Attachment 9. Price Schedule (Contractor).pdf

PDF 133 KB Posted

Attached to
P400 - Demolition of four buildings at Fort Richardson, JBER, AK.
Solicitation number
FA500023Q0035
Issued by

About this file

This document includes an attachment to a price schedule and details of a related federal contract opportunity. The price schedule attachment requests pricing from contractors to demolish four unaccompanied housing units at Joint Base Elmendorf-Richardson in Alaska. Contractors are asked to provide unit pricing and total costs for demolition work. The schedule stipulates a 365-day performance period from notice to proceed and that the proposal will remain valid through a specified date.

The related federal contract opportunity is a solicitation from the 673d Contracting Squadron seeking offers from economically-disadvantaged woman-owned small businesses to perform the demolition work outlined in the price schedule attachment. A site visit is scheduled for June 1, 2023, with final details to be provided in an amendment. The solicitation notes that funds are not presently available and no award will be made until funding is obtained. Offerors are advised the solicitation may be cancelled before or after closing.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OPEN MARKET HJZH 21-1099

Attachment 9 - Price Schedule

PRICE SCHEDULE

HJZH 21-1099

455, 456, 457, 458 Access Rd Joint Base Elmendorf/ Richardson 99506

CONTRACTOR ORGANIZATION ADDRESS

The Contractor shall furnish all design, plant, labor, equipment, supplies, materials, appliances, transportation and perform all work (including work of an incidental nature), for HJZH 21-1099 455, 456, 457, 458 Access Rd Joint Base Elmendorf/ Richardson, Alaska, complete, in strict accordance with the Statement of Work and subject to the terms and conditions of the contract.

ITEM DESCRIPTION QUANTITY UNIT UNIT PRICE TOTAL COST

0001 Demolition 1 Project $ $

TOTAL CONSTRUCTION COST $

Work shall start within 10 days after date of the receipt of the Notice to Proceed, and shall be completed within 365 days.

This performance period includes administrative time, submittal time, material ordering time, and physical construction time.

AMENDMENTS ACKNOWLEDGED___________________________

PROPOSAL VALID THROUGH (DATE) ________________________

SIGNATURE DATE SIGNED

CONTRACTOR ORGANIZATION:
ADDRESS:
AMENDMENTS ACKNOWLEDGED:
PROPOSAL VALID THROUGH DATE:
Date2_af_date:
Text3:

File details come from the government source that posted it. Updated .