CDRL_list_(Draft_-_24_Oct_14).xlsx
XLSX spreadsheet 11 KB Posted
- Attached to
- War Reserve Materiels (WRM) Federal contract opportunity
- Solicitation number
- FA4890-15-R-0004
About this file
CDRL List (Draft - 24 Oct 14)
View the file
Other files for this federal contract opportunity
Show all 50
War Reserve Materiels (WRM) has more files on GovTribe.
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CDRLs
| Award No. FA4890-15-R-0004 | |||||
| CDRL | DID | Title | Deliverable Date | PWS Reference | |
| A001 | Maintenance Control Plan | 45 DAC & Annually 15 Aug | Para. 2.4.1., 2.9.1., 3.1.5.1., 3.1.6.3., 3.1.8.4.1. & 3.5.1. | MCP called out in mupltiple sections do we have one for each functional area? This should also address life cycle management of GFE/GFP | |
| A002 | Halon Report | Monthly by 10th 15 Jan and 15 Jul | Para. 2.9.20. | ||
| A003 | Incident Reports | As Required | Para. 3.1.5.10.1. | DELETED | |
| A004 | Monthly Work Schedule Report | 10 DAC & 5 business days prior to beginning of month in which work is to be done | Para 3.5.1.2.4. | ||
| A005 | Monthly Work Status Report | 40 DAC & 10 business days after end of reporting period | Para 3.5.1.2.4.1., 3.6.1.1., 3.2.4., | make sure functional areas that have a status report have their inputs here | |
| A006 | Management Plan | 30DAC & Annually | para 2.2.1 | Still needs to be drafted | |
| A007 | Vegetation Control/Grounds Maintenance | 90 DAC & 10 business days after a revision | Para 3.5.1.8. | ||
| A008 | Environmental Protection Plan (EEP) | 90 DAC & 10 business days after a revision | Para 3.5.1.8., 3.6.1. | ||
| A009 | Emergency Response Plan | 90 DAC & 10 business days after a revision | Para 3.5.1.10. | ||
| A010 | Facility Survey/Test and Inspection Report | Annually 15 Jul | Para 3.5.1.3. | ||
| A011 | Project Completion Report | As Required (30 days after 332 completion) | Para 3.5.2.2.4.4. | ||
| A012 | As-Built Drawings | 45 days of occurrence | Para 3.5.2.2.4.3., 3.5.2.2.4.5. | ||
| A013 | DELETED | ||||
| A014 | Spill Report | COB next business day | para 3.6.1.2. | ||
| A015 | Safety and Health Plan | 90 DAC & 10 business days after a revision | Para 3.5.1.10. | ||
| A016 | Saftey Mishap Notification | COB next day | para 3.6.2.2. & 3.6.2.3. | ||
| A017 | Key Personnel / Supplemental Manpower Report | 45 DAC & Monthly | para 2.2.1.1, 2.2.10.1 | Still needs to be drafted | |
| A018 | WRM assets in place | Quarterly | para 2.2.10.3 | Still needs to be drafted | |
| A020 | WRM Metrics | Monthly | para 2.3.3 | Still needs to be drafted | |
| A021 | BEAR Reporting | Monthly by the 15th day | para 3.3.1 | Still needs to be drafted | |
| A022 |