This document contains Questions and Answers related to a Hazardous Materials Abatement IDIQ contract opportunity, solicitation number FA500023B0003.

The key details are:

  • The contract requires thorough below-ground surface investigation for the seed project, including coordination for dig permits and hollow stem auguring.
  • The contract requires the State of Alaska certified asbestos abatement Supervisor and Abator, as well as lead abatement Supervisor and Worker personnel, to be direct employees of the prime contractor.
  • The government is not considering removing the actual abatement/construction work from this IDIQ and soliciting it separately.
  • This is an IDIQ contract with a seed project valued between $25,000 and $100,000. The overall IDIQ value is between $5,000,000 and $10,000,000. It is a 100% small business set-aside. All questions must be submitted by May 22, 2024 at 1:00 PM AKDT.

View the file

Other files

File Type Posted
Abstract.pdf PDF
Solicitation Amendment FA500024B00030002.pdf PDF
Solicitation Amendment FA500024B00030001 SF 30.pdf PDF
Solicitation - FA500024B0003.pdf PDF
Attachment 2_AF IMT 3000_2003091_VI_ Submittal.pdf PDF
Attachment 6_Dig Permit Custom Map Elmendorf.pdf PDF
Attachment 8_Dig Permit Fillable Template_ 673ABW Form 3_20200423_Prescribed by 673ABWI32_1007.pdf PDF
Attachment 9_JBER IFS Vol 1 Elmendorf_31 January 2019.pdf PDF
Attachment 10_JBER IFS Vol 2 Richardson_14 February 2019.pdf PDF
Attachment 14_JBER Hazardous Waste Management Plan - 2024.pdf PDF
Attachment 17_Wage Determination_AK20240001 02_23_2024.pdf PDF
Attachment 20 - Seed Project As-builts.pdf PDF
Attachment 4_AF IMT 3065_199600401_VI_Progress Report.pdf PDF
Attachment 7_Dig Permit Custom Map Richardson.pdf PDF
Attachment 16_JBER Integrated Hazardous Material Plan 25 Oct 2020.pdf PDF
Attachment 21 - Seed Project Price Schedule.pdf PDF
Attachment 23 - Seed Project Location map.pdf PDF
Attachment 24 - FOPR Seed Project FXSB 24-1008.pdf PDF
Attachment 19 - Seed Project SOW.pdf PDF
Attachment 1_HMAC _Dated 12 Dec 2023 SOW.pdf PDF
Attachment 3_AF IMT 3064_2003091_VI_Progress Schedule.pdf PDF
Attachment 5_Contractors Fire Safety Guide_Rev 14_14 September 2017.pdf PDF
Attachment 11_JBER CAD GIS Record Drawing As- Built Standard_Dec 2019.pdf PDF
Attachment 12_Environmental Precon Checklist_Updated Sep 19.pdf PDF
Attachment 13_JBER 1500_1600 Environmental Protection and Solid Waste Management Specs 26 Jul 23.pdf PDF
Attachment 15_JBER Telecom Criteria Requirements_ February 11 2021.pdf PDF
Attachment 18_Service Contract Act_Dec25_2023-Revision 19.pdf PDF
Attachment 22 - Seed Project AF Form 66.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ques�ons and Answers: Hazardous Materials Abatement IDIQ – FA500024B0003

Ques�ons in BLACK

Answers in RED

Q1. For the seed project, is the objec�ve to inves�gate and test surficial soils around the buried fuel tank, sep�c tank and water tank or conduct a more thorough below ground surface inves�ga�on requiring dig permit coordina�on and hollow stem auguring?

A1. Yes, conduct thorough below ground surface inves�ga�on.

Q2. Will the contract require that the State of Alaska cer�fied asbestos abatement Supervisor and Abator and lead abatement Supervisor and Worker personnel be direct employees of the prime contractor? Or will the contract allow these personnel to be employees of the prime’s subcontractor?

A2 Yes, contract to require that the State of Alaska cer�fied asbestos abatement Supervisor and Abator and lead abatement Supervisor and Worker personnel be direct employees of the prime contractor.

Q3. Is it possible all the stuff related to actual abatement/construc�on work be removed from this IDIQ and solicited separately as most of our local pool of folks qualified for the assessment side?

A3. The government is not considering this at this �me.