Attachment 3 - Statement of Work Remove Asbestos 415 24 Aug 2020.pdf
PDF 250 KB Posted
- Attached to
- Asbestos Removal BLDGS 1373, 338 and 415
- Solicitation number
- FA488720Q0043
View the file
Other files
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Building 415 Asbestos Flooring Abatement
Luke Air Force Base, Arizona 24 August 2020
1 OVERVIEW
1.1 The purpose of this project is to remove asbestos containing material (ACM) in the flooring and removal of bathroom partitions in areas highlighted on attached map of Building 415. No asbestos abatement will be required under the walls.
1.2 No updated asbestos survey will be provided, nor is one requested under this statement of work (SOW). The Government has confidence in the 2001 Asbestos Survey Report.
2 DESCRIPTION OF WORK
2.1 This project includes all necessary demolition, construction and testing to perform work as listed in description of work below.
2.2 Performance Period: This work should be completed within 15 calendar days after the Notice to Proceed is issued.
2.3 Hazardous Material Abatement: Asbestos is present. An Asbestos Report is available for review.
Although testing was accomplished, the Contractor shall report any additional suspicious material immediately to the Contracting Officer.
2.4 Design Drawings: None required.
2.5 Calculations: None required.
2.6 Survey: None required.
2.7 Asbestos Abatement:
2.7.1 Contractor shall demolish and remove approximately 1,875 square feet of existing flooring and asbestos containing floor mastic from areas highlighted in map. Contractor shall also remove and dispose of bathroom partitions. All asbestos containing materials shall be disposed at EPA approved landfill.
2.7.2 Erect up to three containments/negative pressure enclosures and or regulated areas around affected sections.
2.7.3 Place plastic sheeting protect surrounding walls during abatement procedures.
2.7.4 Conduct air sampling test after abatement.
2.7.5 Compliance with all required NESHAP, EPA and OSHA Regulations. Contractor is responsible for 3rd party clearance and over site.
2.7.6 Provide waste manifest to 56 CES.
3 GOVERNMENT FURNISHED INFORMATION, PROPERTY, OR SERVICES
3.1 Upon the Contractor’s request, the Government will provide electronic and/or hard copies of available documents and correspondences pertinent to the work.
3.2 Adequate power to support contractor tools shall be provided by the government in the form of commercial power from the facility or government supplied generator in the event facility power is inadequate.
3.3 All furnishings and non-permanent fixtures shall be removed by government personnel prior to contractor’s commencement of work.
4 GENERAL INFORMATION
4.1 The Contractor shall furnish all materials, equipment, and personnel necessary to design, manage, and accomplish the project. The Contractor shall thoroughly review the request for proposals for constructability and advise the Contracting Officer of potential problem areas prior to submitting a cost proposal. No alterations, additions or deletions shall be made unless prior written approval is given by the Contracting Officer. Under no circumstances is the Contractor to begin any work on the project until a Notice to Proceed is issued by the Contracting Officer.
4.2 Site Visit
4.2.1 The Contractor shall inspect the site where services are to be performed. This site review shall satisfy the Contractor’s need to identify all general and local conditions that may affect the cost of the contract.
4.2.2 Failure to inspect the site will not constitute grounds for claims after contract award.
4.3 Required Submittals
4.3.1 When required per Schedule of Submittals, Contractor shall submit on an AF Form 3000 all product, material, shop drawing and designs to include Material Safety Data Sheets (MSDS) to the Contracting Officer for approval before any and all items are brought to or installed on project sites at Luke AFB.
4.3.2 Contractor shall submit on Luke AFB Form 317 Contractor’s Reporting Environmental
Entry Form all products used on this project. These items will be tracked monthly and reports will be turned into Mr. Oscar Mabry or Ms. Teri Wesley at the Hazmat office phone number (623) 856- 4748 or 4749.
4.3.3 Demolition List: the Government reserves the right to salvage any/all equipment or materials prior to construction start. The Contractor shall submit a list of equipment to be demolished for Government review. A list of all items with delivery instructions will be provided in return to identify items for Government salvage. All other items will be the Contractor’s responsibility to dispose.
4.3.4 The government reserves the right to request submittals on any product or service for duration of the contract.
5 END STATEMENT OF WORK
| 1 OVERVIEW |
| 1.1 The purpose of this project is to remove asbestos containing material (ACM) in the flooring and removal of bathroom partitions in areas highlighted on attached map of Building 415. No asbestos abatement will be required under the walls. |
| 1.2 No updated asbestos survey will be provided, nor is one requested under this statement of work (SOW). The Government has confidence in the 2001 Asbestos Survey Report. |
| 2 DESCRIPTION OF WORK |
| 2.1 This project includes all necessary demolition, construction and testing to perform work as listed in description of work below. |
| 2.2 Performance Period: This work should be completed within 15 calendar days after the Notice to Proceed is issued. |
| 2.3 Hazardous Material Abatement: Asbestos is present. An Asbestos Report is available for review. Although testing was accomplished, the Contractor shall report any additional suspicious material immediately to the Contracting Officer. |
| 2.4 Design Drawings: None required. |
| 2.5 Calculations: None required. |
| 2.6 Survey: None required. |
| 2.7 Asbestos Abatement: |
| 2.7.1 Contractor shall demolish and remove approximately 1,875 square feet of existing flooring and asbestos containing floor mastic from areas highlighted in map. Contractor shall also remove and dispose of bathroom partitions. All asbestos containin... |
| 2.7.2 Erect up to three containments/negative pressure enclosures and or regulated areas around affected sections. |
| 2.7.3 Place plastic sheeting protect surrounding walls during abatement procedures. |
| 2.7.4 Conduct air sampling test after abatement. |
| 2.7.5 Compliance with all required NESHAP, EPA and OSHA Regulations. Contractor is responsible for 3rd party clearance and over site. |
| 2.7.6 Provide waste manifest to 56 CES. |
| 3 GOVERNMENT FURNISHED INFORMATION, PROPERTY, OR SERVICES |
| 3.1 Upon the Contractor’s request, the Government will provide electronic and/or hard copies of available documents and correspondences pertinent to the work. |
| 3.2 Adequate power to support contractor tools shall be provided by the government in the form of commercial power from the facility or government supplied generator in the event facility power is inadequate. |
| 3.3 All furnishings and non-permanent fixtures shall be removed by government personnel prior to contractor’s commencement of work. |
| 4 GENERAL INFORMATION |
| 4.1 The Contractor shall furnish all materials, equipment, and personnel necessary to design, manage, and accomplish the project. The Contractor shall thoroughly review the request for proposals for constructability and advise the Contracting Officer ... |
| 4.2 Site Visit |
| 4.2.1 The Contractor shall inspect the site where services are to be performed. This site review shall satisfy the Contractor’s need to identify all general and local conditions that may affect the cost of the contract. |
| 4.2.2 Failure to inspect the site will not constitute grounds for claims after contract award. |
| 4.3 Required Submittals |
| 4.3.1 When required per Schedule of Submittals, Contractor shall submit on an AF Form 3000 all product, material, shop drawing and designs to include Material Safety Data Sheets (MSDS) to the Contracting Officer for approval before any and all items a... |
| 4.3.2 Contractor shall submit on Luke AFB Form 317 Contractor’s Reporting Environmental Entry Form all products used on this project. These items will be tracked monthly and reports will be turned into Mr. Oscar Mabry or Ms. Teri Wesley at the Hazmat... |
| 4.3.3 Demolition List: the Government reserves the right to salvage any/all equipment or materials prior to construction start. The Contractor shall submit a list of equipment to be demolished for Government review. A list of all items with deliver... |
| 4.3.4 The government reserves the right to request submittals on any product or service for duration of the contract. |
5 END STATEMENT OF WORK
File details come from the government source that posted it. Updated .