SCHEDULE OF MATERIAL SUBMITTALS

PROJECT NUMBER

QYZH 02-0001A/B

PROJECT TITLE

Demo LG HQ’s, B2408 and Construct New Chapel Annex

SOLICITATION/CONTRACT NUMBER

TO BE COMPLETED BY PROJECT ENGINEER
TO BE COMPLETED BY CONTRACT ADMINISTRATOR
LINE NUMBER
ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL
NUMBER OF COPIES REQUIRED
REQUIRED SUBMISSION DATE
DATE RECEIVED IN CONTRACTING
DATE TO CIVIL ENGINEERING
RETURN SUSPENSE DATE
SUBMITTAL NUMBERS
DATE

CONTRACTOR

NOTIFIED

CONTRACTOR SUBMITTAL
FINAL APPROVAL
REMARKS
PRECONSTRUCTION
SHOP DRAWINGS
PRODUCT DATA
SAMPLES
DESIGN DATA
TEST REPORTS
CERTIFICATES
MANUFACTURER’S INSTRUCTIONS
MANUFACTURER’S FIELD REPORTS
OPERATION AND MAINTENANCE DATA
CLOSEOUT
APPROVED
DIS-APPROVED
1
35% Design, Drawings and Specs
4
4
1
4

Submission is # of days after Notice To Proceed

2
95% Design, Drawings and Specs
4
4
1
4
4
4
4

Submission is # of days after Notice To Proceed

3
All material and equipment materials for building purposes to include manufacturer literature, options and specifications.
3
3
3

Submission is # of days after Notice To Proceed

4
100% Design, Drawings, Specs and CD-ROM Copies
4
4
1
4
4
4
4

Submission is # of days after Notice To Proceed

Schedule of Material Submittals Template, Feb 05 (SAF/AQCP)

FA4897-12-B-0002

Attachment 4