STATEMENT OF WORK
Building 338, Remove old carpet/tile/Asbestos abatement
Luke Air Force Base, Arizona
21 July 2020
1. OVERVIEW
The purpose of this project is to remove approximately 1,300 sq ft of Asbestos based tile flooring, carpet and glue then grind/polish concrete floor surface. This work will be performed during normal business hours at a date TBD upon award of contract. The contractor will remove all existing tile/carpet, abate asbestos in the area and grind/polish concrete surface to a smooth, polished finish.
2. DESCRIPTION OF WORK
2.1. This project includes all necessary demolition, construction and testing to perform work as listed in description of work below.
2.2. Performance Period: all work shall be completed at a date to be determined after the Notice to
Proceed is issued.
2.3. General Construction
2.3.1. The contractor shall safely remove old carpet/tile/baseboards. Removal of carpet/tile/baseboard shall be done by qualified abatement contractor in proper containment.
2.3.2. The contractor will remove carpet, tile and glue, repair cracks and divots as necessary, grind and polish the bare concrete floor to a “salt and pepper” finish.
2.3.3. All asbestos found shall be properly abated.
2.4. Abatement shall be performed utilizing Environmental Protection Agency’s National Emissions
Standards for Hazardous Air Pollutants (NESHAP) and pass the AHERA TEM clearance test upon abatement completion.
2.5. Conduct air sampling test after abatement.
3. GOVERNMENT FURNISHED INFORMATION, PROPERTY, OR SERVICES
3.1. Upon the Contractor’s request, the Government will provide electronic and/or hard copies of available documents and correspondences pertinent to the work.
3.2. Adequate power to support contractor tools shall be provided by the government in the form of commercial power from the facility or government supplied generator in the event facility power is inadequate.
3.3. All furnishings and non-permanent fixtures shall be removed by government personnel prior to contractor’s commencement of work.
4. GENERAL INFORMATION
4.1. GENERAL
The contractor shall furnish all materials, equipment, and personnel necessary to design, manage, and accomplish the project. The Contractor shall thoroughly review the request for proposals for constructability and advise the contracting officer of potential problem areas prior to submitting a cost proposal. No alterations, additions or deletions shall be made unless prior written approval is given by the contracting officer. Under no circumstances is the Contractor to begin any work on the project until a
Notice to Proceed is issued by the Contracting Officer.
4.2. SITE VISIT
The Contractor shall inspect the site where services are to be performed. This site review shall satisfy the
Contractor’s need to identify all general and local conditions that may affect the cost of the contract.
Failure to inspect the site will not constitute grounds for claims after contract award.
4.3. REQUIRED SUBMITTALS
4.3.1. Provide Operation and Maintenance manual in accordance with Luke Master Specification, Section
017000.
4.3.2. The government reserves the right to request submittals on any product or service for duration of the contract.
END STATEMENT OF WORK