not begin actual construction until the Construction Start Letter is received and approved. This letter is written by the contractor and coordinated through contracting and SABER personnel. It shall coincide with the negotiated start date. The requested start date will be approved once all necessary paperwork is received and notifications have been made.
9.14 When the work is complete, the contractor will request a final inspection from the contracting officer and a date will be scheduled with the facility manager/user, a SABER project manager, the contractor, and contract administrator within 7 working days. More information regarding final inspections is included in sections 10 and 11.
9.15 Proposal Task Order Procedures
9.15.1 The following procedures allow the Government to issue a task order for proposal preparation without obligating the Government to issue an order to construct the work described in the resulting negotiated proposal. One contract line item will be used (per option year) for task orders issued for proposal preparation. Following are the steps involved in a Proposal Task Order:
1. SABER submits request for proposal (RFP) to Contracting. Include:
Magnitude/Complexity determination for pricing purposes and recommended number of days for proposal return.
2. Contracting Officer (CO) submits abbreviated RFP to Contractor for
Magnitude/Complexity determination review. (Site Visits can be arranged at this time at the Contractor’s request.)
3. Contractor submits response (agreement or disagreement) to Magnitude/Complexity determination/proposal return days.
4. A task order will then be issued (upon agreement by both parties on the Magnitude, Complexity, and Proposal Return Time) using scale (see schedule B) for pricing against the appropriate CLIN on the Basic Contract:
5. Contractor prepares and submits the proposal in the agreed upon time frame.
6. Government reviews proposal and schedules negotiation (as required).
7. Government and Contractor negotiation (as required).
8. Government approves final negotiated proposal.
9. Contractor invoices and Government pays for Proposal Task Order.
9.15.2 Supplemental Information
9.15.2.1 Upon completion of the steps listed above, the project is considered “on the shelf” and awaiting funds.
9.15.2.2 The negotiated/accepted cost resulting from the task order shall remain valid for a period of 90 calendar days unless otherwise negotiated by the Contracting Officer.
JA-1 Specifications (Statement of Work) Page 12 of 31
9.15.3 Prior to invoicing, the contractor shall submit a Progress Report (AF Form 3065) indicating 100% progress to meet receiving report requirements. (No AF Form 3064 will be required).
9.15.4 If funding to build the project becomes available at any time during the proposal process, the Proposal Task Order may be converted to a normal Build Task Order.
9.15.5 Issuance of Build Task Orders from Proposal Task Orders(PTO):
If within 90 days of a negotiated PTO, upon receipt of funding, a new task order will be issued to build the project. The previously paid proposal fees will be deducted from the overall price of the new task order
10. PERFORMANCE OF WORK BY THE CONTRACTOR:
10.1 The Contractor shall perform on the site, and with its own craftsman, work equivalent to at least 15 percent of the total amount of work to be performed on each task order under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the
Contracting Officer determines that the reduction would be to the advantage of the
Government.
10.2 Contractor shall maintain a professional work area to include the entire job site. Smoking shall not be allowed except in designated areas. No noxious or harmful fumes shall be allowed to infiltrate occupied facilities or work areas.
10.3 SABER Project Review Meetings: Contractor shall host project review meetings at the request of the government with applicable 354 CONS and 354 CES personnel.
10.3.1 Contractor shall coordinate the meeting date and time with the Contracting Officer (CO) and 354 CES personnel.
10.3.2 CO shall chair the meeting.
10.3.3 Contractor shall provide a list of all projects to include (but not limited to)
10.3.3.1 Contract Number
10.3.3.2 TO Number and Cost
10.3.3.3 Project Number
10.3.3.4 Work Order Number(s)
10.3.3.5 Award Cost
JA-1 Specifications (Statement of Work) Page 13 of 31
10.3.3.6 Modification Number with cost and purpose (as applicable)
10.3.3.7 Scheduled and Actual Start and Completion Dates
10.3.3.8 Required Utility Outages, Road Closures, and remarks to include, but not limited to, a
BRIEF statement of significant issues, work performed, ongoing work, and scheduled work for future weeks
10.3.4 The contractor shall also maintain a submittal and request for information (RFI) log.
10.3.5 For project review meetings, the contractor may use government conference rooms with the coordination of 354 CONS.
10.4 Worksite
10.4.1 Equipment/Material Storage
11. FINAL INSPECTIONS AND ACCEPTANCE:
11.1 The contractor shall request a final inspection in writing at least 7 working days prior to proposed inspection date. The contractor shall have a quality control manager inspect the project and ensure all work is complete and meets the terms of the contract prior to the final.
11.2 Any punch list items noted during the final inspection shall be recorded by a government representative and a copy given to the contractor within 24 hours. The contractor must provide a written schedule showing completion dates for the punch list items.
11.3 After all discrepancies have been corrected, the contractor shall notify contracting and request another inspection. Once work has met acceptable standards, as determined by
SABER and contracting personnel, the work shall be accepted and final payment will be authorized. Final payment of 10 percent of the task order amount will only be authorized after acceptance and approval of as-built drawings for the individual task order.
12. GOVERNMENT-FURNISHED EQUIPMENT/MATERIALS (GFE/GFM):
12.1 The contractor, with his own forces, shall load and transport all government-furnished equipment/materials, if any, described on the task order. The equipment/materials shall be transported from the government storage area to the work site indicated on the task order. As unit prices include materials/equipment, work using GFE/GFM shall be accomplished by use of the non-prepriced items clause or the labor portion of a RS
Means line item for a similar installation that is agreed upon by the contractor and the government.
JA-1 Specifications (Statement of Work) Page 14 of 31
12.2 The contractor shall follow the instructions of the contracting officer’s representative regarding the disposition of all Government-furnished property not consumed in performance of a task order.
13. SECURITY REQUIREMENTS:
13.1 The contractor shall comply with security regulations imposed by the Installation
Commander and the agency occupying the space where work is to be performed, including any necessary security clearances. Prior to mobilization the contractor shall provide the contracting officer or authorized representative a list of personnel requiring authority to work on Eielson AFB and Clear AFS. The list shall be kept current and the
Contracting Office or authorized representative must be notified as to any changes in the list. The contractor’s employees will be required to obtain and display employee identification as prescribed by Air Force directives. The contracting officer shall provide these requirements upon request.
13.2 Whenever facility security is breached to perform work required under this contract, the contractor will be responsible for providing temporary measures in order to assure security is maintained at the level existing prior to construction. This may include such security items as fencing around a facility or closing all openings in a structure during non-work hours.
14. GENERAL INFORMATION:
14.1 The contract is divided into 3 sections to be used in the execution of work.
14.1.1 Volume I: General Specifications. Volume I shall consist of Solicitation.
14.1.2 Volume II: Statement of Work and Technical Specifications.
14.1.2.1 The Construction Specification Institute’s (CSI’s) Master Specifications shall be used for this contract. All specifications are filed in Divisions 1 through 46 per CSI guidelines.
14.1.2.2 The contents of this contract shall make up the technical provisions section of the specifications.
14.1.2.3 The intent of these specifications is to furnish concise industrial and commercial standards for maintenance, repair, and minor construction of Government facilities.
Any work not addressed in the master specifications shall require submittal of applicable specifications as part of the task order.
14.1.3 Volume III: Unit Price Book (UPB). The UPB shall consist of the approved RS Means based software package and items listed in Section 8.
JA-1 Specifications (Statement of Work) Page 15 of 31
15. WORK BY THE GOVERNMENT:
15.1 The government reserves the right to undertake performance, by whatever means available or necessary, of the same type or similar work as contracted for herein. To do so will not breach or otherwise violate this contract.
16. SCHEDULING WORK:
16.1 Before any work is initiated under an individual task order, the Contractor and
Contracting with the coordination of the CE representative shall agree on a sequence of procedures. Items discussed shall be: means of access to premises and facilities, space for storage of materials and equipment, delivery of materials and use of approaches, use of corridors, stairways, elevators, spaces, and restrooms for the contractor’s employees.
16.2 The contractor must submit a schedule of work with the proposal for approval not later than 10 calendar days after the notice to proceed as described in paragraph 1.5 of this statement of work.
16.3 Prior to any work being initiated on each task order, the contractor shall complete and coordinate a, AF Form 103, in its entirety. The contractor shall not, under any circumstances, enter an “N/A” into any blocks on the form. The contractor shall not begin the project without a signed, approved AF Form 103. Copies of the approved form shall be submitted to the contracting officer and the SABER project manager prior to work beginning.
16.4 Delivery of materials and equipment shall be made with minimum interference to
Government operations and personnel.
16.5 The work shall, so far as practicable, be done in definite sections or divisions and confined to limited areas which shall be completed before work in other sections or divisions is begun.
16.6 The contractor shall obtain a permit from the Base Fire Chief for all hot work (use of oxyacetylene gas or welding machine.
16.7 The contractor shall store all supplies, materials, and equipment in an area approved by the government. The contractor must propose a staging area for each task order if one is needed. The contractor shall be responsible for securing materials and equipment to preclude theft or damage. The site shall be maintained in a neat and orderly manner.
17. UTILITIES, WORK RELATED:
17.1 Available water, electrical and local telephone services at the job site may be used in the performance of work under this contract at no cost to the contractor. The government shall not be held liable for interruptions of utilities. Electricity will not be used for
JA-1 Specifications (Statement of Work) Page 16 of 31 heating purposes. The contractor shall make arrangements for such services with the contracting officer or his designated representative.
17.2 The Base Civil Engineer shall approve all temporary outages of any utility services required for the performance of work under this contract at least 10 working days prior to the requested outage. No outage will be performed without prior written approval from the 354 CES.
17.3 Steam used for heating will not be turned off until after May 15 th of each year. Projects that require removing heat from a facility will be phased if possible to avoid interrupting heat before this date.
18. AS-BUILT DRAWINGS AND REAL PROPERTY UPDATES:
18.1 During the progress of work, the contractor shall keep a careful record at the job site of all changes and corrections from the layouts shown on the drawings, if applicable. The contractor shall enter such changes and corrections on contract or record drawings promptly and submit drawings to the SABER project manager in accordance with the schedule provided in the task order.
18.2 The as-built drawings shall indicate, in addition to all changes and corrections, the actual location of all subsurface utility lines to include the exact coordinates.
18.2.1 In order that the location of these lines and appurtenances may be determined in the event the surface openings or indicators become covered over or obscured, the as-built drawings shall show, by offset dimensions to two permanently fixed surface features, the end of each run including each change in direction.
18.2.2 Valves, splice boxes, and similar appurtenances shall be located by dimensioning along the utility run from a reference point.
18.2.3 The depth below the surface of each run shall also be recorded.
18.3 The as-built drawings showing for each task order shall be submitted no later than 10 working days following task order completion.
18.3.1 These drawings shall include, at a minimum, one hard copy, two labeled compact disks
(CD) each containing the drawings in both the digital format utilizing the same software release as that of 354 CES drafting personnel (which is currently AutoCad 2010) and saved as a read-only Adobe Acrobat Reader (.pdf file) format.
18.3.2 The hard copies will be 11”x17” as a minimum; however, they will be produced at the most appropriate size to ensure the drawings can be clearly read when plotted exactly at the planned scale.
18.3.3 The drawings must meet the format outlined in the National CAD Standards.
JA-1 Specifications (Statement of Work) Page 17 of 31
18.4 If the contractor fails to maintain the record drawings as required herein, the contracting officer may consider that satisfactory progress has not been achieved for the period in question, thereby requiring the retention of 10 percent of the task order total amount until such drawings are made current and approved.
18.5 A DD Form 1354, Transfer and Acceptance of Military Real Property must be accomplished by the contractor after a task order is completed. The form will indicate the quantity and category of Real Property being installed during the execution of the task order. The contractor will be responsible for verifying the accuracy of the data before submitting to the contracting office.
18.6 An Eielson AFB Building Checklist will be completed by the contractor with the DD
Form 1354. The government shall provide an example and instructions upon request.
19. GOVERNMENT-PROVIDED AS-BUILTS:
19.1 The government does not guarantee the accuracy or adequacy of existing as-built drawings that may be made available to the contractor. It is the contractor’s responsibility to field verify all existing conditions prior to submitting proposals for work under any task order. The contractor can request as-builts from SABER as applicable.
After award of the task order, increases in award price shall not be granted based on site conditions that the government determines could have been verified prior to task order issuance.
20. ENVIRONMENTAL PROTECTION:
20.1 Solid, Liquid, and Gaseous Contaminants. The contractor shall be responsible for the proper disposal of all solid, liquid, and gaseous contaminants, including asbestos and lead-based paints, in accordance with all applicable Federal, State, and local codes and regulations.
20.2 Disposal of Refuse. The contractor shall be required to remove all refuse from Eielson
AFB and Clear AFS for negotiated task orders. Separate asbestos disposal sites will be provided in accordance with Volume II, Technical Specifications, Section 02080 for task orders requiring asbestos removal. See also, Waste Disposal/Base Borrow Pit
Requirements, attached as attachment A of the specifications.
20.3 Covered Chutes. All chutes for refuse or other materials disposed of during execution of a task order shall be covered or of such design as to fully confine the material to prevent dissemination of dust.
20.4 Contractor shall not incorporate any asbestos containing material in any work.
20.5 The applicable items from the list below will be included in the contractor’s proposed schedule and will be submitted by the contractor once the task order has been awarded:
JA-1 Specifications (Statement of Work) Page 18 of 31
20.5.1 Request for use of Ionizing Radiation (if required)
20.5.2 Request for use of Lasers (if required)
20.5.3 Request for use of Radioactive Materials (if required)
20.5.4 Request for use of Radio Frequency radiation (if required)
20.5.5 Request for use of Ultraviolet Radiation (if required)
20.5.6 Environmental Protection Plan (if required)
20.5.7 Contaminated Soil Sampling and Analysis Plan (if required)
20.5.8 ADEC Approval to Transport Contaminated Soil (if applicable)
20.5.9 Storm Water Pollution Prevention Plan (if required)
20.5.10 Copy of NPDES NOI and EPA approval (if required)
20.5.11 Evidence of delivery of SWPPP to ADEC (if required)
20.5.12 Wetlands Permit (if Contractor obtained)
20.5.13 Dewatering Permit (if required)
20.5.14 Phase I Environmental Assessment Certificate for Imported Borrow Materials (if required)
20.5.15 ADEC Permit to Construct (if required for project)
20.5.16 Any other Environmental Plans or Permits the Contractor is required to obtain in order to legally perform the work of the Task Order.
20.6 Submit the initial asbestos and lead base paint abatement plans as part of the design submittals. Abatement plans shall conform to the requirements described in Appendix 16 of these specifications.
21. CONSTRUCTION SITE MAINTENANCE:
21.1 Storage Trainers and Boxes. All trailer and boxes shall:
21.1.1 Be free from damage to an acceptable condition
21.1.2 Ensure proper storage of project materials/equipment
JA-1 Specifications (Statement of Work) Page 19 of 31
21.1.3 Be free from graffiti
21.1.4 When utilized as permanent storage at the contractor’s office location, be neat and clean in appearance
21.1.5 All sides of storage trailers/boxes shall have professionally manufactured applicable warning placards mounted for each HAZMAT stored
21.1.6 All storage trailer/box shall have a 5” x 7” Contractor Identification Placard in a weatherproof holder affixed to the right entrance door indicating:
21.1.6.1 SABER Contrator’s Name
21.1.6.2 TO Number
21.1.6.3 Project Number and Title
21.1.6.4 Contractor’s Point of Contact with Contact Number.
21.1.7 Storage of materials and debris under trailers is prohibited.
21.1.8 All storage trailers/boxes shall be removed from the worksite prior to the final inspection date.
21.2 Laydown/Bulk/Stockpile Storage
21.2.1 All equipment materials shall be stored on pallets, dunnage and racks as appropriate, and shall not be stored directly on the ground at any time.
21.2.2 All materials sensitive to sunlight shall be covered at all times.
21.2.3 All loose or stockpile material, to include excavated earthworks staged for screening and re-utilization shall be fully covered by tarpaulins and properly staked against winds.
21.2.4 Contractor shall enclose the lay down area with fencing appropriate for the particular TO.
Contractor’s lay-down area shall also be screened from view.
21.3 Refuse
21.3.1 Solid Waste Disposal
21.3.1.1 All solid waste materials generated by any work under this contract performed on a Government installation shall be handled, transported, stored, and disposed of by the Contractor and by his/her subcontractors at any time in accordance with these specifications, all applicable
Federal, state, or local laws, applicable AFI’s and UFC’s, ordinances, regulations, court orders, or other types of rules or rulings having the same effect of law.
21.3.1.2 Contractor shall remove and dispose of off-base, in compliance with all federal, state, local, and
Eielson AFB ordinances, all trash, debris, refuse, and etc., as stated above.
JA-1 Specifications (Statement of Work) Page 20 of 31
21.3.1.3 Contractor shall not use installation dumpsters or recycle containers for construction debris or waste.
21.3.1.4 Contractor shall either include dumpsters as a line item in each TO proposal or, for projects generating small quantities of debris, remove the debris from the job site and dispose of off-base. For Contractor-supplied dumpsters, the Contractor shall post signs on each dumpster stating "SABER CONTRACTOR DUMPSTER" and "NOT FOR PUBLIC USE."
21.3.1.5 Contractor shall immediately clean up any and all spillage from equipment, material, supply, vehicle, container, and/or dumpster removals and/or deliveries, including mud on tires.
21.3.1.6 Contractor shall ensure any substance that can fall off delivery/pick-up vehicles is securely covered to prevent spillage.
21.3.2 Daily Cleanup
21.3.2.1 Contractor shall maintain a worksite free from accumulation of debris.
21.3.2.2 Contractor shall empty trash receptacles on a regular basis throughout the day’s activity to avoid overflow or spillage.
21.3.2.3 Contractor shall perform daily general sweeping/pick-up of debris prior to close of a day’s worksite activity; empty all trash receptacles into worksite refuse containers; and shall comply with protection of existing Government property.
21.3.3 Salvageable Materials
21.3.3.1 All salvageable material to be reused in the construction work shall be stored for reuse in a suitable location within the work area.
21.3.3.2 All such items shall be marked so as to be reinstalled in their proper locations.
21.3.3.3 All salvageable material, not to be used in the construction, shall be reviewed by 354 CES to determine if the material is to be retained by the Government. Materials not retained by 354
CES shall be disposed of by the Contractor.
21.3.4 Unsalvageable Material
21.3.4.1 All unsalvageable material shall become the sole property of the Contractor, unless designated otherwise by the Contracting Officer.
21.3.4.2 Unsalvageable material shall be promptly removed from the site and disposed of.
21.3.5 Trash Receptacles
21.3.5.1 Worksite barrels/carts used for general daily debris accumulation.
JA-1 Specifications (Statement of Work) Page 21 of 31
21.3.5.2 Trash receptacles shall be free from graffiti, and shall have “TRASH” stenciled on opposite sides of the receptacle.
21.3.5.3 Contractor shall provide a minimum of one trash container for each 10,000 square feet of worksite area.
21.3.6 Demolition/Bulk Debris
21.3.6.1 When required, the Contractor shall provide refuse containers for the large accumulation of demolition waste and other debris.
21.3.6.2 Hauling of demolition/bulk debris to refuse containers shall comply with protection of existing
Government property.
21.3.6.3 Trucks may be utilized for removal of demolition/bulk debris, but shall not be utilized for demolition/bulk debris accumulation.
21.3.6.4 Contractor shall empty refuse containers and trucks on a regular basis to avoid overflow, spillage, and remain below tonnage allowances for travel on municipal and base roadways IAW current local, state, and federal regulations.
21.3.7 Refuse Containers
21.3.7.1 All refuse containers shall be free from graffiti, and be equipped with a securable tarpaulin or cover (NOTE: The cover shall be in place at all TIMES, except when waste is being deposited or removed).
21.3.8 Trucking
21.3.8.1 Contractor shall remove all loose debris on truck sidewalls prior to leaving the worksite.
21.3.8.2 Shall be loaded in a manner that shall prevent dropping of materials on roadways per IAW current local, state and federal ordinances and regulations.
21.3.8.3 Contractor shall provide suitable covers/tarpaulins over loads prior to leaving the worksite.
21.3.8.4 Contractor shall be responsible for any clean up, and liable for any resulting damage from any debris that may fall from trucks/refuse containers.
21.4 Sanitation Facilities
21.4.1 Contractor shall provide self-contained portable/chemical toilet sanitation facilities, with hand cleansing capabilities and self-closing securable doors, for worksites without restroom facilities available unless otherwise specified by the CO.
21.4.2 Sanitation facilities shall be located in an out-of-view location if practical as approved by the government representative.
JA-1 Specifications (Statement of Work) Page 22 of 31
21.4.3 When specified, Contractor personnel may be permitted use of existing Government restroom facilities.
21.4.4 If the restrooms at worksites are under contractors’ full jurisdictions, then such facilities shall be kept neat and clean.
21.4.5 The Contractor shall not use sanitary facilities for cleaning of work tools or equipment.
22. GROUNDS MAINTENANCE:
22.1 Grass
22.1.1 Contractor shall maintain all grass that is sectioned off within a work site and is not accessible by ground maintenance
22.1.2 Maintain all work sites in a presentable manner that is not accessible by grounds maintenance.
22.1.3 Contractor employees, to include subcontractor employees and deliveries, shall not park any vehicle or equipment on grassed areas, unless otherwise authorized by the 354 CES project manager. When authorized, parking on grassed areas shall only be for short-term delivery purposes (to include heavy tools, equipment, construction materials etc.), vehicles shall then be promptly removed.
22.1.4 Tire/ track impressions (ruts) created on wet or soft soils by vehicles and/or equipment operated by the Contractor shall be restored to original state by the end of the project, or as otherwise directed by the CO.
22.2 Trees/Shrubs/Bushes
22.2.1 All trees/shrubs/bushes within a worksite that is not accessible by grounds maintenance shall be maintained during growing seasons, and pruned as directed by the CO.
22.3 Vegetation
22.3.1 All trees, shrubs, bushes, vegetation beds and grass shall be protected from damage at all times.
22.3.2 During painting and stucco operations, or as otherwise directed, all trees, shrubs and bushes shall be tied and/or bundled, and vegetation beds and grass covered to protect from splatter and or damage
22.4 Damaged Curbs, Pedestrian ways and Roadways: Contractor shall repair/replace all damaged locations resulting from Contractor operations/negligence, to include sub-Contractors and deliveries at no additional cost to the Government.
23. CONSTRUCTION SIGNS:
23.1 All construction sites shall have signs posted that say, “Construction Area—Authorized
Personnel Only”, “Hard-Hat Area—Construction in Progress”, and…