Questions and Responses 005.doc

DOC document 33 KB Posted

Attached to
RECOVERY--Z--COAL CRUSHER REPLACEMENT AT CLEAR AIR STATION, ALASKA
Solicitation number
FA5004-09-R-C009
Issued by

View the file

Other files

File Type Posted
Questions and Responses 009.doc DOC document
Attachment JA-1 Specifications —
JA-2 Wage Determination 5 June 2009.pdf PDF
P0005 Amendment 5.pdf PDF
Questions and Responses 008.doc DOC document
Questions and Responses 006.doc DOC document
Combined Specifications —
0004.pdf PDF
Questions and Responses 004.doc DOC document
Attachment JA-1 Specifications —
JA-2 Wage Determination 29 April 09.doc DOC document
Questions and Responses 003.doc DOC document
Amendment 2.pdf PDF
JA-8.6.pdf PDF
JA-8.5.pdf PDF
JA-8.2.pdf PDF
JA-8.1.pdf PDF
JA-8.8.pdf PDF
JA-8.3.pdf PDF
JA-8.7.pdf PDF
JA-8.4.pdf PDF
JA-8.9.pdf PDF
Site Visit Attendance Sheet —
Amendment 1.pdf PDF
Attachment JA-7 Drawings.pdf PDF
Notice of Question Submittal Due Date.pdf PDF
Attachment JA-2 Schedule of Wage Rates.pdf PDF
Attachment JA-1 Specifications.pdf PDF
Solicitation.pdf PDF
Attachment JA-3 Past Performance Questionaire.pdf PDF
Attachment JA-4 Financial Institution Reference Sheet.pdf PDF
Attachment JA-5 Haz Mat Sheet.pdf PDF
Attachment JA-6 AF Form 66.pdf PDF
Show all 33

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS AND RESPONSES

FOR

COAL CRUSHER REPLACEMENT

AT

CLEAR AIR STATION, ALASKA

SOLICITATION NO. FA5004-09-R-C009

It shall be noted to all interested parties that the following questions have been received in writing regarding the subject acquisition. Additionally, responses have been provided to the below listed questions.

As a reminder, it is the responsibility of all Interested Parties to review this website (http://www.fedbizopps.gov) frequently for any updates and/or amendments to any and all subject documents.

Question 1:

When referring to Specification Section 01005, 1.5 (B)

B. Schedule work so that one crusher, existing or new, is fully operational at all time.

As a contractor, will we be required to install or connect a by-pass system to maintain the fully operational coal feed system to this crusher? If so, please indicate the non operational time of the system in hours, days, etc. so that such by-pass system could be erected. If (B) of the above listed section should be revised please list the details of all allowable non operational periods for the crushers if no by-pass system will apply. Although the crusher itself could be fully operational, if no coal supply is feed to the crusher, the complete system fails to be fully operational. If a by-pass plan has been specified please list any and all details.

Answer 1:

Ref. section 01005, 1.5 - The replacement of the crushers should be fairly straight forward as one crusher can isolated from the other.

Ideally, the Government would prefer to run coal once a day, after the contractor's normal duty shift. If required, the system can be kept down for up to 24 hours while a given section of chute is replaced. With prior request by the contractor, and approval by the Government, this period can be extended to 48 hours. All 24 and 48 hour outages need to be closely coordinated and scheduled with the Government. The Government will schedule coal runs before or after the contractor's normal work shift so that personnel do not have to contend with the noise and rotating equipment. We do not see the need for a bypass.

Question 2:

Section 01005, 1.5 (C)

When notified for emergency reconstruction, how long will the system be in operation following the 48 hour notification (operational time of the system in hours, days, etc.) and how often will the contractor experience a loss of production periods (stand-by time). Is the contractor or owner responsible for this stand-by-time and other expenses during this operational period?

Will all operational periods which cause delays extend the original days allowed for contract completion?

Answer 2:

Ref. section 01005, 1.5, C, - We do not anticipate any standby time for the contractor and believe the probability of an emergency recall of the system, as described in this paragraph, to be remote. Should such an emergency occur, the bunkers could be filled in six hours or less at which time the system would be returned to the contractor. In the rare event of a national defense emergency, all work will be called to a halt, after restoration of an operational system. The contractor would be advised to contact the Contracting Officer for recourse on any such extended delays.

Questions and Responses 003 Solicitation No. FA5004-09-R-C009