Attachment 9 - Priority Recommendations.pdf
PDF 110 KB Posted
- Attached to
- Install Backflow Preventers Federal contract opportunity
- Solicitation number
- FA487720R0032
About this file
This memorandum report summarizes the results of a cross-connection control survey conducted at Davis-Monthan Air Force Base. It identifies numerous facilities requiring installation of backflow prevention devices to isolate hazards. The related federal contract opportunity is for installing approved lead free reduced pressure backflow preventers and upstream wye strainers at various base facilities, as outlined in the Statement of Work dated December 9, 2019. The solicitation was issued by the Department of the Air Force Air Combat Command. The report provides detailed information on each required backflow preventer, including the facility, cross-connection details, recommended device type and sizing, and installation requirements. This includes a variety of applications such as domestic water systems, fire suppression systems, irrigation systems, medical equipment, and industrial/commercial processes.
View the file
Other files for this federal contract opportunity
Show all 34
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Final Cross-Connection Control Survey Memorandum Report, DMAFB May 2019 Page D-4 Table D-1. Priority Recommendations and Cost Estimates, Davis-Monthan AFB
URS Group, Inc.
Facility Num. Facility Name CC Owner CC ID CC Location Hazard / Cross- Connection
Degree of Hazard
Pipe Size (in)
Isolation or Containment BP Type BP Size
(in.)
Height
(ft) Priority
Category System Type Deficiency Recommendation
74 General James H Doolittle Center CES Utilities 74-A 1st Floor, Mechanical
Room Building Supply Low 3 Containment LFRP_REQ 3 10 1 Containment
Unprotected building supply line. The facility is considered low hazard due to facility activities; however, high hazard cross connections are present within the building elevating the overall hazard of the building.
Install an approved LFRP with an upstream wye strainer at an accessible height (1-5 ft) for testing and maintenance. Install drain line to floor drain.
130 Maintenance Operations Facility CES Utilities 130-A
1st Floor, Mechanical Room, S Side of Building
Building Supply Low 3 Containment LFRP_REQ 3 1 1 Containment
Unprotected building supply line. The facility is considered low hazard due to facility activities; however, high hazard cross connections are present within the building elevating the overall hazard of the building.
Install an approved LFRP with an upstream wye strainer.
251 SP Kennel CES Utilities 251-A Inside Walkway Ceiling Building Supply High 2 Containment LFRP_REQ 2 8 1 Containment Unprotected building supply line fed from
Building 250 located inside walkway ceiling.
Install an approved LFRP with an upstream wye strainer outside with approved freeze protection.
Install unit at an accessible height (1-5 ft) for testing and maintenance.
400 Hospital FSI 400-A 1st floor, Mechanical Room, Room 105 Building Supply High 4 Containment LFRP_REQ 4 6 1 Containment Unprotected building supply bypass to 400-
2.
Install an approved LFRP with an upstream wye strainer at an accessible height (1-5 ft) for testing and maintenance.
401 355th Medical Group Mechanical Plant FSI 401-A Basement, Next to
Tunnel to Building 400 Building Supply High 4 Containment LFRP_REQ 4 7 1 Containment Unprotected building supply line.
Install an approved LFRP with an upstream wye strainer at an accessible height (1-5 ft) for testing and maintenance.
1540 355th Communications Squadron CES Utilities 1540-A
1st Floor, Mechanical Room, E Side of Building
Building Supply Low 6 Containment LFRP_REQ 6 1 1 Containment
Unprotected building supply line. The facility is considered low hazard due to facility activities; however, high hazard cross connections are present within the building elevating the overall hazard of the building.
Install an approved LFRP with an upstream wye strainer.
2446 Shoppette and Auto Center CES Utilities 2446-A
1st floor, Electrical Room, S Side of Building
Building Supply High 2 Containment LFRP_REQ 2 0 1 Containment Unprotected building supply line. Install an approved LFRP with an upstream wye strainer.
2612 Dorothy H Finley Child Development Center CES Utilities 2612-A
1st Floor, Mechanical Room, E Side of Building
Building Supply High 3 Containment LFRP_REQ 3 0 1 Containment Unprotected building supply line. Install an approved LFRP with an upstream wye strainer.
355th FSS / Mission Support Group Headquarters
CES Utilities 3200-A Could Not Locate Building Supply Low 2 Containment LFRP_REQ 2 Unknown 1 Containment
Could not locate building water supply line.
Recommendation assumes there is no BFPA on the supply line and provides an estimate of the line size. The facility is considered low hazard due to facility activities;
however, high hazard cross-connections are present within the building elevating the overall hazard of the building.
Install an approved LFRP with an upstream wye strainer. It is assumed the unit will need to be installed outside in an insulated enclosure.
3205 Desert Dover Chapel CES Utilities 3205-A Outside, Near Mech Room Building Supply Low 2 Containment LFRP_REQ 2 1 1 Containment
Unprotected building supply line. The facility is considered low hazard due to facility activities; however, high hazard cross connections are present within the building elevating the overall hazard of the building.
Install an approved LFRP with an upstream wye strainer outside with approved freeze protection.
3208 Hope Chapel CES Utilities 3208-A 1st Floor, Mechanical Room Building Supply Low 2 Containment LFRP_REQ 2 2 1 Containment
Unprotected building supply line. The facility is considered low hazard due to facility activities; however, high hazard cross connections are present within the building elevating the overall hazard of the building.
Install an approved LFRP with an upstream wye strainer.
Facility Information Cross-Connection Information BP Information Backflow Recommendation
Page D-5 Table D-1. Priority Recommendations and Cost Estimates, Davis-Monthan AFB
URS Group, Inc.
Facility Num. Facility Name CC Owner CC ID CC Location Hazard / Cross- Connection
Degree of Hazard
Pipe Size (in)
Isolation or Containment BP Type BP Size
(in.)
Height
(ft) Priority
Category System Type Deficiency Recommendation
Facility Information Cross-Connection Information BP Information Backflow Recommendation
4300 CE SABER CES Utilities 4300-A 1st Floor, Mechanical Room Building Supply Low 4 Containment LFRP_REQ 4 3 1 Containment
Unprotected building supply line. The facility is considered low hazard due to facility activities; however, high hazard cross connections are present within the building elevating the overall hazard of the building.
Install an approved LFRP with an upstream wye strainer.
4809 A-10 Maintenance Dock CES Utilities 4809-A 1st floor, Mechanical Room, Between Bays 3 and 4
Building Supply High 2.5 Containment LFRP_REQ 2.5 1 1 Containment Unprotected building supply line. Install an approved LFRP with an upstream wye strainer.
4809 A-10 Maintenance Dock CES Utilities 4809-B 1st Floor, Mechanical Room, Between Bays 1 and 2
Building Supply High 2.5 Containment LFRP_REQ 2.5 2 1 Containment Unprotected building supply line. Install an approved LFRP with an upstream wye strainer. Install drain line to floor drain.
4816 Federal Aviation Administration CES Utilities 4816-A 1st Floor, Mechanical
Room Building Supply Low 2 Containment LFRP_REQ 2 1 1 Containment
Unprotected building supply line. The facility is considered low hazard due to facility activities; however, high hazard cross connections are present within the building elevating the overall hazard of the building.
Install an approved LFRP with an upstream wye strainer.
4820 Base Operations CES Utilities 4820-A NE Side of Building Building Supply Low 2 Containment LFRP_REQ 2 2 1 Containment
Unprotected building supply line. The facility is considered low hazard due to facility activities; however, high hazard cross connections are present within the building elevating the overall hazard of the building.
Install an approved LFRP with an upstream wye strainer outside with approved freeze protection.
4844 C-130 Maintenances CES Utilities 4844-A SE Side of Building Building Supply High 2 Containment LFRP_REQ 2 2 1 Containment Unprotected building supply line. Install an approved LFRP with an upstream wye strainer outside with approved freeze protection.
5245 CMS Propulsion Shop CES Utilities 5245-A 1st Floor, Mechanical Room Building Supply High 2 Containment LFRP_REQ 2 2 1 Containment Unprotected building supply line. Install an approved LFRP with an upstream wye strainer.
5245 CMS Propulsion Shop CES Utilities 5245-D Bay Area Wash Rack Building Supply High 3 Containment LFRP_REQ 3 1 1 Containment Unprotected building supply line. Install an approved LFRP with an upstream wye strainer.
5607 355th Weapons Maintenance CES Utilities 5607-B 1st Floor, Mechanical
Room Building Supply High 2.5 Containment LFRP_REQ 2.5 1 1 Containment Unprotected building supply line. Install an approved LFRP with an upstream wye strainer.
400 Hospital FSI 400-F 1st Floor, Room 363 Dental Equipment Low 0.25 Isolation DUAL CHK ATM_REQ 0.25 1 1 Dental Equipment Unprotected supply to water filtration system used for dental chair water containers. Install a dual check with atmospheric vent.
400 Hospital FSI 400-G 1st Floor, Dental Lab Dental Equipment Low 0.38 Isolation DUAL CHK ATM_REQ 0.38 4 1 Dental Equipment Unprotected supply line to dental plaster grinder. Install dual check with atmospheric vent.
1540 355th Communications Squadron CES Utilities 1540-E NE Side of Building Swamp Cooler Supply
Line High 0.75 Isolation RP_REQ 0.75 2 1 Heating and Cooling Systems Unprotected supply line to swamp cooler. Install an approved RP with an upstream wye strainer outside with approved freeze protection.
2446 Shoppette and Auto Center CES Utilities 2446-C S Side of Building, in
Brick Enclosure Swamp Cooler Supply Line High 0.38 Isolation RP_REQ 0.38 1 1 Heating and Cooling
Systems Unprotected supply line to swamp cooler. Install an approved RP with an upstream wye strainer outside with approved freeze protection.
5245 CMS Propulsion Shop CES Utilities 5245-B Bay, N Wall Swamp Cooler Supply Line High 0.5 Isolation RP_REQ 0.5 1 1 Heating and Cooling
Systems Unprotected supply line to eleven swamp coolers.
Install an approved RP with an upstream wye strainer. Install on common supply line. OR Install an approved RP with an upstream wye strainer on supply line to each swamp cooler.
5607 355th Weapons Maintenance CES Utilities 5607-C SE Corner of Building Swamp Cooler Supply
Line High 0.5 Isolation RP_REQ 0.5 3 1 Heating and Cooling Systems Unprotected supply line to swamp cooler. Install an approved RP with an upstream wye strainer outside with approved freeze protection.
5607 355th Weapons Maintenance CES Utilities 5607-D SE Corner of Building Swamp Cooler Supply
Line High 0.5 Isolation RP_REQ 0.5 3 1 Heating and Cooling Systems Unprotected supply line to swamp cooler. Install an approved RP with an upstream wye strainer outside with approved freeze protection.
Page D-6 Table D-1. Priority Recommendations and Cost Estimates, Davis-Monthan AFB
URS Group, Inc.
Facility Num. Facility Name CC Owner CC ID CC Location Hazard / Cross- Connection
Degree of Hazard
Pipe Size (in)
Isolation or Containment BP Type BP Size
(in.)
Height
(ft) Priority
Category System Type Deficiency Recommendation
Facility Information Cross-Connection Information BP Information Backflow Recommendation
4809 A-10 Maintenance Dock CES Utilities 4809-C 1st Floor, Maintenance Bays 1, 2, 3, and 4 High Hazard Hose Bib High 0.75 Isolation RP_REQ 0.75 3 1 Industrial Water
Usage
Unprotected supply lines to four high hazard hose bibs used to operate portable swamp coolers. Drainage in area where RP is to be installed is insufficient.
Install an approved RP with an upstream wye strainer. Install RP on common supply line. Label hose bibs as "Non-Potable." Install drain line through the exterior wall to drain outside. OR Install an approved RP with an upstream wye strainer on the supply line to each hose bib.
4809 A-10 Maintenance Dock CES Utilities 4809-D Bay 4, Back Wall High Hazard Hose Bib High 0.75 Isolation RP_REQ 0.75 6 1 Industrial Water Usage
Unprotected supply line to high hazard hose bib and filter / POU drinking water system.
Drainage in area where RP is to be installed is insufficient.
Install a dedicated line to the filter system with an approved LFRP and an upstream wye strainer. AND Install another approved RP with an upstream wye strainer downstream of tee for filter system to protect against high hazard hose bib. Install drain line through the exterior wall to drain outside. Label hose bib as "Non-Potable".
4809 A-10 Maintenance Dock CES Utilities 4809-E SE Corner of Building, Back of Bay 4 High Hazard Hose Bib High 0.75 Isolation RP_REQ 0.75 2 1 Industrial Water
Usage Unprotected supply line to two high hazard hose bibs.
Install an approved RP with an upstream wye strainer outside with approved freeze protection.
Install RP on common supply line. Label hose bibs as "Non-Potable".
4844 C-130 Maintenances CES Utilities 4844-B NE Corner of Bay High Hazard Hose Bib High 0.5 Isolation RP_REQ 0.5 1 1 Industrial Water Usage
Unprotected supply line to high hazard hose bib used to fill portable swamp cooler and sink. Hose is currently laying in sink. A domestic water heater is located downstream of the hose bib. No floor drains present.
Install an approved RP with an upstream wye strainer. Disconnect hose from sink when not in use.
Reroute the supply line to the domestic water heater to be upstream of the BFPA. Label hose bib as "Non- Potable." Improve drainage in area where RP is to be installed.
5245 CMS Propulsion Shop CES Utilities 5245-C 1st Floor, Propulsion Shop, Flightline Side of Building
High Hazard Hose Bib High 0.75 Isolation RP_REQ 0.75 4 1 Industrial Water Usage
Unprotected supply line to high hazard hose bib connected to parts washer.
Install an approved RP with an upstream wye strainer. Label hose bib as "Non-Potable."
5245 CMS Propulsion Shop CES Utilities 5245-E Bay Area Wash Rack High Hazard Hose Bib High 0.75 Isolation RP_REQ 0.75 2 1 Industrial Water Usage
Unprotected hot and cold water supply lines to 3 total high hazard hose bibs connected to pressure washers.
Install an approved, hot water rated RP with upstream wye strainer on the hot water supply line.
Install an approved RP with an upstream wye strainer on the cold water supply line. "Label hose bibs as Non-Potable."
5607 355th Weapons Maintenance CES Utilities 5607-A 1st Floor, Maintenance
Bay High Hazard Hose Bib High 0.75 Isolation RP_REQ 0.75 2 1 Industrial Water Usage
Unprotected supply line to high hazard hose bib connected to a port-a-cool. No floor drains present.
Install an approved RP with an upstream wye strainer. Label hose bib as "Non-Potable." Improve drainage in area where RP is to be installed.
2612 Dorothy H Finley Child Development Center CES Utilities 2612-C 1st Floor, Kitchen Dishwasher, Commercial High 0.5 Isolation RP_REQ 0.5 0 1 Kitchen Equipment Unprotected supply line to commercial dishwasher.
Install an approved, hot water rated RP with an upstream wye strainer.
2612 Dorothy H Finley Child Development Center CES Utilities 2612-D 1st Floor, Kitchen, E
Wall Food Grinder High 0.5 Isolation RP_REQ 0.5 2 1 Kitchen Equipment Unprotected supply line to food grinder. Install an approved, hot water RP with an upstream wye strainer.
400 Hospital FSI 400-C 1st Floor, Laboratory Medical Equipment High 0.38 Isolation RP_REQ 0.38 4 1 Medical Equipment Unprotected supply line to water softener, which feeds a blood analytical machine.
Install an approved RP with an upstream wye strainer.
400 Hospital FSI 400-14 Room 38C Unknown High 0.5 Isolation DC 0.5 1 1 Miscellaneous
No access to equipment that is connected to BFPA. Existing unit is protecting an unknown hazard. Existing unit does not have an upstream wye strainer. Due to limited access, the recommendation assumes the hazard is considered high.
Determine hazard the unit is protecting. If high hazard, install an approved RP with an upstream wye strainer. If low hazard, keep existing unit and install an upstream wye strainer.
2446 Shoppette and Auto Center Vendor 2446-7
1st Floor, Employees Only Store Room, Under Counter to Right of Beverage Dispenser
Carbonator High 0.5 Isolation DC 0.5 3 2 Carbonated Beverage Dispensers
Existing unit provides insufficient protection for carbonated beverage dispensers. Existing unit is installed behind the counter and is not readily accessible for testing and repair.
Replace existing unit with an approved stainless steel RP with an upstream wye strainer. Install unit in an accessible location with sufficient clearance around the unit for testing and maintenance.
Page D-7 Table D-1. Priority Recommendations and Cost Estimates, Davis-Monthan AFB
URS Group, Inc.
Facility Num. Facility Name CC Owner CC ID CC Location Hazard / Cross- Connection
Degree of Hazard
Pipe Size (in)
Isolation or Containment BP Type BP Size
(in.)
Height
(ft) Priority
Category System Type Deficiency Recommendation
Facility Information Cross-Connection Information BP Information Backflow Recommendation
2446 Shoppette and Auto Center CES Utilities 2446-D N Side of building, Right of Entrance Glacier Water Filler Low 0.38 Isolation DUAL CHK ATM 0.38 4 2 Domestic Water Usage
Supply line fed from hose bib. Existing unit provides insufficient protection for Glacier Water Filler.
Create a supply line off of the main supply line.
Replace existing unit with an approved LFDC with an upstream wye strainer outside with approved freeze protection.
3205 Desert Dover Chapel CES Utilities 3205-1 1st Floor, Mechanical Room, E Side of Building
Boiler and Chiller, Make-Up High 1 Isolation RP 1 4 2 Heating and Cooling
Systems RP relief valve is leaking. Existing unit does not have an upstream wye strainer.
Test RP. Repair or replace unit, as necessary. When existing unit is repaired or replaced, install an upstream wye strainer.
5607 355th Weapons Maintenance CES Utilities 5607-2 1st Floor, Mechanical
Room Boiler and Chiller, Make-Up High 0.75 Isolation RP 0.75 4 2 Heating and Cooling
Systems
RP relief valve is leaking. Insufficient air gap between relief valve and drain line.
Existing unit does not have an upstream wye strainer.
Test RP. Repair or replace unit, as necessary.
Increase air gap on drain line from RP relief valve to meet UPC standards. When existing unit is repaired or replaced, install an upstream wye strainer.
3205 Desert Dover Chapel CES Utilities 3205-2 1st Floor, Mechanical Room, SE Corner of Building
Irrigation High 3 Isolation DC 3 2 2 Irrigation
Existing unit provides insufficient protection for high hazard applications. Existing unit does not have adequate freeze protection.
Existing unit does not have an upstream wye strainer.
Replace existing unit with an approved RP with upstream wye strainer. Install approved freeze protection.
2612 Dorothy H Finley Child Development Center CES Utilities 2612-B 1st Floor, Kitchen Food Grinder High 0.5 Isolation AVB 0.5 2 2 Kitchen Equipment Existing AVB provides insufficient protection for a food grinder.
Replace existing device with an approved, hot water rated RP with an upstream wye strainer.
400 Hospital FSI 400-11 1st Floor, Room 207 Building Supply High 2 Containment RP 2 2 3 Containment
Staining on relief valve indicates past discharges. Insufficent air gap between relief valve and drain line. Existing unit is not lead free. Existing unit does not have an upstream wye strainer.
Increase air gap on drain line from RP relief valve to meet UPC standards. When existing unit is replaced, install an approved LFRP with an upstream wye strainer.
400 Hospital FSI 400-10 1st Floor, Room 62 Dental Equipment High 0.75 Isolation RP 0.75 3 3 Dental Equipment Insufficient air gap between relief valve to drain line. Existing unit does not have an upstream wye strainer.
Increase air gap on drain line from RP relief valve to meet UPC standards. When existing unit is repaired or replaced, install an upstream wye strainer.
401 355th Medical Group Mechanical Plant FSI 401-1 Basement, Behind
Water Softener Water, Softening System High 2 Isolation RP 2 4 3 Domestic Water
Usage
Insufficient air gap between relief valve and drain line. Existing unit does not have an upstream wye strainer.
Increase air gap on drain line from RP relief valve to meet UPC standards. When existing unit is repaired or replaced, install an upstream wye strainer.
4844 C-130 Maintenances CES Utilities 4844-3 Base of FSS Tank 4844-1
Fire Suppression System Tank High 3 Isolation LFRP 3 2 3 Fire Suppression
System Tank Existing unit does not have adequate freeze protection. Install approved freeze protection.
4844 C-130 Maintenances CES Utilities 4844-4 Base of FSS Tank 4844-2
Fire Suppression System Tank High 3 Isolation LFRP 3 2 3 Fire Suppression
System Tank Existing unit does not have adequate freeze protection. Install approved freeze protection.
1540 355th Communications Squadron CES Utilities 1540-5
1st Floor, Mechanical Room, E Side of Building
Fire Suppression System W/ FDC High 6 Isolation LFDC 6 1 3 Fire Suppression
System W/ FDC Existing unit is missing test cock #1.
Install test cock #1 and test the unit. An approved RP is recommended; however, AFI 32-1067 only requires an approved DC for this cross-connection.
2612 Dorothy H Finley Child Development Center CES Utilities 2612-3
1st Floor, Mechanical Room, E Side of Building
Fire Suppression System W/ FDC High 4 Isolation LFDC 4 5 3 Fire Suppression
System W/ FDC Missing shutoff valve.
Install the missing shutoff valve and test the unit. An approved RP is recommended; however, AFI 32- 1067 only requires an approved DC for this cross-connection.
4820 Base Operations CES Utilities 4820-3 NE Side of Building Fire Suppression System W/ FDC High 4 Isolation DC 4 2 3,7 Fire Suppression
System W/ FDC Existing unit does not have adequate freeze protection.
Install approved freeze protection. An approved RP is recommended; however, AFI 32-1067 only requires an approved DC for this cross-connection.
5607 355th Weapons Maintenance CES Utilities 5607-3 1st Floor, Mechanical
Room Fire Suppression System W/ FDC High 4 Isolation LFDC 4 5 3 Fire Suppression
System W/ FDC Existing unit is missing test cock #1.
Install test cock #1 and test the unit. An approved RP is recommended; however, AFI 32-1067 only requires an approved DC for this cross-connection.
74 General James H Doolittle Center CES Utilities 74-2
Gated Mechanical/HVAC Yard
Swamp Cooler Supply Line High 2 Isolation RP 2 6 3 Heating and Cooling
Systems
Test cock #1 has calcified, which suggests it is damaged. Existing unit does not have adequate freeze protection. Existing unit does not have an upstream wye strainer.
Replace test cock #1 and test the unit. Install approved freeze protection. When existing unit is repaired or replaced, install an upstream wye strainer.
Page D-8 Table D-1. Priority Recommendations and Cost Estimates, Davis-Monthan AFB
URS Group, Inc.
Facility Num. Facility Name CC Owner CC ID CC Location Hazard / Cross- Connection
Degree of Hazard
Pipe Size (in)
Isolation or Containment BP Type BP Size
(in.)
Height
(ft) Priority
Category System Type Deficiency Recommendation
Facility Information Cross-Connection Information BP Information Backflow Recommendation
74 General James H Doolittle Center CES Utilities 74-5
Gated Mechanical/HVAC Yard
Chiller, Make-Up High 1 Isolation RP 1 5 3 Heating and Cooling Systems
Existing unit does not have adequate freeze protection. Existing unit does not have an upstream wye strainer. This unit may be redudant (see CCID: 74-2) with the supply line to the swamp coolers / chiller make-up line and may not be needed.
Recommendation assumes the unit is not necessary.
Determine the hazard the unit is protecting. If the unit is not needed, remove the device. If the unit is necessary, install approved freeze protection. When existing unit is repaired or replaced, install an upstream wye strainer.
401 355th Medical Group Mechanical Plant FSI 401-2 1st Floor, Mechanical
Room, Next to Boiler Boiler, Make-Up High 0.75 Isolation RP 0.75 13 3 Heating and Cooling Systems
Existing unit is installed 13 feet above the ground. The unit is not readily accessible for testing and repair. Existing unit does not have an upstream wye strainer.
Relocate existing unit to an accessible height (1-5 ft) for testing and maintenance. When existing unit is repaired or replaced, install an upstream wye strainer.
401 355th Medical Group Mechanical Plant FSI 401-3
1st Floor, Back Corner Near Backflow Testing Training Area
Chiller, Make-Up High 0.75 Isolation RP 0.75 3 3 Heating and Cooling Systems
Insufficient air gap between relief valve and drain line. Existing unit does not have an upstream wye strainer.
Increase air gap on drain line from RP relief valve to meet UPC standards. When existing unit is repaired or replaced, install an upstream wye strainer.
1540 355th Communications Squadron CES Utilities 1540-4 S Side of Building Chiller, Make-Up High 0.5 Isolation RP 0.5 1 3 Heating and Cooling
Systems
Existing unit does not have adequate freeze protection. Existing unit does not have an upstream wye strainer.
Install approved freeze protection. When existing unit is repaired or replaced, install an upstream wye strainer.
3208 Hope Chapel CES Utilities 3208-1 1st Floor, Mechanical Room, N Side of Building
Chiller, Make-Up High 0.75 Isolation RP 0.75 6 3 Heating and Cooling Systems
Existing unit is installed 6 feet above the ground. The unit is not readily accessible for testing and repair. Existing unit does not have an upstream wye strainer.
Relocate unit to an accessible height (1-5 ft) for testing and maintenance. When existing unit is repaired or replaced, install an upstream wye strainer.
4300 CE SABER CES Utilities 4300-1 1st Floor, Mechanical Room
Boiler and Chiller, Make-Up High 0.75 Isolation RP 0.75 5 3 Heating and Cooling
Systems
Existing unit is not rated for hot water applications. Existing unit does not have an upstream wye strainer.
Replace existing unit with an approved, hot water rated RP with an upstream wye strainer.
4809 A-10 Maintenance Dock CES Utilities 4809-1 1st Floor, Mechanical Room, Between Bays 3 and 4
Boiler, Make-Up High 0.75 Isolation RP 0.75 4 3 Heating and Cooling Systems
Existing unit is not rated for hot water applications. Wye strainer is not installed properly. Wye strainer is installed downstream of unit.
Replace existing unit with an approved, hot water rated RP, and move wye strainer so that it is immediately upstream of unit.
4816 Federal Aviation Administration CES Utilities 4816-1 1st Floor, Mechanical
Room Boiler and Chiller, Make-Up High 1 Isolation RP 1 3 3 Heating and Cooling
Systems
Insufficient air gap between relief valve and drain line. Existing unit does not have an upstream wye strainer.
Increase air gap on drain line from RP relief valve to meet UPC standards. When existing unit is repaired or replaced, install an upstream wye strainer.
4820 Base Operations CES Utilities 4820-1 2nd Floor, Mechanical Room
Boiler and Chiller, Make-Up High 1 Isolation RP 1 2 3 Heating and Cooling
Systems
Existing unit is not rated for hot water applications. Insufficient air gap between relief valve and drain line. Test cock #1 is damaged. Existing unit does not have an upstream wye strainer.
Replace existing unit with an approved, hot water rated RP with an upstream wye strainer.
4844 C-130 Maintenances CES Utilities 4844-2 1st Floor, Mechanical Room, E Side of Building
Boiler and Chiller, Make-Up High 0.75 Isolation RP 0.75 5 3 Heating and Cooling
Systems
Insufficient air gap between relief valve and drain line. Existing unit does not have an upstream wye strainer.
Increase air gap on drain line from RP relief valve to meet UPC standards. When existing unit is repaired or replaced, install an upstream wye strainer.
4844 C-130 Maintenances CES Utilities 4844-5 NE Corner of Building Chiller, Make-Up High 0.5 Isolation LFRP 0.5 2 3 Heating and Cooling Systems
Existing unit does not have adequate freeze protection. Existing unit does not have an upstream wye strainer.
Install approved freeze protection. When existing unit is repaired or replaced, install an upstream wye strainer.
4844 C-130 Maintenances CES Utilities 4844-6 NW Corner of Building Chiller, Make-Up High 0.5 Isolation LFRP 0.5 2 3 Heating and Cooling
Systems
Existing unit does not have adequate freeze protection. Existing unit does not have an upstream wye strainer.
Install approved freeze protection. When existing unit is repaired or replaced, install an upstream wye strainer.
400 Hospital FSI 400-13 S Side of Building Irrigation High 1.5 Isolation RP 1.5 3 3 Irrigation
Water supply to existing unit is shut off.
Existing unit does not have adequate freeze protection. Existing unit does not have an upstream wye strainer.
Install approved freeze protection. When existing unit is repaired or replaced, install an upstream wye strainer. OR If unit is to remain inactive, remove existing unit and cap the lines.
400 Hospital FSI 400-7 W Side of Building, Near Hospital Entrance Irrigation High 3 Isolation RP 3 1 3 Irrigation Hazard associated with this unit has been removed.
Remove unit and cap line. If existing unit is not removed, it must be tested as an active unit and an upstream wye strainer and approved freeze protection must be installed.
Page D-9 Table D-1. Priority Recommendations and Cost Estimates, Davis-Monthan AFB
URS Group, Inc.
Facility Num. Facility Name CC Owner CC ID CC Location Hazard / Cross- Connection
Degree of Hazard
Pipe Size (in)
Isolation or Containment BP Type BP Size
(in.)
Height
(ft) Priority
Category System Type Deficiency Recommendation
Facility Information Cross-Connection Information BP Information Backflow Recommendation
2612 Dorothy H Finley Child Development Center CES Utilities 2612-4 W Side of Building, on
Perimeter Irrigation High 2 Isolation RP 2 1 3 Irrigation Existing unit does not have adequate freeze protection. Existing unit does not have an upstream wye strainer.
Install approved freeze protection. When existing unit is repaired or replaced, install an upstream wye strainer.
400 Hospital FSI 400-12 1st Floor, Room 61A, Back Closet Sterilizer High 2 Isolation RP 2 2 3 Medical Equipment
Insufficient air gap between relief valve and drain line. Existing unit does not have an upstream wye strainer.
Increase air gap on drain line from RP relief valve to meet UPC standards. When existing unit is repaired or replaced, install an upstream wye strainer.
400 Hospital FSI 400-B
1st Floor, Mechanical Room, Room 355, Access Through Dental X-Ray Room
Fire Suppression System W/ FDC High 4 Isolation BFPA_REQ 4 4 4 Fire Suppression
System W/ FDC Unprotected fire suppression system supply line with fire department connections.
An approved RP is recommended; however, AFI 32- 1067 only requires an approved DC for this cross-connection.
Note: Table D-1 is sorted by priority category. Bold lines indicate divisions between priority category groupings. Within each priority category, recommendations are sorted by system type then building number.
File details come from the government source that posted it. Updated .