This document is a Construction Site Visit Minutes record for Solicitation No. FA4897138Q0006, dated 1/6/76, detailing key specifications and requirements for a construction project. The document provides critical installation guidelines for fire alarm systems, including panel placement restrictions (cannot be placed over expansion joints), and clarifies that permanent fixtures may be removed to accommodate panel installation, except for the electrical box.
The minutes also specify additional technical and procedural requirements, such as a 14-day completion window for patch and paint work on each floor, and flexibility in fire alarm strobe placement (wall or ceiling), with the mandate that old strobes/alarms must be patched and painted. The document includes two attendance tables listing participants from various companies and departments, suggesting this is a collaborative site visit involving multiple stakeholders in the construction process.
View the file
Other files
Show all 28
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
The fire alarm panel shall be in the designated location. Any permanent fixtures may be removed to allow the panel to be installed, except the electrical box. Cannot be placed over expansion joint.
The brand name is for standardization
The 14-day requirement has been clarified to “Patch and paint work must be completed for a floor to be considered complete, and must be completed within 14 days of all other work on that floor.”
Fire alarm strobes may be placed on wall or ceiling, and the old strobes/alarms must be patched/painted.