Attachment 1 - Statement of Work (Amended).pdf

PDF 172 KB Posted

Attached to
AMENDED_Install Electrical Service for B10571 Federal contract opportunity
Solicitation number
FA500023R0028
Issued by
Department of the Air Force Pacific Air Forces

About this file

This statement of work outlines the requirements for a federal contract to install electrical service for Building 10571 at Joint Base Elmendorf-Richardson in Alaska. The scope of work includes providing primary electrical service, a pad-mounted transformer, power station, secondary electric service, feeder conductors, and installation of a pedestrian gate and fence repairs. The contractor must follow all applicable engineering and construction standards, conduct required testing, and coordinate work with the base. Radiation safety procedures and COVID-19 protocols must also be followed. The solicitation number for this opportunity is FA500023R0028 and it is being issued by the Department of the Air Force Pacific Air Forces.

View the file

Other files for this federal contract opportunity

Other files attached to AMENDED_Install Electrical Service for B10571, newest first.
File Type Posted
Solicitation Amendment FA500023R00280001 SF 30.pdf PDF
Attachment 7 - Question and Answers.pdf PDF
Solicitation - FA500023R0028.pdf PDF
Attachment 1 - Statement of Work.pdf PDF
Attachment 2 - Drawings.pdf PDF
Attachment 5 - LIQDG.pdf PDF
Attachment 6 - DBA Wage Determination.pdf PDF
Attachment 3 - Specifications.pdf PDF
Attachment 4 - AF 66.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section 01020 Scope of Work

01020-1

FXSB 23-1031

Install Electrical Service B10571

01020

SCOPE OF WORK

1. Project Description

1.1. This project will provide power service to the temporary shelters located just north of B10571 as shown in the drawings. Work consists of providing primary electrical service, pad-mounted transformer, power station, secondary electric service, and feeder conductors to the generator shelter. Project will also install pedestrian gate (with 5-key mechanical cypher lock) on existing airfield fence and repair damaged or removed fencing due to electrical service installation. This project is located inside the airfield perimeter fence. This project only requires One Person required personnel for the Superintendent/QC/SSHO.

2. Electrical Work

2.1. See Electrical drawings for electrical requirements.

3. Demolition/Civil Work

3.1. Saw-cut all asphalt prior to demolishing asphalt material. Demolished asphalt shall be disposed of in the asphalt landfill site on base as shown in the plans.

3.2. Asphalt patch at top of trench shall be minimum 2’ wide.

3.3. Contractor shall replace any damaged asphalt that is damaged during construction. For construction within the roadway/airfield, the typical asphalt structural section to be used is:

• 3” HMA, Type II, Class A (PG 58-34)

• Remainder of trench: excavated material 1-1/4” minus, commonly known “reject material”, may not be used as backfill under roadway or airfield areas.

3.4. Site is located within a possible contaminated plume. Any excavated soil must be returned to the excavation and no soil may be transported or disposed of off-site.

3.5. Contractor shall install new 5-key mechanical cypher lock at the new pedestrian gate location.

Location of pedestrian gate and lock shall be determined by Project Manager. Cypher Lock will be programmed by end user.

4. Unique Requirements

4.1. Underground Communications System Locate: Contractor shall be responsible for escorting

AT&T personnel to locate underground communications system. See MACC SOW for airfield driving permit requirements.

4.2. Building 10571 is a controlled facility. Individuals working on or around the facility must possess the required basic clearance and credentials as required by the Facility Manager and 673rd Security Forces Squadron and are subject to inspection upon entering and leaving the site.

4.3. Escort: Individuals are required to be escorted by the Airman in-charge, all day every day while the Contractor is on site performing task order on or near Building 10571.

01020-2

5. General Notes:

Contractors are strongly encouraged to visit the site and get familiar with all of the work related to the scope of work prior to submitting a bid, to verify existing site condition and other information as noted in the scope of work and drawings, as well as to become familiar with the scope of work.

Failure to visit the site does not relieve the Contractor from the responsibility of performing all work required to provide a complete and usable project in accordance with the Contract documents.

5.1. Workmanship: All work shall be accomplished in accordance with all applicable codes. The

Contractor shall field verify all measurements, quantities, or values stated by the Government before ordering any material.

5.2. Worksite: The Contractor shall limit the work to the areas indicated by the government. The Contractor shall make every effort not to disturb or obstruct portions of the facilities still occupied by the government. The Contractor shall coordinate and schedule work with the 673 CES/CENM & Facility owner/CE offices prior to the start of any operation. The Contractor shall dispose of all construction debris off base at an approved disposal facility.

5.3. Site Security and Protection: The Contractor shall make every effort to secure the work site, allowing only authorized personnel to enter the work site. Contractor shall protect the site from damage from weather, vandalism, and/or theft.

5.4. Health/Safety: The Contractor shall be responsible for compliance with OSHA and AFOSH standards. The Contractor shall keep driveways and entrances into and around the work site clear at all times.

5.5. Damage to Existing Conditions: The Contractor shall be responsible to repair any and all damage incurred to existing Real Property/Grounds at no cost to the government. This includes any damage to the existing guard facility, supports, or any other components.

5.6. Environmental Protection and Hazardous Materials: Reference the project specifications and/or applicable laws and directives for requirements covering protection of land resources, protection of air and water quality, hazardous materials safety and general management, and storm water management.

5.7. Site Storage/Staging Area: On-site storage outside the intersection is not permitted; the Contractor shall minimize storage of materials and equipment on-site and shall coordinate with the facility manager, user coordinator, contracting officer and the construction inspector.

5.8. Engineering Requirements and Department Of Defense DOD Standards: Contractor must comply with Industry Standards; all Federal, State, and Local codes; and the following regulations at the time of issue of this project. The project shall be designed in accordance with the design and construction standards contained in the latest version of the Unified Facilities Criteria (UFC) DoD Building Code1-200-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1- 200-01. The Unified Facilities Criteria (UFC) https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc.The Unified Facility Specifications https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs , and all core UFC codes. Other codes referenced therein including but not limited to: International Building Code, National Fire Code, Life Safety Code, National Electrical Code, International Plumbing Code, and other applicable Department of Defense and Air Force regulations, Air Force Instructions AFI’s, manuals, engineering technical letters, and energy conservation criteria including Guiding Principles for Federal Leadership in High Performance and Sustainable Buildings.

https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-200-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc/ufc-1-200-01 https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc https://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs https://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs

01020-3

5.9. Contractor’s Material Testing for Quality Control: Unless otherwise called out in the MACC Statement of Work or the specific material specifications, the Contractor’s QC Plan shall meet or exceed either the State of Alaska DOT’s Materials Sampling & Frequency Table https://dot.alaska.gov/stwddes/dcsconst/assets/pdf/mstf_highway_hl.pdf or the requirements called out in the Unified Facility Specifications (UFGS), whichever is more stringent.

5.10. COVID Base Access Information: When work under this contract requires unescorted entry to controlled or restricted areas, the Contractor shall comply with AFI 31-101, Integrated Defense, and DODMAN5200.02_AFMAN 16-1405, Air Force Personnel Security Program. Contractors requiring access to any area on Joint Base Elmendorf-Richardson (JBER) shall comply with installation, state, and local COVID-19 policies and mandates and respect any guidelines or restrictions imposed by local businesses. These policies and mandates frequently change. COVID- 19 policies and mandates are found at:

https://www.jber.jb.mil/Coronavirus/ for JBER COVID-19 Policy Memo, https://covid19.alaska.gov/ for State of Alaska COVID-19 Coronavirus Information, and https://covid-response-moa-muniorg.hub.arcgis.com/pages/emergency-orders for the

Municipality of Anchorage Emergency Orders.

Failure to comply with the guidelines or restrictions may result in suspended access to

JBER or debarment. Contractors shall comply with the above-referenced documents citing the appropriate paragraphs as applicable.

5.11. Radioactive Materials Procedures: Non-Air Force organizations, except DOW organizations and DOE prime Contractors, bringing radioactive materials to Air Force installations or using them there shall have an NRC or Agreement State license authorizing work on the installation and written approval from the installation commander’s appointed approval authority, normally the base Radiation Safety Officer (RSO).

Civilian Contractors or any other agency bringing a radioactive device (including, but not limited to, soil or asphalt density meters) on Joint Base Elmendorf Richardson shall have prior approval by the Base RSO (673 AMDS/SGPB 580-4047). An application to bring a radioactive device on Joint Base Elmendorf Richardson shall be forwarded to the Base RSO at least 60 days prior to the anticipated use. The application package (two copies) shall include:

5.11..1. A copy of the NRC or Agreement State license authorizing use of the radioactive materials. The license must be current as shown by the expiration date or include a “deemed timely filed notice” from the issuing agency and either specifically list the base or grant approval for work at temporary job sites anywhere in the United States where the NRC or Agreement State has jurisdiction. EXCEPTION: DOE or DOE prime Contractors must give written certification of their exemption from NRC licensing and cite the applicable exemption of 10 CFR.

5.11..2. Copy of the operator’s qualifications and/or radiation safety training.

5.11..3. Statement of the expected start date and length of the contract.

5.11..4. A brief description of the proposed activities, to include safety precautions to be enforced.

5.11..5. A copy of that part of the Air Force contract describing work to be done at the base and the inclusive dates of the work.

https://dot.alaska.gov/stwddes/dcsconst/assets/pdf/mstf_highway_hl.pdf https://www.jber.jb.mil/Coronavirus/ https://covid19.alaska.gov/ https://covid-response-moa-muniorg.hub.arcgis.com/pages/emergency-orders

01020-4

5.11..6. The name, local address, and telephone number for the responsible local representative and the name, address, and telephone number of the RSO named on their license.

5.11..7. Statement of expected storage and security requirements or other particular needs of the Contractor.

5.11..8. Radiation dosimetry results for the operator for the prior calendar year, if applicable.

5.11..9. Copies of last two leak checks (if appropriate). Under no circumstances will an unlicensed radioactive device be used on Joint Base Elmendorf Richardson. Any questions on a Contractor’s responsibility, regarding this topic, shall be directed to the base RSO prior to the Contractor starting work.

5.11..10. Radiation dosimetry results for the operator for the prior calendar year, if applicable.

5.11..11. An acknowledgment that the base RSO can make periodic checks to ensure that Contractor personnel follow radiation safety practices to prevent exposure to Air Force personnel and avoid contamination of Government property. In addition, the base RSO shall have authority to suspend Contractor operations believed to be unsafe.

Agreement State licensees using NRC regulated materials must supply a copy of the NRC Form 241 approved by the base’s NRC Region according to 10 CFR 150.20. State Licensees may not work on Air Force or other installations where exclusive federal jurisdiction exists for more than 180 calendar days per calendar year without first getting an NRC license 3.4.19.4. Non-Air Force organizations that do not have an NRC or Agreement State License and who are not DOE or DOE prime Contractors exempted for licensing must contact AFMOA/SGPR for guidance and approval to use radioactive materials on an Air Force installation.

The Contractor shall notify the RSO immediately upon completion of use, and when the material(s) are removed from the installation.

Any and all accidents or incidents involving the radioactive materials, and any known or potential exposure of non-Contractor personnel to radiation shall be reported immediately to the RSO (673 AMDS/SGPB, 580-4047) and the Contracting Officer, and operations shall be suspended until the circumstances have been evaluated by the RSO, and approval to re-start has been received by the Contracting Officer.

END OF SECTION

File details come from the government source that posted it. Updated .