Amendment 001.doc
DOC document 53 KB Posted
- Attached to
- Interior/Exterior Finishes IDIQ
- Solicitation number
- FA4887-11-R-0007
About this file
Amendment 001
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 0004.pdf | ||
| Amendment 0002.doc | DOC document | |
| Attch 1 Base Specs.docx | DOCX document | |
| Attch 12 Misc. Q A.docx | DOCX document | |
| Amendment 0002.doc | DOC document | |
| Attch 10 Pre-Bid Sign-In.PDF | ||
| Attch 11 Pre-Bid Q A.docx | DOCX document | |
| Attch 9 Bldg 545 Tile-Carpet.pdf | ||
| Attch 8 Bldg 545 Floorplan.pdf | ||
| Attch 2 AFI32-1065.pdf | ||
| Attch 3 AFOSHSTD91-66.pdf | ||
| Attch 4 AFOSHSTD91-501.pdf | ||
| Attch 6 PP Information.rtf | RTF text file | |
| Attch 5 MIL-HDBK-419Apdf.pdf | ||
| Attch 7 PP Questionairre.docx | DOCX document | |
| FA4887-11-R-0007 Finishes IDIQ.docx | DOCX document | |
| Attch 6 PP Information.rtf | RTF text file | |
| Attch 4 AFOSHSTD91-501.pdf | ||
| Attch 3 AFOSHSTD91-66.pdf | ||
| Attch 1 Base Specs.docx | DOCX document | |
| Attch 5 MIL-HDBK-419Apdf.pdf | ||
| Attch 2 AFI32-1065.pdf | ||
| Attch 7 PP Questionairre.docx | DOCX document | |
| FA4887-11-R-0007 Finishes IDIQ.docx | DOCX document |
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The Issued By organization has changed from
56TH CONTRACTING SQ- (FA4887)
WILLIAM.SILVERS@LUKE.AF.MIL
623-856-7179 X232
14100 W. EAGLE ST.
LUKE AFB AZ 85309
to
56TH CONTRACTING SQ- (FA4887)
WILLIAM.SILVERS@LUKE.AF.MIL
623-856-7179 X254
14100 W. EAGLE ST.
LUKE AFB AZ 85309
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
SAMPLE PROJECT SOW
STATEMENT OF WORK
PROJECT NUEX 11-9999; Renovate dining area, Bldg 545.
1. Please provide a cost proposal for accomplishing the following work .
a. Title: Renovate Bldg 545
b. Work Request Number: 112210
c. Location: Bldg. 545
d. Scope of work: See Statement of Work.
e. Drawings and technical descriptions required: no
f. Material submittals required: Yes
g. Shop drawings required: Yes
2. Performance period: 24 Days
3. Attachments:
a. Work Request: Yes
b. Sketches and/or drawings: Yes
c. Statement of Work: Yes
The contractor shall remove and replace flooring materials, cove base and paint in Building 545. Flooring materials will not be removed and replaced throughout the entire building; therefore, floor plans specifying work areas are attached.
1. The work area is clear of asbestos containing materials – abatement is not required.
2. The contractor shall remove carpet (550 Sq Yds ), rubber cove base (600 Lineal Ft ), and ceramic tile ( 1500 Sq Ft ).
3. The contractor shall install carpet squares (550 Sq Yds ), ceramic tile (1500 Sq Ft ), and rubber cove base (600 Lineal Ft).
4. Transition strips will be installed at all dissimilar flooring material (56 ft).
5. Medium sanding on all walls only. (2200 Sq ft)
6. Retexturing walls medium only. (2200 Sq ft)
7. Paint 1 coat primer and 2 finish coats ( 4200 Sq ft ceiling 2200 Sq ft walls )
Attached floor plan specifies the areas in which, and the type of, flooring materials to be installed. The contractor will be responsible for removing and replacing all furnishing. The contractor will be responsible for all parts, labor, tools, materials, facilities, and transportation necessary to correctly complete this job.
The contractor will be responsible for moving and storing all furniture ( tables, chairs, etc.) The user will be responsible for moving all electronic equipment (computers, copiers, fax machines, etc.). Half the building shall be occupied during the entire performance period. All surrounding areas are required to be kept clean and free of debris on a daily basis and protected from any and all damages. The contractor is responsible for repairing any damage to the floor and walls caused by any mishap during the installation of interior finishes.
Materials Selected for Project (submittals required):
- Carpet
-- Manufacturer: Shaw or comparable
-- Style/Color: 01400 Range ( White Noise J0101 Book )
- Cove Base
-- Manufacturer: Roppe or comparable, rubber 4”
-- Style/Color: Fawn 4”
- Grout
-- Manufacturer: C-Cure or comparable
-- Style/Color: Grey
- Ceramic Tile
-- Manufacturer: Armstrong or comparable
-- Style/Color: Grey
- Paint
-- Manufacturer: Sherman Williams or comparable
-- Style/Color: Navajo White
SECTION J - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
Table of Contents has been deleted
The following have been added by full text:
ATTACHMENTS
Exhibit/Attachment Table of Contents
| DOCUMENT TYPE |
| DESCRIPTION |
| PAGES |
| DATE |
| Attachment 1 |
| Luke AFB Base Specs |
| 323 |
| Attachment 2 |
| AFI 32-1065 |
| 36 |
| 1 Oct 98 |
| Attachment 3 |
| AFOSHSTD 91-66 |
| 19 |
| 1 Oct 97 |
| Attachment 4 |
| AFOSHSTD 91-501 |
| 381 |
| 7 Jul 04 |
Attachment 5
Attachment 6
Attachment 7
Attachment 8
Attachment 9
MIL-HDBK-419A
PP Information
PP Questionaire
Bldg 545 Floorplan
Bldg 545 Tile-Carpet
29 Dec 87
The following have been deleted: