1)_SOW_Bldg_2316.pdf
PDF 44 KB Posted
- Attached to
- Repair Roof Bldg 2316 Federal contract opportunity
- Solicitation number
- FA489720B0001
About this file
This document includes a Statement of Work and related federal contract opportunity solicitation. The Statement of Work outlines requirements for a roof replacement project at Building 2316 on Mountain Home Air Force Base, including removal of the existing roof down to the deck and installation of a new 80 mil white PVC membrane roof with a minimum R-30 insulation and 20-year manufacturer's warranty. The 120-day period of performance is also specified. The related solicitation is a total small business set-aside for the roof replacement project, estimated between $250,000 to $500,000. The pre-bid site visit will take place on November 4th and bids are due by November 15th. The solicitation is issued by the Air Force Air Combat Command and funds are not presently available.
Statement of Work Bldg 2316
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Bldg 2316 - Lay down Area.pdf | ||
| Addendum 3 Bldg 2316.pdf | ||
| Solicitation Amendment FA489720B00010003 SF 30.pdf | ||
| Pre-Bid Site Inspection Questions and Answers Bldg 2316.docx | DOCX document | |
| Site Visit Sign-In Sheet Bldg 2316.pdf | ||
| Addendum 2 Bldg 2316.pdf | ||
| Solicitation Amendment FA489720B00010002 SF 30.pdf | ||
| Solicitation_Amendment_FA489720B00010001_SF_30.pdf | ||
| Solicitation_Amendment_-_FA489720B00010001.pdf | ||
| 6)_366_SFS_FORM_30.pdf | ||
| 2)_Final_Drawings_Bldg_2316.pdf | ||
| 3)_Final_Specifications_for_Bldg_2316_roof.pdf | ||
| 5)_Wage_Determination.pdf | ||
| Solicitation_-_FA489720B0001.pdf | ||
| 4)_Bldg_2316_Schedule_of_Submittals.pdf |
Show all 15
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
May 28, 2019
Project Title: Repair Roof, Dining Hall Fac 2316 Project No. 1068396 Project Manager: Reid Dudley Liquidated Damages: N/A Period of Performance: 120 Days
SCOPE OF WORK
Project shall include all necessary demolition, construction, and modifications necessary to replace the existing roofing structure of Building 2316, Section B with a new R-30 fully adhered, reinforced, white, 80 mil Polyvinyl Chloride (PVC) roofing system that will provide adequate drainage. This project will not include any modifications to Section A metal roof.
1. Contractor shall remove and dispose of the following items: existing roofing materials down to the roof deck including roofing accessories, insulation, abandoned HVAC curbs, flashing, trim, roof drains and covers. All non-hazardous materials removed during demolition shall become property of the contractor and shall be removed from MHAFB and transported to off-base landfills.
2. Provide and install new 80 mil white, reinforced, fully adhered PVC membrane roofing sloped at minimum ¼”/12” slope to new roof drains over 1/2" high density protection board over R-30 minimum polyiso insulation board over approved vapor barrier over existing roof deck. Provide crickets on high side of HVAC units and where needed to accommodate drainage. No roofing materials or accessories removed during demolition shall be reinstalled. All roofing materials and accessories brought on the project site to replace existing materials and accessories shall be new. Existing HVAC rooftop units, exhaust fans, extractor vents and equipment associated with ongoing building operations shall be supported and remain operational during demolition and construction. If it becomes necessary to shut down an electrical or mechanical system or to cordon off a portion of the building to accommodate construction, the Contracting Officer and Facility Manager shall be notified at least two weeks in advance and the contractor shall follow instructions given. This facility shall remain operational at all times including existing HVAC units unless approved in advance by the Contracting Officer. Drain lines and pipe insulation for new roof drains, overflow roof drains, and vent ductwork located below the roof deck shall be extended as required. The roofing system shall meet the following Structural Design Criteria:
a: Risk Category: II b: Wind: 115 mph Exposure C c: Impact Resistance: 1” diameter hail stones
3. Contractors shall make a pre-bid site visit to verify all dimensions, conditions, and placement of all rooftop units, utility lines and conduits prior to submitting a bid.
Construction drawings with details and photos provided by the Government depict general construction criteria and parameters only.
4. All construction shall be in compliance with the requirements of UFC 1-200-01 (DOD Building Code), UFC 3- 110-03 Roofing, and with the attached project drawings and specifications.
5. All materials shall be installed in accordance with roofing manufacturer’s recommendations and installation instructions and shall conform to all requirements necessary to meet contract warranty requirements.
6. Environmental: All work shall be performed in accordance with Mountain Home AFB Environmental requirements as written in Specifications Section 01 57 19, and with all applicable Local, State, and Federal environmental requirements. The contractor may assume there is no asbestos in existing roofing materials.
7. During construction, the building will remain occupied. There shall be no contractor access inside Building 2316 without prior approval from the Contracting Officer.
Contractor shall provide protection for building occupants entering and exiting building when necessary. Contractor shall also protect and ensure storm water does not enter facility and shall be responsible for any damages caused by construction or failure to protect against storm water intrusion.
8. Warranty – Provide a manufacturer's 20-year “No Dollar Limit” Watertight warranty for the new roof and a Roofing System Installer Warranty in accordance with UFC 3-110-03 and with specification Section 07 54 19, part 1.10 – 1.10.3 Warranty. The watertight roof system warranty shall include all roof penetrations, flashing, and all joints between the sections of roof being replaced. Roof must be installed by a manufacturer’s certified installer and installed according to manufacturer’s requirements. Manufacturer’s warranty shall not exclude conditions indicated in the Structural Design Criteria.
Signatures are required on the Watertight warranty and must be from the roof system manufacturer and not from the General Contractor. The warranty shall not be pro-rated.
Roofing System Installer Warranty - The roof system installer must warrant for a minimum period of two years that the roof system, as installed, is free from defects in installation workmanship, to include the roof membrane, flashing, insulation, accessories, attachments, and sheet metal installation integral to a complete watertight roof system assembly. Write the warranty directly to the Government. The roof system installer is responsible for correction of defective workmanship and replacement of damaged or affected materials. The roof system installer is responsible for all costs associated with the repair or replacement work. When a roof leak occurs and the manufacturer is notified per warranty requirements and the manufacturer or his approved applicator fails to perform the repairs within 72 hours of notification, emergency temporary repairs performed by others shall not void the warranty.
9. Period of Performance (PoP) shall be 120 days from Notice to Proceed (NTP).