STATEMENT OF WORK
B1373 Asbestos Abatement
Luke Air Force Base, Arizona 24 August 2020
1 OVERVIEW
1.1 The purpose of this project is to the removal and abatement of asbestos containing materials
(ACM) in the flooring, drywall, lower and upper grid ceiling and tiles in building 1373 at Luke
AFB, AZ.
1.2 The Government proposes two options for asbestos remediation as indicated below. Quotes must provide separate pricing for each option effort as the Government will need to ascertain which work can be accomplished within the budget allotted for this project.
1.3 No updated asbestos survey will be provided, nor is one requested under this statement of work
(SOW). The Government has confidence in the 1999 Asbestos Survey Report.
2 DESCRIPTION OF WORK
2.1 This project includes all necessary demolition, construction and testing to perform work as listed in description of work below.
2.2 Performance Period: For both options, the work should be completed within 15 calendar days after the Notice to Proceed is issued.
2.3 Hazardous Material Abatement: Asbestos is present. An Asbestos Report is available for review.
Although testing was accomplished, the Contractor shall report any additional suspicious material immediately to the Contracting Officer.
2.4 Design Drawings: None required.
2.5 Calculations: None required.
2.6 Survey: None required.
2.7 Asbestos Abatement:
2.7.1 Option 1: The work under Option 1 will include the following:
2.7.1.1 Removal of ceramic floor tile, vinyl floor tile and adhesive mastic approximately 1,800 Square Feet (SF).
2.7.1.2 Removal of drywall, up from floor 2’ for 932 SF.
2.7.1.3 Option 1 will require installation of poly ceiling and criticals at 466 linear feet (LF) of wall to pass clearances.
2.7.2 Option 2: The work under Option 2 will include the following:
2.7.2.1 Removal of ceramic floor tile, vinyl floor tile and adhesive mastic approximately 1,800 SF.
2.7.2.2 Removal of drywall, full height, for approximately 5,592 SF.
2.7.2.3 Removal of lower grid ceiling and tiles for approximately 1,800 SF
2.7.2.4 Removal of upper grid and ceiling tiles for approximately at 1,800 SF.
2.7.2.5 Option 2 will not require poly ceiling, but will require the building to be be non-ACM and clean/free of microbial contamination.
2.8 All asbestos containing materials shall be disposed at EPA approved landfill. Contractor will dispose of all contents. This includes removal of the mercury containing lightbulbs and thermostats, and PCB containing light ballasts.
2.9 Erect one containment/negative pressure enclosures and or regulated areas around affected sections.
2.10 Place plastic sheeting protect surrounding walls during abatement procedures. Contractor will not be required to abate flooring under walls.
2.11 Conduct air sampling test after abatement.
2.12 Compliance with all required NESHAP, EPA and OSHA Regulations. Contractor will be responsible for 3rd party clearance.
2.13 Provide waste manifest to 56 CES.
3 GOVERNMENT FURNISHED INFORMATION, PROPERTY, OR SERVICES
3.1 Upon the Contractor’s request, the Government will provide electronic and/or hard copies of available documents and correspondences pertinent to the work.
3.2 Adequate power to support contractor tools shall be provided by the government in the form of commercial power from the facility or government supplied generator in the event facility power is inadequate.
3.3 All furnishings and non-permanent fixtures shall be removed by government personnel prior to contractor’s commencement of work.
4 GENERAL INFORMATION
4.1 The Contractor shall furnish all materials, equipment, and personnel necessary to design, manage, and accomplish the project. The Contractor shall thoroughly review the request for proposals for constructability and advise the Contracting Officer of potential problem areas prior to submitting a cost proposal. No alterations, additions or deletions shall be made unless prior written approval is given by the Contracting Officer. Under no circumstances is the Contractor to begin any work on the project until a Notice to Proceed is issued by the Contracting Officer.
4.2 Site Visit
4.2.1 The Contractor shall inspect the site where services are to be performed. This site review shall satisfy the Contractor’s need to identify all general and local conditions that may affect the cost of the contract.
4.2.2 Failure to inspect the site will not constitute grounds for claims after contract award.
4.3 Required Submittals
4.3.1 When required per Schedule of Submittals, Contractor shall submit on an AF Form 3000 all product, material, shop drawing and designs to include Material Safety Data Sheets (MSDS) to the Contracting Officer for approval before any and all items are brought to or installed on project sites at Luke AFB.
4.3.2 Contractor shall submit on Luke AFB Form 317 Contractor’s Reporting Environmental
Entry Form all products used on this project. These items will be tracked monthly and reports will be turned into Mr. Oscar Mabry or Ms. Teri Wesley at the Hazmat office phone number (623) 856- 4748 or 4749.
4.3.3 Demolition List: the Government reserves the right to salvage any/all equipment or materials prior to construction start. The Contractor shall submit a list of equipment to be demolished for Government review. A list of all items with delivery instructions will be provided in return to identify items for Government salvage. All other items will be the Contractor’s responsibility to dispose.
4.3.4 The government reserves the right to request submittals on any product or service for duration of the contract.
5 END STATEMENT OF WORK
| 2.7.2 Option 2: The work under Option 2 will include the following: |
| 2.7.2.1 Removal of ceramic floor tile, vinyl floor tile and adhesive mastic approximately 1,800 SF. |
| 2.7.2.2 Removal of drywall, full height, for approximately 5,592 SF. |
| 2.7.2.3 Removal of lower grid ceiling and tiles for approximately 1,800 SF |
| 2.7.2.4 Removal of upper grid and ceiling tiles for approximately at 1,800 SF. |
| 2.7.2.5 Option 2 will not require poly ceiling, but will require the building to be be non-ACM and clean/free of microbial contamination. |
| 2.8 All asbestos containing materials shall be disposed at EPA approved landfill. Contractor will dispose of all contents. This includes removal of the mercury containing lightbulbs and thermostats, and PCB containing light ballasts. |
| 2.9 Erect one containment/negative pressure enclosures and or regulated areas around affected sections. |
| 2.10 Place plastic sheeting protect surrounding walls during abatement procedures. Contractor will not be required to abate flooring under walls. |
| 2.11 Conduct air sampling test after abatement. |
| 2.12 Compliance with all required NESHAP, EPA and OSHA Regulations. Contractor will be responsible for 3rd party clearance. |
| 2.13 Provide waste manifest to 56 CES. |
| 3 GOVERNMENT FURNISHED INFORMATION, PROPERTY, OR SERVICES |
| 3.1 Upon the Contractor’s request, the Government will provide electronic and/or hard copies of available documents and correspondences pertinent to the work. |
| 3.2 Adequate power to support contractor tools shall be provided by the government in the form of commercial power from the facility or government supplied generator in the event facility power is inadequate. |
| 3.3 All furnishings and non-permanent fixtures shall be removed by government personnel prior to contractor’s commencement of work. |
| 4 GENERAL INFORMATION |
| 4.1 The Contractor shall furnish all materials, equipment, and personnel necessary to design, manage, and accomplish the project. The Contractor shall thoroughly review the request for proposals for constructability and advise the Contracting Officer ... |
| 4.2 Site Visit |
| 4.2.1 The Contractor shall inspect the site where services are to be performed. This site review shall satisfy the Contractor’s need to identify all general and local conditions that may affect the cost of the contract. |
| 4.2.2 Failure to inspect the site will not constitute grounds for claims after contract award. |
| 4.3 Required Submittals |
| 4.3.1 When required per Schedule of Submittals, Contractor shall submit on an AF Form 3000 all product, material, shop drawing and designs to include Material Safety Data Sheets (MSDS) to the Contracting Officer for approval before any and all items a... |
| 4.3.2 Contractor shall submit on Luke AFB Form 317 Contractor’s Reporting Environmental Entry Form all products used on this project. These items will be tracked monthly and reports will be turned into Mr. Oscar Mabry or Ms. Teri Wesley at the Hazmat... |
| 4.3.3 Demolition List: the Government reserves the right to salvage any/all equipment or materials prior to construction start. The Contractor shall submit a list of equipment to be demolished for Government review. A list of all items with deliver... |
| 4.3.4 The government reserves the right to request submittals on any product or service for duration of the contract. |
5 END STATEMENT OF WORK