This performance work statement and related solicitation describe a requirement for demolition services at Joint Base Elmendorf-Richardson in Alaska. The contractor will demolish four unaccompanied housing buildings totaling approximately 120,000 square feet. Services include abatement of hazardous materials, removal of debris, site restoration, and compliance with environmental regulations. The solicitation is set aside for economically disadvantaged woman-owned small businesses and is subject to Service Contract Labor Standards. The 673d Contracting Squadron issued the solicitation with a tentative site visit on June 1st, 2023 and no established award date due to lack of available funds. The contractor must thoroughly survey the buildings for hazardous materials and waste and properly dispose all materials.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HJZH 21-1099, Demo Unaccompanied Housing (Multi Facility), Bldgs 455, 456, 457, 458
Version 1.2 Page 1 of 9
PERFORMANCE WORK STATEMENT (PWS)
FOR
DEMO UNACCOMPANIED HOUSING (MULTI FAC), BLDG 455, 456, 457, 458
AT
JOINT BASE ELMENDORF-RICHARDSON, AK
7 June 2023
(Solicitation # FA5000-23-Q-0035)
PROJECT NUMBER: HJZH 21-1099
Revision 002
Version 1.2 Page 2 of 9
1.1 General Requirements: Provide all labor, materials, and equipment necessary to complete the work for the demolition, removal, and/ or disposal of four separate, three-story, wood framed buildings, in accordance with the PWS, the attached specifications, and drawings. The Contractor shall comply with all applicable Federal, State, and local regulations. Please see attached drawings for approximate dimensions and locations.
The Contractor shall not rely on drawings, and is responsible for field verifying all measurements and locations of utilities to be demolished prior to works. The Contractor will coordinate with Doyon Utilities for the proper location, disconnection, and removal of utilities prior to demolition of the buildings. Utilities will be located and demolished by Doyon. All utilities for these facilities are owned by Doyon Utilities except for the natural gas, which is owned by Enstar.
1.2 Project Location: All work under this project will be performed on Joint Base Elmendorf-Richardson (JBER), Alaska. These buildings are located at 455, 456, 457, and 458 Access road on JBER Richardson.
1.3 Incidental Work: Incidental work may be required to accomplish the intent of the contract. The Contractor is responsible to ensure all incidental work required for a complete demolition is included in their proposal. Work includes demolition-related tasks on items which may not be attached to the structure, such as sidewalks, parking lots, vehicle plug-in stations, steam vaults, some underground electrical lines, landscaping, etc. All work indicated shall be accomplished for the original proposal price, including special work times required for utility outages, and repair of damages to the site, by the Contractor.
1.3.1. The Contractor will remove all portions of the buildings and not leave any structure in the ground. The Contractor shall flag trees within the demolition area for Government approval for removal or transplanting. Care shall be taken to protect all other trees from debris and equipment.
1.3.2. Upon project completion, the Contractor will leave a levelled area that is top soiled and seeded. The Contractor will water newly-seeded areas and maintain until the first cutting. Cutting will not occur until the grass is six inches in length.
First cutting is the responsibility of the Contractor.
1.3.3. The Contractor shall completely remove slab on grade, foundation, foundation supports, foundation walls and utilities within the construction site. Termination of utilities shall be as outlined in Section 1.7.
1.3.4. The Contractor shall dispose of all solid waste outside of the military installation.
1.3.5. Disposal of asphalt and clean concrete will be on JBER at the main gravel pit located near the east end of the 06/24 runway off Richardson drive. Coordinate with the project inspector for proper disposal location of asphalt and clean concrete.
Version 1.2 Page 3 of 9
1.3.6. Demolish the handicap ramps near the entrances of the main public sidewalk on Dyea Ave. Install a new sidewalk, with curb and gutter along the roadway frontage, to meet existing sidewalk ends at the extent of the demo area.
Contractor will take care not to damage existing parking lot/sidewalks, any damage will be repaired by the Contractor at no additional cost.
1.3.7. Keys and locks: Coordinate with 773CES lock shop to remove lock cores from all keyed doors prior to demolition.
1.3.8. Community Mailboxes: The Contractor shall coordinate with USPS to remove communal post office boxes onsite, prior to demolition.
1.3.9. HVAC: The Contractor shall coordinate with 673 CES to allow Aurora Housing to reclaim HVAC system components.
1.3.10. Ozone Depleting Substances and Alternatives: Contractor will ensure all equipment containing ozone depleting substances are evacuated prior to disposal. Any equipment that contains ozone depleting substances that the Department Logistics Agency has identified as mission-critical will be turned into DLA IAW Department of Defense Ozone Depleting Substances Customer Turn- In Procedures, November 2021.
1.4 Hazardous Materials and Waste Disposal:
1.4.1. Provide a complete hazardous materials and hazardous waste survey for buildings 455, 456, 457, and 458 including testing, test reports and identification of all hazardous containing materials and lead containing materials that exist.
These structures are anticipated to have asbestos, lead, and PCB containing material. Please refer to included reports. This should not alleviate the Contractor from sampling any material they feel may contain asbestos. The Contractor may request additional time for testing if it is deemed necessary. A complete survey shall be submitted no later than 30 days prior to the beginning of any demolition work.
1.4.2. The Contractor must prepare/submit all required notifications to Alaska Occupational Safety and Health (AKOSH) and EPA Region 10, consistent with notification requirements for Asbestos Containing Material (ACM) and regulated ACM found in 40 CFR 61 Subpart M. In addition, an asbestos abatement plan must be prepared that includes, but is not limited to, a description of the work, methods of containment and airborne fiber mitigation, management of waste, disposal, air testing and copies of certifications for workers. Contractor shall submit copies of notifications required under 40 CFR 61.145(a)(1), 61.145(a)(3), and 61.145(b) to the Contracting Officer (CO), and the Asbestos Program Officer (Toxics PM).
1.4.3. After all hazardous materials (if any) are removed, the Contractor will compile a
Version 1.2 Page 4 of 9 list to indicate the quantities of materials removed and supply the information to the 673 CES/CEIE office. The Contractor shall abide by all applicable environmental provisions.
1.4.4. Remove and properly dispose of all non-hazardous and hazardous waste, including but not limited to, asbestos and lead-containing materials, light bulbs, ballasts, glycol, thermostats, polychlorinated biphenyls (PCBs), and other reportable materials; in accordance with JBER Environmental Protection Specifications, local, State, and Federal regulations.
1.4.5. Records of non-hazardous solid waste landfilled (hauling/weight tickets/landfill receipts/etc.) are to be provided to the COR and 673 CES/CEIE Solid Waste Program Manager, at minimum on a quarterly basis or prior to project completion, whichever occurs first.
1.4.6. Salvage, reuse, or recycle metals (i.e., conduit, piping, wiring, etc.) to the greatest extent possible. DoD requires a 60% diversion rate for construction and demolition projects in accordance with Executive Orders and DoD Instruction requirements. Diversion includes reuse, donation, recycling, and composting. Waste diversion reports, including associated costs and weight tickets must be submitted monthly to the 673 CES/CEIE Solid Waste Program Manager for any materials disposed or diverted on or off base, including concrete and asphalt. Reports are due by the first business day of the following month or prior to project completion, whichever comes first. Scrap metal must be recycled through a reputable scrap metal recycler off base, with weight tickets provided.
1.5 Site Restoration:
1.5.1. Backfill material will be made available to the Contractor from the main gravel location off Richardson drive. The exact location of borrow material will be determined at the time of need. The Contractor will be responsible for loading and excavation of pit material. There is no processed material available at the pit for use by this contract. Any processed material needed by the Contractor will be purchased off-installation and hauled on by the Contractor at his expense. Topsoil is not available on base and must be purchased and hauled by the Contractor.
1.5.2. Any grassed area disturbed by demolition activity will be left level and seeded.
Provide approved seed, or hydro-seed, lawn material over all areas not getting asphalt or concrete. Install topsoil & hydro seed for all grass areas disturbed and sidewalks, drives & utilities that have been removed. Fill top 6" with topsoil compacted to 85% of maximum density and prepare surface for seeding. The Contractor supplied seed shall comply with the Integrated JBER Natural Resources Management Plan (INRMP) dated 2020. Urban forestry is discussed in Section 7.7.7 Management Strategies for Vegetation Establishment and table
Version 1.2 Page 5 of 9
7-7 for recommended native seed mix. JBER managers also recommend following State of Alaska and Cooperative Extension Service guidance on what species can and cannot be planted in this area.
1.6 Safety
1.6.1. Site Specific Safety Plan: The Contractor shall provide a site-specific safety plan, written by a certified safety professional and approved by the Government.
1.6.2. Fencing: Provide temporary fence for security around the demolition site prior to beginning abatement and maintain through project completion. Temporary fences shall be chain-link, minimum 6’- 0” high, and shall be continuous and secure around site, free from gaps or breaks. Appropriate signage shall be conspicuously posted on fence, around construction site, including but not limited to Danger – Keep Out! Building demolition limits shall extend to 75 feet around perimeter of building, including sidewalks, parking lot, and electrical plug-in stations.
1.6.3. “Fugitive Dust: Contractor will take measures to prevent generation of fugitive dust during active demolition and when grading the area. These measures will be implemented until vegetation has been established. Measures include watering down areas of bare mineral soil.”
1.7 Utilities Work: The Contractor will coordinate with the 673 CES Inspector prior to demolition of the buildings. Doyon Utilities will demolish the utility service (electric, sewer, water, gas) in coordination with the Demolition Contractor. The Contractor shall provide a work schedule for the demolition of the structures to 673 CES to ensure proper coordination with Doyon. Contractor will provide a work start notice prior to any work start and shall provide a minimum three (3) weeks’ notice for approval for any work that will require a shutdown of utilities affecting other facilities.
1.7.1. Electrical: The Contractor shall be responsible for coordinating use of on-site power with Doyon Utilities, LLC (DU) and shall provide any temporary electrical connection components required, or shall provide their own independent power prior to beginning the abatement phase of the work. All electrical work will be coordinated with DU and per their requirements. The Contractor shall notify the Government 10 days prior to beginning work on building 455, 456, 457, and
458. All interior electrical equipment within the building limits shall be the property of the Contractor to salvage or dispose of as required. All vehicle outlets will be the responsibility of the Contractor, not DU. Final termination shall be coordinated with the Government and shall be made at the transformer serving the building. Additionally, the Contractor will remove the meter base/disconnect, remove electrical conductors, plug open end of conduit at electrical vault and at open end at demo excavation limits. Abandoned in-place conduits need to be tracked in DU GIS.
Version 1.2 Page 6 of 9
1.7.2. Communications: The Contractor shall be responsible for notifying the 673d Communications Squadron (673 CS), Maintenance Support, minimum ten (10) business days prior to beginning any communications demolition. The Contractor shall be responsible for complying with Attachment 3, JBER Telecommunications Installation Standards, applicable to the termination. The Contractor must ensure no live circuits or communication equipment remains in the building prior to demolition.
1.7.2.1. Cables
In the case of cables in a duct or conduit system, it is required that all telecommunications cables in the plant (copper, fiber optic, coaxial, etc.) be demolished back to the nearest service delivery point, such as a splice case in a manhole. At this location, the distribution cable count (copper pairs, fiber strands, etc.) will be spliced back into the main trunk cable so that the pair count is once again available the full length of the backbone trunk cable. In cases where the distribution count is coming off the end of a backbone cable count, the count will be recovered and prepared for future use, such as terminating with a pluggable, modular type splice for copper counts, or dressing out fiber strands in preparation for fusion splicing, then managing and sealing the counts in an approved splice case assembly. The ducts or conduits will be cut off and the ends terminated (properly plugged or end capped) for possible future use. Care will be taken to preserve without damage or collapsing the remaining duct or conduit going back to the nearest communications manhole.
1.7.2.2. Direct Buried Cabling
The Contractor shall ensure cables will be cut-off, clear capped with pic filled mods (pic-a-bonds or 710), encased in a preformed stainless-steel splice case, filled with re-enterable, and marked with a 3M EMS locate marker and buried 36” below grade. Contact 673th Communications Squadron at 907-782-8337, or 907-552-2165; prior to demolition and trenching backfill.
1.7.3 Steam Lines: Steam lines are present on the site. Where lines come above ground the Contractor is responsible for cutting down the portion above ground, to a minimum of 12 inches below grade, and filling the line with grout or concrete.
Steam pits shall be removed from site.
1.7.3. Other utilities: Other utilities that may be part of this contract could include AT&T and GCI communications. The Contractor will verify that these other utilities companies are contacted. If necessary for completion of demolition, the Contractor shall ensure these other utilities have been removed, as necessary.
1.7.4. Mechanical: The Contractor shall remove and dispose of all mechanical equipment within buildings 455, 456, 457, and 458; and properly remove and dispose of any hazardous material and hazardous waste from any equipment prior to disposal.
Version 1.2 Page 7 of 9
1.7.5. Fire Alarm Panels: The Contractor shall notify the 773 CES Alarm Shop prior to demolition to give shop personnel an opportunity to remove the Fire Alarm Panel, transceivers, and antenna mast from the buildings.
1.8 Environmental Coordination: All work shall be performed in accordance with JBER Environmental Requirements.
1.8.1. Hazardous materials/ hazardous waste abatement: Hazardous materials and hazardous waste expected to be encountered and removed by the Contractor include Asbestos (ACM), lead including lead-based paint (LBP), glycol, light bulbs, ballasts, and PCB’s. Other hazardous waste and hazardous materials containers may be encountered as determined through the required hazardous waste testing performed by the Contractor. All required sampling, testing, documentation, and disposal shall be by the Contractor as a part of the resulting contract work.
1.8.2. The Contractor is responsible for abatement of all hazardous materials and hazardous waste from the facilities identified for demolition. Competent Persons shall perform all abatement. The Competent Persons shall be trained, knowledgeable, and qualified in the techniques of abatement, handling and disposal of hazardous materials and the subsequent cleaning of contaminated areas. The Contractor and his personnel shall comply with all applicable Federal, State, and local regulations to perform the work of this contract.
1.8.3. User knowledge and/or sampling is required to determine if waste is hazardous or non-hazardous, as defined under RCRA Subtitle C and RCRA Subtitle D regulations. Non-hazardous waste must be disposed at a permitted RCRA Subtitle D (non-hazardous waste) landfill. All disposals shall be in accordance with the Contractor's Waste Disposal and Recycling Plan, as included in the Environmental Protection Plan.
1.8.4. A Storm Water Pollution Prevention Plan (SWPPP) and Notice of Intent (NOI) for coverage under the Alaska Construction General Permit (ACGP) shall be completed and submitted to the Alaska Department of Environmental Conservation (ADEC). The SWPPP shall be submitted to JBER’s MS4 Operator (673 CES/CEIEC water quality program manager) for review prior to commencing ground disturbance.
1.8.5. All Contractor personnel operating on Joint Base Elmendorf- Richardson (JBER) must abide by the most current version of the JBER Hazardous Waste Management Plan, JBER Spill Plan, and the JBER Integrated Solid Waste Management Plan.
1.8.6. The facilities to be demolished are adjacent to habitat in which little brown bats (LBB) have been detected. LBB are managed as an unclassified game species, and therefore may not be harassed or killed except under the terms of a permit
Version 1.2 Page 8 of 9 issued by the Alaska Department of Fish and Game. If LBB are discovered in the facilities to be demolished, notify Conservation Law Enforcement, or the JBER Bat Biologist.
1.9. CONTRACTOR PROJECT MANAGEMENT: The Contractor shall appoint a project manager to serve as the single point-of-contact and liaison between the Contractor and the Contracting Officer or representative for all work under the contract. Upon receipt of the Notice to Proceed (NTP), the Contractor shall immediately provide the name of the designated individual and contact information to the Contracting Officer, in writing. The Project Manager will be responsible for the complete coordination of all work under the contract.
1.9.1. Quality Control Plan (QCP): The Contractor shall create a comprehensive QCP consisting of controls to ensure quality of demolition and recycling within a safe manner. The QCP shall include an organization chart/listing of Contractor key personnel (e.g. Project Manager, Site Superintendent, etc.) with clearly established roles and responsibilities within the company. The QCP shall also include a demolition plan which complies with standards as listed in Unified Facilities Guidelines Specification 02 41 00, Demolition
1.9.2. At the minimum, the demolition plan shall contain a detailed description of methods and equipment to be used for each operation and the sequence of operations; the demolition schedule and phasing; the site safety plan, abatement, and hazardous waste disposal plan; construction debris and recycling plan, and environmental protection.
1.9.3. The Contractor shall submit the QCP to the Contracting Officer within 10 days of award. The Contractor shall not proceed until the QCP has been finalized and accepted by the Contracting Officer. The final QCP shall be incorporated into this PWS. Any revisions or corrections directed by the Contracting Officer shall be completed for the Contracting Officer’s review within five business days.
1.9.4. Reports: All Contractor activities, inspections and tests must be verifiable, and contain sufficient information to provide complete documentation of the Contractor’s activities, as part of this requirement. Reports shall include a record of deficiencies, if any, and corrective actions taken. Reports shall be submitted to the Government daily no later than 1200 hours the first working day following the week which the report covers; or at a frequency specified by the Contracting Officer.
Version 1.2 Page 9 of 9
2. SERVICES SUMMARY (SS):
Performance Objective Performance Threshold
Method of Surveillance Deficiency Resolution
SS 1:
Demolish Facilities and grounds
Facility demolished All materials removed from the site in compliance (100%) with the PWS and applicable environmental laws and regulations
Government inspection (100%)
Contractor re-performance and payment of Contractor caused fines
SS 2:
Remove debris off deconstruction site
All material removed from the site of the existing facility and waste disposed of properly
Government inspection (100%)
Contractor re-performance and payment of Contractor caused fines
SS 3:
Inventory HAZMAT
Furnish the Government with an accurate inventory of HAZMAT to include type, volume, and location
Government inspection (100%)
Contractor re-performance
SS 4:
Restore site
Perform all site restoration work as described in the PWS
Government inspection (100%)
Contractor re-performance
PWS Attachments:
1. Project As-Built/Site Plan Drawings
2. AF Form 66, Schedule of Materials Submittals
3. JBER Telecommunications Standards
4. JBER Environmental Protection Specifications
5. JBER Natural Resources Management Plan
6. Unified Facilities Guide Specifications (UFGS) 02 41 00 Demolition
-END OF SECTION-