Atch_44_WD_NV160001_20160311.pdf

PDF 144 KB Posted

Attached to
Nellis AFB Multiple Award Construction Contract (MACC) Solicitation Federal contract opportunity
Solicitation number
FA4861-16-R-A100
Issued by
Department of the Air Force Air Combat Command

About this file

Atch 44_Wage Determination_NV160001_20160311

View the file

Other files for this federal contract opportunity

Other files attached to Nellis AFB Multiple Award Construction Contract (MACC) Solicitation, newest first.
File Type Posted
SYNOPSIS_OF_AWARD.docx DOCX document
Atch_62__Nellis_Creech_AFB_Facility_Metering_Requirements.pdf PDF
Atch_60_ETL_07-04_AF_Carpet_Standard.pdf PDF
16RA100_Tech_QA_(Part_3).pdf PDF
Atch_61__AF_Facility_Metering_Policy.pdf PDF
Atch_53_Statement_of_Work _RKMF_16-0062_Rpr_Courtroom _Bldg_16_Revision_2.pdf PDF
Atch_43_Schedule_of_Values_Template_UNLOCKED.xlsx XLSX spreadsheet
Atch_01_MACC_SOW_Revision_1.pdf PDF
16RA100SignInRosters.pdf PDF
Atch_54_Demolition_Plan _RKMF_16-0062_Rpr_Courtroom _Bldg_16.pdf PDF
Atch_48_Teaming_List.doc DOC document
16RA100_General_Q As_(Part_2).pdf PDF
16RA100_Q A_(Part_1).pdf PDF
Atch_53_Statement_of_Work _RKMF_16-0062_Rpr_Courtroom _Bldg_16_Revision1.pdf PDF
FA4861-16-R-A100-0003_Amendment.pdf PDF
FA4861-16-R-A100-0001_Amendment.pdf PDF
Atch_25_3PH__CJE_CREECH_4in-Profile_A-size.pdf PDF
Atch_29_Trench_Sand.pdf PDF
Atch_46_WD_NV160022_201600603.pdf PDF
Atch_50_Subcontractor_Teaming_Partner_Consent_Form.doc DOC document
Atch_19_AFI_33-580_Spectrum_Management.pdf PDF
Atch_31_UM3-14-Profile_A-size.pdf PDF
Atch_45_WD_NV160004_20160603.pdf PDF
Atch_06_Engineering_Technical_Letter_20020627.pdf PDF
Atch_52_Past_Performance_Questionnaire.doc DOC document
Atch_41_AF_3064_Progress_Schedule.xfdl XFDL file
Atch_11_AFI_23-204_Material_Management.pdf PDF
Atch_40_AF_3052_Construction_Cost_Estimate_Breakdown.xlsx XLSX spreadsheet
Atch_42_Contract_Progress_Report_Template.xfdl XFDL file
Atch_24_1PH_CJE-Profile_A-size.pdf PDF
Atch_55_Facility_Photos _RKMF_16-0062_Rpr_Courtroom _Bldg_16.pdf PDF
Atch_16_AFI_32-7042_Waste_Management.pdf PDF
Atch_10_ACCMAN32-7051_hollomanafbsup_1.pdf PDF
Atch_02_Nellis_Creech_ID2_Handbook_201108.pdf PDF
Atch_12_AFI_32-1021_Planning_and_Programming_MILCON_Projects.pdf PDF
Atch_08_ACC_Architectural_and_Interior_Design_Stds_200201.pdf PDF
Atch_17_AFI_32-7086_Hazardous_Materials.pdf PDF
Atch_32_UM17-2_XFMR-Profile_A-size.pdf PDF
Atch_54_Demolition_Plan _RKMF_16-0062_Rpr_Courtroom _Bldg_16.pdf PDF
Atch_18_NAFB_Plan_32-7086_Hazardous_Materials_Management_Plan.pdf PDF
Atch_51_Sample_Client_Authorization_Letter.doc DOC document
FA486116RA100_Solicitaion.pdf PDF
Atch_20_AFI_40-201_Radioactive_Materials_Management.pdf PDF
Atch_14_AFI_32-1044_Visual_Air_Navigation_Systems.pdf PDF
Atch_07_Communication_Installation_Stds_20140320.pdf PDF
Atch_15_AFI_32-7044_Storage_Tank.pdf PDF
Atch_47_WD_NV160034_20160108.pdf PDF
Atch_03_Nellis_Creech_AFB_Lighting_Fixture_Req_20150528.pdf PDF
Atch_26_3PH__CJE-Profile_A-size.pdf PDF
Atch_27_1728F-806_UG__Main_VEA_standard.pdf PDF
Show all 50

Nellis AFB Multiple Award Construction Contract (MACC) Solicitation has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

General Decision Number: NV160001 03/11/2016 NV1

Superseded General Decision Number: NV20150001

State: Nevada

Construction Types: Building, Heavy and Highway

NEVADA TEST SITE (NTS), TONOPAH TEST RANGE (TTR) AND NATIONAL

TEST AND TRAINING RANGE (NTTR) ONLY

Counties: Clark, Lincoln and Nye Counties in Nevada.

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.15 for calendar year 2016 applies to all contracts subject to the Davis-Bacon Act for which the solicitation was issued on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least

$10.15 (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2016. The EO minimum wage rate will be adjusted annually. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date

0 01/08/2016

1 01/15/2016

2 02/26/2016

3 03/11/2016

ASBE0135-001 07/01/2015

Rates Fringes

Asbestos/Insulator Worker........$ 42.00 18.23

Includes application of all insulation materials, protective coverings, coatings and finishes to all mechanical systems.

BOIL0092-001 01/01/2013

BOILERMAKER......................$ 33.50 27.02

BRNV0003-003 03/01/2015

BRICKLAYER.......................$ 34.95 11.88

MARBLE SETTER....................$ 40.76 11.68

TERRAZZO WORKER/SETTER...........$ 40.76 11.68

TILE FINISHER....................$ 27.34 9.29

TILE SETTER......................$ 38.13 10.23

CARP1780-007 07/01/2015

CARPENTER

Carpenters..................$ 39.13 14.86

Millwrights.................$ 35.69 20.62

ZONE PAY:

0 to 40 miles radius from intersection of Maryland Parkway and Charleston Blvd in Las Vegas: Free Zone

40 to 60 miles radius: $2.50 additional per hour

Over 60 miles radius: $4.25 additional per hour

Laughlin Area: $2.00 additional per hour

* ELEC0357-002 10/01/2015

Including Nevada Test Site and the Tonopah Test Range

ELECTRICIAN......................$ 48.72 17.36+3%

Zone 1: Work performed within Nevada Test Site (NTS): $2.00 per hour additional.

Zone 2: Work performed within Tonopah Test Range (TTR):

$2.50 per hour additional.

Zone 3: Work performed within Nevada Test and Training Range

(NTTR): Excluding Nevada Test Site and Tonopah Test Range:

$2.50 per hour additional.

ELEV0018-002 01/01/2016

ELEVATOR MECHANIC................$ 51.01 29.985

FOOTNOTE:

Employer contributes 8% of the basic hourly rate for over 5 years service and 6% of the basic hourly for 6 months to 5 years service as Vacation Pay Credit. Eight paid Holidays:

New Years Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day, Friday after Thanksgiving, and Christmas Day.

ENGI0012-005 08/01/2015

POWER EQUIPMENT OPERATOR

GROUP 1.....................$ 39.54 26.00

GROUP 2.....................$ 39.78 26.00

GROUP 3.....................$ 40.02 26.00

GROUP 4.....................$ 40.13 26.00

GROUP 5.....................$ 40.32 26.00

GROUP 6.....................$ 40.42 26.00

GROUP 7.....................$ 40.67 26.00

GROUP 8.....................$ 40.92 26.00

GROUP 9.....................$ 41.42 26.00

POWER EQUIPMENT OPERATOR CLASSIFICATIONS

GROUP 1: Air Compressor; Pump or Generator Operator;

Engineer- Oiler and Signalman; Blade Operator; Rotary Drill

Tender (Rotary and Core); Steam Cleaner/Pressure Washer;

Switchman or Brakeman; Gupie Operator(Cement).

GROUP 2: Concrete Mixer Operator; Skid Type Conveyor and

Beltman; Fireman; Generator; Pump or Compressor Operator

(2 to 5 Units inclusive, over 5 units; $0.10 per hour for each additional unit up to 10 units; portable units);

Generator; Pump or Compressor Plant; Hydrostatic Pump

Motorman (rotary and core); PJU Side Dump Jack; Screening and Conveyor machine Operator (or similar type);

Skiploader; Wheeltype; Ford; Ferguson; Jeep or similar type, 3/4 yard or less (without drag-type attachments);

Temporary Heating Plant Operator; Truck Crane Oiler.

GROUP 3: A-frame or Winch Truck Operator; Bobcat or similar type (Skid Steer); Derrickman (Rotary and Core); Dinky

Locomotive or Tunnel Motor operator; Elevator Hoist

Operator; Equipment Greaser; Ford, Ferguson or similar type

(with drag-type attachments); Global Position Systems

Chainman and Rodman; Hydra-Hammer or similar type equipment; Material Hoist/Outside manlift Operator; Power concrete Curing Machine; Power Concrete Saw Operator (or similar type); Power-Driven Jumbo Form Setter; Ross Carrier

Operator; Self-Climbing Scaffold (or similar type);

Self-propelled Tar Pipelining Machine; Stationary Pipe

Wrapping ang Cleaning Machine Operator; Towblade Operator.

GROUP 4: Asphalt Plant Fireman; Boring Machine; Boring

System Electronic Tracking Locator; Boxman or Mixer Box

(concrete or asphalt plant); Fishing Tool Engineer;

Highline Cableway Signalman; Horizontal Directional

Drilling Machine; Instrumentman; Locomotive Engineer; Micro

Tunneling (above ground tunnel); Mud Plant Operator; Power

Sweeper Operator; Roller Operator, Compacting; Screed

Operator; Seeder Trenching Machine Operator (up to 6ft.

depth capacity, manfacturer's rating) Vacuum Truck.

GROUP 5: Asphalt or Concrete Spreading; Mechanical Tamping or Finishing Machine Operator- roller (all types and sizes); soil, cement, asphalt finish; Asphalt Plant

Engineer; Deck Engine; Grade Checker; Pavement- breaker;

Pneumatic heading shield- Tunnel; Road Oil Mixing Machine;

Forklift, under five tons; Rubber-tired, heavy duty equipment (Oshkosh; DW Euclid, Letourneau; Laplant-Choate, or similar type equipment with any type attachments);

Skidloader; wheeltype, over 3/4 yds., up to and including 1

1/2-yards; Slip Form Pump (power-driven hydraulic lifting device for concrete forms); Tractor Operator Drag-Type

Shovel; Bulldozer; Tamper Scraper and Push Tractor.

GROUP 6: Batch Plant; Bulk Plant Concrete Mixer-paving;

Concrete Mobile Mixer; Concrete Pump or Pumpcrete Gun;

Crushing PlantEengineer; Dandy Digger; Driller (rotary and core); Elevating Grade; Forklift, over 5 tons;

Grade-all;Heavy Duty Welder; Highline Cableway; Hoist

(Chicago boom and mine); Jumbo Pipe Carrier; Kolman Belt

Loader and similar type; Lift slab machine; Loader

Operator- Athey, Euclid, Hancock, Sierra or similar type;

Machinist; Micro Tunnel System (below ground); Motor Patrol

(any type or size); Ozzie Padder (or similar type), Pneumatic Concrete Placing Machine Hackley- Presswell or similar type; Pneumatic Pipe Ramming Tool (and similar types); Rotomill; Sewer Plant; Shovel, Backhoe, Dragline, Clamshell, Derrick, Derrick Barge, Crane Piledriver and

Mucking Machine; Shuttle Buggy; Skiploader, wheeltype, over

1-1/2 yds.; Surface Heater and Planer; Tractor Loader -

Crawler type all types and sizes; Tractor, with boom attachments; Traveling Pipe Wrapping, Cleaning and Bending

Machine; Trenching Machine (over 6 ft. depth capacity, manufacturer's rating); Tunnel Boring Machine; Water pull

(compaction); water Well Driller.

GROUP 7: Heavy Duty Repairman; Body and Fender Mechanic;

Global Position Systems Party Chief; Heavy Duty Welder

GROUP 8: Combination Heavy Duty Repairman and Welder.

GROUP: 9 Rubber Tired, Tandem, Multiple Engine, Earth-Moving

Equipment;Sewer Treatment Plant Operator.

IRON0118-001 07/01/2015

IRONWORKER

Fence Erectors..............$ 27.08 20.29

Ornamental, Reinforcing and Structural..............$ 33.97 28.92

LABO0872-002 07/01/2014

LABORER

GROUP 1.....................$ 24.81 22.48

GROUP 2.....................$ 25.02 22.48

GROUP 1: Building/office cleanup; Cement dumper; Cesspool digger & installer; Concrete curer; Dry packing concrete & filling of bolt holes; Fence builder; Fine grader, Highway

& Street; Flagperson; Gas & oil pipeline laborer; Gas & oil pipeline wrapper - pot tender and form man; Guineau chaser;

Laborer-packing rod steel and plans; Laborer (General) construction cleanup, etc; Laborer demolition; Landscape gardener, nurseyman and grounds keeper; Making & caulking of all nonmetallic pipe joints; Paving, airport run ways & similar work; Rip rap work; Rip rap stone paver; Roto scraper; Sandblaster (pot tender); Scaler; Septic tank digger and installer (leadman); Tank scaler and cleaner;

Tool attendant(jobsite only); Tree climber; Faller, Chain saw, Pittsburg chipper and similar type brush shedders, Window cleaners.

GROUP 2: Asbestos abatement/rad worker; Asphalt raker, Ironer, Spreader; Buggymoble man; Concrete core cutter, Sawman and Cement grinding, Cribber or shorer, Cutting torch (demolition); Driller, Gas and oil pipeline wrapper;

Hard rock slinger; Jackhammer, Driller and/or pavement breaker; Laying of all nonmetallic pipe, including sewer pipe, drain pipe and underground tile; Machine tool op., (operator and tenders of pneumatic & electric tools, Vibrating machines and similar mechanical tools not separately classified herein, including hand guided ditch witch and hand- type rooler); Pesticide, Herbcide, Insecticide applicator; Powder man; Rock Slinger, Sandblaster (nozzleman); Steel Headerboard man.

PAIN0159-003 07/01/2015

PAINTER (Including Drywall

Finishing and Paper Hanging).....$ 36.38 15.24

PLAS0797-004 07/01/2014

CEMENT MASON/CONCRETE FINISHER...$ 35.18 13.70

PLUM0525-002 10/01/2015

PLUMBER/PIPEFITTER...............$ 39.76 21.06

Zone A (Las Vegas)-No Zone Pay

Zone B (NTS)-Add $2.00/hour

Zone C (TTR)-Add $2.50/hour

ROOF0162-001 08/01/2015

ROOFER...........................$ 24.88 8.49

SFNV0669-003 01/01/2016

SPRINKLER FITTER.................$ 37.59 20.83

SHEE0088-002 08/01/2014

SHEET METAL WORKER...............$ 41.41 23.57

Zone 1: 0 to 30 miles $0.00

Zone 2: 30 to 50 miles $2.50

Zone 3: 50 to 100 miles (including Laughlin) $3.50

Zone 4: over 100 miles $5.00

TEAM0631-002 07/01/2014

TRUCK DRIVER

GROUP 1.....................$ 27.19 22.31

GROUP 2.....................$ 27.29 22.31

GROUP 3.....................$ 27.50 22.31

GROUP 4.....................$ 27.68 22.31

GROUP 5.....................$ 28.18 22.31

ZONE 1: All work within 30 road miles of City Hall in Las

Vegas shall be considered a Free Zone.

ZONE 2: All work 30 to 50 road miles from City Hall in Las

Vegas shall receive $1.50 additional per hour.

ZONE 3: All work 50 to 70 road miles from City Hall in Las

Vegas shall receive $2.50 additional per hour.

ZONE 4: All work over 70 road miles from City Hall in Las

Vegas shall receive $3.50 additional per hour.

TRUCK DRIVERS CLASSIFICATIONS

GROUP 1: Light duty driver.

Light duty drivers shall include: service truck drivers, dump truck drivers of less than 16 yards water level, truck driver with legal payload capacities of less than 20 tons, road oil spreader truck drivers, water truck drivers under 4,000 gallons, and passenger bus drivers on the jobsite.

GROUP 2: Bootman; Truck greaser; Tireman; Light Vehicle

Dispatcher.

GROUP 3: Heavy duty driver; Forklift driver; Warehouseman;

Forklift driver; Equipment Parts

GROUP 4: Extra heavy duty driver; Forklift driver (over 15 tons).

GROUP 5: Off road and special equipment.

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses

(29CFR 5.5 (a) (1) (ii)).

The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of "identifiers" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate

(weighted union average rate).

Union Rate Identifiers

A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than "SU" or

"UAVG" denotes that the union classification and rate were prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.

Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.

Survey Rate Identifiers

Classifications listed under the "SU" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.

Survey wage rates are not updated and remain in effect until a new survey is conducted.

Union Average Rate Identifiers

Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010

08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.

A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.

WAGE DETERMINATION APPEALS PROCESS

1.) Has there been an initial decision in the matter? This can be:

* an existing published wage determination

* a survey underlying a wage determination

* a Wage and Hour Division letter setting forth a position on a wage determination matter

* a conformance (additional classification and rate) ruling

On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour

Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the

Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)

and 3.) should be followed.

With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the

Branch of Construction Wage Determinations. Write to:

Branch of Construction Wage Determinations

Wage and Hour Division

U.S. Department of Labor

200 Constitution Avenue, N.W.

Washington, DC 20210

2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator

(See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:

Wage and Hour Administrator

U.S. Department of Labor

The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative

Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board

U.S. Department of Labor

4.) All decisions by the Administrative Review Board are final.

END OF GENERAL DECISION