Time and Attendence Required
Facility No Nomenclature Brand Type Capacity Total Boiler Capacity Montly Quarterly Semi-Annual Annually
2218 D3025 130 2950 BOILER, HOT WATER, O/G/C, 120 TO 500 MBH, ANNUALIZED Burnham Hydronic 276 NA X X X X NA
2218 D3025 130 2950 BOILER, HOT WATER, O/G/C, 120 TO 500 MBH, ANNUALIZED Burnham Hydronic 276 NA X X X X NA
2218 D3025 130 2950 BOILER, HOT WATER, O/G/C, 120 TO 500 MBH, ANNUALIZED Burnham Hydronic 100 NA X X X X NA
6104 D3025 130 2950 BOILER, HOT WATER, O/G/C, 120 TO 500 MBH, ANNUALIZED Burnham Hydronic 850 NA X X X X NA
6104 D3025 130 2950 BOILER, HOT WATER, O/G/C, 120 TO 500 MBH, ANNUALIZED Burnham Hydronic 850 NA X X X X NA
6104 D3025 130 2950 BOILER, HOT WATER, O/G/C, 120 TO 500 MBH, ANNUALIZED Burnham Hydronic 850 NA X X X X NA
6346 D3025 130 2950 BOILER, HOT WATER, O/G/C, 120 TO 500 MBH, ANNUALIZED Neo Them Hydronic 850 NA X X X X NA
6346 D3025 130 2950 BOILER, HOT WATER, O/G/C, 120 TO 500 MBH, ANNUALIZED Neo Them Hydronic 850 NA X X X X NA
7137 D3025 130 2950 BOILER, HOT WATER, O/G/C, 120 TO 500 MBH, ANNUALIZED Neo Them Hydronic 285 NA X X X X NA
7137 D3025 130 2950 BOILER, HOT WATER, O/G/C, 120 TO 500 MBH, ANNUALIZED Neo Them Hydronic 285 NA X X X X NA
7309 D3025 130 2950 BOILER, HOT WATER, O/G/C, 120 TO 500 MBH, ANNUALIZED Neo Them Hydronic 850 NA X X X X NA
7309 D3025 130 2950 BOILER, HOT WATER, O/G/C, 120 TO 500 MBH, ANNUALIZED Neo Them Hydronic 850 NA X X X X NA
8559 D3025 130 2950 BOILER, HOT WATER, O/G/C, 120 TO 500 MBH, ANNUALIZED Laars Hydronic 850 NA X X X X NA
8559 D3025 130 2950 BOILER, HOT WATER, O/G/C, 120 TO 500 MBH, ANNUALIZED Laars Hydronic 850 NA X X X X NA
9361 D3025 130 2950 BOILER, HOT WATER, O/G/C, 120 TO 500 MBH, ANNUALIZED Hydronic 400 NA X X X X NA
9361 D3025 130 2950 BOILER, HOT WATER, O/G/C, 120 TO 500 MBH, ANNUALIZED Hydronic 400 NA X X X X NA
10555 D3025 130 2950 BOILER, HOT WATER, O/G/C, 120 TO 500 MBH, ANNUALIZED Hydronic 202 NA X X X X NA
10571 D3025 130 3950 BOILER, HOT WATER, O/G/C, 500 TO 1000 MBH, ANNUALIZED Laars Hydronic 4174 NA X X X X NA
10571 D3025 130 3950 BOILER, HOT WATER, O/G/C, 500 TO 1000 MBH, ANNUALIZED Laars Hydronic 4174 NA X X X X NA
7265 D3025 140 1950 BOILERS, STEAM, O/G/C, UP TO 120 MBH, ANNUALIZED Burnham LPS 51 Under 1,000,000 Btu/h X X X Once every week during operation
7265 D3025 140 1950 BOILERS, STEAM, O/G/C, UP TO 120 MBH, ANNUALIZED Burnham LPS 51 Under 1,000,000 Btu/h X X X Once every week during operation
9559 D3025 140 1950 BOILERS, STEAM, O/G/C, UP TO 120 MBH, ANNUALIZED LPS 115 Under 1,000,000 Btu/h X X X Once every week during operation
5126 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 347 Under 1,000,000 Btu/h X X X X Once every week during operation
2212 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 150 Under 1,000,000 Btu/h X X X X Once every week during operation
2212 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 150 Under 1,000,000 Btu/h X X X X Once every week during operation
5329 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 200 Under 1,000,000 Btu/h X X X X Once every week during operation
5329 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 200 Under 1,000,000 Btu/h X X X X Once every week during operation
5333 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 200 Under 1,000,000 Btu/h X X X X Once every week during operation
5126 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 347 Under 1,000,000 Btu/h X X X X Once every week during operation
5201 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 202 Under 1,000,000 Btu/h X X X X Once every week during operation
5201 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 202 Under 1,000,000 Btu/h X X X X Once every week during operation
6262 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 200 Under 1,000,000 Btu/h X X X X Once every week during operation
6262 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 200 Under 1,000,000 Btu/h X X X X Once every week during operation
6211 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 250 Under 1,000,000 Btu/h X X X X Once every week during operation
6211 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 250 Under 1,000,000 Btu/h X X X X Once every week during operation
7250 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 200 Under 1,000,000 Btu/h X X X X Once every week during operation
7250 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 200 Under 1,000,000 Btu/h X X X X Once every week during operation
6211 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 250 Under 1,000,000 Btu/h X X X X Once every week during operation
7508 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 200 Under 1,000,000 Btu/h X X X X Once every week during operation
7508 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 200 Under 1,000,000 Btu/h X X X X Once every week during operation
5253 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 347 Under 1,000,000 Btu/h X X X X Once every week during operation
8124 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 250 Under 1,000,000 Btu/h X X X X Once every week during operation
8124 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 250 Under 1,000,000 Btu/h X X X X Once every week during operation
8197 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 347 Under 1,000,000 Btu/h X X X X Once every week during operation
5253 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 347 Under 1,000,000 Btu/h X X X X Once every week during operation
8197 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 347 Under 1,000,000 Btu/h X X X X Once every week during operation
8199 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 250 Under 1,000,000 Btu/h X X X X Once every week during operation
8199 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 250 Under 1,000,000 Btu/h X X X X Once every week during operation
8306 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 231 Under 1,000,000 Btu/h X X X X Once every week during operation
8306 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 231 Under 1,000,000 Btu/h X X X X Once every week during operation
8317 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 231 Under 1,000,000 Btu/h X X X X Once every week during operation
8317 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 231 Under 1,000,000 Btu/h X X X X Once every week during operation
8364 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 483 Under 1,000,000 Btu/h X X X X Once every week during operation
6210 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 483 Under 1,000,000 Btu/h X X X X Once every week during operation
8364 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 483 Under 1,000,000 Btu/h X X X X Once every week during operation
8450 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 231 Under 1,000,000 Btu/h X X X X Once every week during operation
6210 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 483 Under 1,000,000 Btu/h X X X X Once every week during operation
8450 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 231 Under 1,000,000 Btu/h X X X X Once every week during operation
8535 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 231 Under 1,000,000 Btu/h X X X X Once every week during operation
8535 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 231 Under 1,000,000 Btu/h X X X X Once every week during operation
8574 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 347 Under 1,000,000 Btu/h X X X X Once every week during operation
8574 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 347 Under 1,000,000 Btu/h X X X X Once every week during operation
9268 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 483 Under 1,000,000 Btu/h X X X X Once every week during operation
9268 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 483 Under 1,000,000 Btu/h X X X X Once every week during operation
9341 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 347 Under 1,000,000 Btu/h X X X X Once every week during operation
9341 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 347 Under 1,000,000 Btu/h X X X X Once every week during operation
9477 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 231 Under 1,000,000 Btu/h X X X X Once every week during operation
9477 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 231 Under 1,000,000 Btu/h X X X X Once every week during operation
10306 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 231 Under 1,000,000 Btu/h X X X X Once every week during operation
10306 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 231 Under 1,000,000 Btu/h X X X X Once every week during operation
10488 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 347 Under 1,000,000 Btu/h X X X X Once every week during operation
Preventive Maintenance FrequencyInventory
Draft
10488 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 347 Under 1,000,000 Btu/h X X X X Once every week during operation
10555 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 202 Under 1,000,000 Btu/h X X X X Once every week during operation
11540/11550 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 231 Under 1,000,000 Btu/h X X X X Once every week during operation
11540/11550 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 231 Under 1,000,000 Btu/h X X X X Once every week during operation
11540/11550 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED LPS 231 Under 1,000,000 Btu/h X X X X Once every week during operation
6258 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 349 Under 1,000,000 Btu/h X X X X Once every week during operation
6258 D3025 140 2950 BOILERS, STEAM, O/G/C, 120 To 500 MBH, ANNUALIZED Burnham LPS 349 Under 1,000,000 Btu/h X X X X Once every week during operation
6230 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 808 Under 1,000,000 Btu/h X X X X Once every week during operation
6230 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 808 Under 1,000,000 Btu/h X X X X Once every week during operation
6315 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 959 Under 1,000,000 Btu/h X X X X Once every week during operation
6315 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 959 Under 1,000,000 Btu/h X X X X Once every week during operation
7113 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED Burnham LPS 808 Under 1,000,000 Btu/h X X X X Once every week during operation
7113 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED Burnham LPS 808 Under 1,000,000 Btu/h X X X X Once every week during operation
7163 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED Burnham LPS 808 Under 1,000,000 Btu/h X X X X Once every week during operation
7163 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED Burnham LPS 808 Under 1,000,000 Btu/h X X X X Once every week during operation
7181 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED Burnham LPS 808 Under 1,000,000 Btu/h X X X X Once every week during operation
7181 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED Burnham LPS 808 Under 1,000,000 Btu/h X X X X Once every week during operation
7377 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED Burnham LPS 959 Under 1,000,000 Btu/h X X X X Once every week during operation
7377 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED Burnham LPS 959 Under 1,000,000 Btu/h X X X X Once every week during operation
8378 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 959 Under 1,000,000 Btu/h X X X X Once every week during operation
8378 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 959 Under 1,000,000 Btu/h X X X X Once every week during operation
5223 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED Burnham LPS 646 Under 1,000,000 Btu/h X X X X Once every week during operation
5223 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED Burnham LPS 646 Under 1,000,000 Btu/h X X X X Once every week during operation
8549 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED Burnham LPS 646 Under 1,000,000 Btu/h X X X X Once every week during operation
8549 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED Burnham LPS 646 Under 1,000,000 Btu/h X X X X Once every week during operation
9327 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 959 Under 1,000,000 Btu/h X X X X Once every week during operation
9327 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 959 Under 1,000,000 Btu/h X X X X Once every week during operation
2204A D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED Burnham LPS 808 Under 1,000,000 Btu/h X X X X Once every week during operation
2204A D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED Burnham LPS 808 Under 1,000,000 Btu/h X X X X Once every week during operation
9336 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 808 Under 1,000,000 Btu/h X X X X Once every week during operation
9336 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 808 Under 1,000,000 Btu/h X X X X Once every week during operation
9551 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 646 Under 1,000,000 Btu/h X X X X Once every week during operation
9551 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 646 Under 1,000,000 Btu/h X X X X Once every week during operation
10337 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 808 Under 1,000,000 Btu/h X X X X Once every week during operation
10427 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 808 Under 1,000,000 Btu/h X X X X Once every week during operation
10427 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 808 Under 1,000,000 Btu/h X X X X Once every week during operation
10435 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 646 Under 1,000,000 Btu/h X X X X Once every week during operation
10435 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 646 Under 1,000,000 Btu/h X X X X Once every week during operation
10437 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 808 Under 1,000,000 Btu/h X X X X Once every week during operation
10441 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 808 Under 1,000,000 Btu/h X X X X Once every week during operation
10441 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 808 Under 1,000,000 Btu/h X X X X Once every week during operation
11575 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 646 Under 1,000,000 Btu/h X X X X Once every week during operation
11575 D3025 140 3950 BOILERS, STEAM, O/G/C, 500 to 1000 MBH, ANUALIZED LPS 646 Under 1,000,000 Btu/h X X X X Once every week during operation
2204 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 2154 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
4241 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 4551 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
4241 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 4551 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
4109 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Laars LPS 4551 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
4109 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Laars LPS 4551 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
4109 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Laars LPS 4551 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
4109 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Laars LPS 4551 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
4109 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Laars LPS 4551 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
4109 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Laars LPS 4551 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
5250 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 3957 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
5250 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 3957 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
5257 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 3580 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
5257 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 3580 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
6253 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1342 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
5333 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1110 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
5385 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1110 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
6136 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1714 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
6136 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1714 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
6253 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1342 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
6260 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 3353 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
6260 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 3353 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
6263 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 3739 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
6263 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 3739 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
6263 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 3739 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
6263 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 3739 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
7079 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1941 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
7079 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1941 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
7122 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1714 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
7122 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1714 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
7148 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1342 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
7148 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1342 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
7153 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 3739 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
7153 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 3739 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
7176 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1714 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
7176 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1714 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
7179 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 3957 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
7179 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 3957 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
7228 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1342 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
7228 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1342 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
7271 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1110 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
7271 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1110 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
7301 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1741 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
7301 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1714 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
7535 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1941 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
7535 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1941 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
8088 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 3129 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
8088 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 3129 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
8113 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1342 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
8113 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1342 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
8237 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1528 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
8237 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 1528 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
8288 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 2154 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
8288 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 2154 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
8326 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 2503 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
8326 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 2503 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
8515 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 2154 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
8515 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 2154 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
8517 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 3739 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
8517 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 3739 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
8565 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 2730 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
8565 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 2730 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
9311 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1714 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
9311 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1714 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
9311 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1714 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
9387 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 2730 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
9387 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 2730 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
9480 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 3580 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
9480 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 3580 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
9480 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 3580 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
9497 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1714 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
9497 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1714 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
9510 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 4551 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
9510 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 4551 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
9510 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 4551 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
9549 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1110 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
9549 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1110 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
9569 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1110 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
9569 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1110 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
10286 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1528 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
10286 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1528 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
10471 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 3129 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
10480 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 3129 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
10480 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 3129 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
11415 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1528 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
11415 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1528 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
11525 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 3739 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
11525 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 3739 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
11535 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1342 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
11535 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1342 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
10364/10369 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1528 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
10364/10369 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1528 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
6326 (CS) D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1342 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
6326 (CS) D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH LPS 1342 1,000,000 Btu/h to 5,000,000 Btu/h X X X X Twice per week during operation
4251 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 4551 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
4251 D3025 140 4950 BOILERS, STEAM, O/G/C FIRED OVER 1000MBH Burnham LPS 4551 Over 5,000,000 Btu/h X X X X Once per 24 hour period during operation
2204 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 100 Under 5,000,000 Btu/h X X Once per month when operationg
4109 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Laars LPS 4551 Under 5,000,000 Btu/h X X Once per month when operationg
5126 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 90 Under 5,000,000 Btu/h X X Once per month when operationg
6263 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 645 Under 5,000,000 Btu/h X X Once per month when operationg
6263 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 645 Under 5,000,000 Btu/h X X Once per month when operationg
7079 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 745 Under 5,000,000 Btu/h X X Once per month when operationg
7079 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 745 Under 5,000,000 Btu/h X X Once per month when operationg
7113 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 495 Under 5,000,000 Btu/h X X Once per month when operationg
7113 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 495 Under 5,000,000 Btu/h X X Once per month when operationg
7153 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 745 Under 5,000,000 Btu/h X X Once per month when operationg
7153 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 745 Under 5,000,000 Btu/h X X Once per month when operationg
7179 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 745 Under 5,000,000 Btu/h X X Once per month when operationg
7179 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 745 Under 5,000,000 Btu/h X X Once per month when operationg
7535 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 645 Under 5,000,000 Btu/h X X Once per month when operationg
8088 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 645 Under 5,000,000 Btu/h X X Once per month when operationg
8378 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 645 Under 5,000,000 Btu/h X X Once per month when operationg
8378 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 645 Under 5,000,000 Btu/h X X Once per month when operationg
8450 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 495 Under 5,000,000 Btu/h X X Once per month when operationg
8574 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 65 Under 5,000,000 Btu/h X X Once per month when operationg
9361 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 1796 Under 5,000,000 Btu/h X X Once per month when operationg
9361 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 1796 Under 5,000,000 Btu/h X X Once per month when operationg
9387 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 1796 Under 5,000,000 Btu/h X X Once per month when operationg
10471 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 495 Under 5,000,000 Btu/h X X Once per month when operationg
10471 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 495 Under 5,000,000 Btu/h X X Once per month when operationg
10480 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 495 Under 5,000,000 Btu/h X X Once per month when operationg
10480 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 495 Under 5,000,000 Btu/h X X Once per month when operationg
10571 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 1796 Under 5,000,000 Btu/h X X Once per month when operationg
11415 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED Lochinvar LPS 495 Under 5,000,000 Btu/h X X Once per month when operationg
11525 D2025 260 3950 WATER HEATER, STEAM COIL, TO 2500 GAL, ANNUALIZED LPS 1796 Under 5,000,000 Btu/h X X Once per month when operationg
6252 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
6252 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
6252 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
6252 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
6254 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
6254 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
6254 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
6254 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
6256 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
6256 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
6256 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
6256 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
6258 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
6264 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
6264 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
6264 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
6264 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
6266 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
6266 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
6266 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
6266 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 100 NA X NA
7265 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 750 NA X NA
11519 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 400 NA X NA
11519 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 400 NA X NA
11519 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 400 NA X NA
11523 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 400 NA X NA
11523 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 400 NA X NA
11523 D3055 110 3950 SPACE HEATER, UNIT HEATER, STEAM, ANNUALIZWD Gas 400 NA X NA
8481 D3055 122 2950 FORCED AIR HEATER, OIL/GAS OVER 120MBH, ANNUALIZED Reznor Furnace 400 NA X X X NA
6211 D3095 118 2950 AIR COMPRESSOR, RECIPROCATING,5 TO 40 HP, ANNUALIZED Ingersoll Rand NA NA NA X X X X NA
9480 D3095 210 1950 STEAM HUMIDIFICATION SYSTEMS NA NA NA X X X X NA
6211 G3015 650 1950 WATER SOFTENER, ANNUALIZED Sofner NA NA X X X NA
9480 G3015 650 1950 WATER SOFTENER, ANNUALIZED Sofner NA NA X X X NA