Atch_03_Nellis_Creech_AFB_Lighting_Fixture_Req_20150528.pdf

PDF 170 KB Posted

Attached to
Nellis AFB Multiple Award Construction Contract (MACC) Solicitation Federal contract opportunity
Solicitation number
FA4861-16-R-A100
Issued by
Department of the Air Force Air Combat Command

About this file

Atch 03_Nellis_Creech AFB Lighting Fixture Req_20150528

View the file

Other files for this federal contract opportunity

Other files attached to Nellis AFB Multiple Award Construction Contract (MACC) Solicitation, newest first.
File Type Posted
SYNOPSIS_OF_AWARD.docx DOCX document
Atch_62__Nellis_Creech_AFB_Facility_Metering_Requirements.pdf PDF
Atch_60_ETL_07-04_AF_Carpet_Standard.pdf PDF
16RA100_Tech_QA_(Part_3).pdf PDF
Atch_61__AF_Facility_Metering_Policy.pdf PDF
Atch_53_Statement_of_Work _RKMF_16-0062_Rpr_Courtroom _Bldg_16_Revision_2.pdf PDF
Atch_43_Schedule_of_Values_Template_UNLOCKED.xlsx XLSX spreadsheet
Atch_01_MACC_SOW_Revision_1.pdf PDF
16RA100SignInRosters.pdf PDF
Atch_54_Demolition_Plan _RKMF_16-0062_Rpr_Courtroom _Bldg_16.pdf PDF
Atch_48_Teaming_List.doc DOC document
16RA100_General_Q As_(Part_2).pdf PDF
16RA100_Q A_(Part_1).pdf PDF
Atch_53_Statement_of_Work _RKMF_16-0062_Rpr_Courtroom _Bldg_16_Revision1.pdf PDF
FA4861-16-R-A100-0003_Amendment.pdf PDF
FA4861-16-R-A100-0001_Amendment.pdf PDF
Atch_25_3PH__CJE_CREECH_4in-Profile_A-size.pdf PDF
Atch_29_Trench_Sand.pdf PDF
Atch_46_WD_NV160022_201600603.pdf PDF
Atch_50_Subcontractor_Teaming_Partner_Consent_Form.doc DOC document
Atch_19_AFI_33-580_Spectrum_Management.pdf PDF
Atch_31_UM3-14-Profile_A-size.pdf PDF
Atch_45_WD_NV160004_20160603.pdf PDF
Atch_06_Engineering_Technical_Letter_20020627.pdf PDF
Atch_52_Past_Performance_Questionnaire.doc DOC document
Atch_41_AF_3064_Progress_Schedule.xfdl XFDL file
Atch_11_AFI_23-204_Material_Management.pdf PDF
Atch_40_AF_3052_Construction_Cost_Estimate_Breakdown.xlsx XLSX spreadsheet
Atch_42_Contract_Progress_Report_Template.xfdl XFDL file
Atch_24_1PH_CJE-Profile_A-size.pdf PDF
Atch_55_Facility_Photos _RKMF_16-0062_Rpr_Courtroom _Bldg_16.pdf PDF
Atch_16_AFI_32-7042_Waste_Management.pdf PDF
Atch_10_ACCMAN32-7051_hollomanafbsup_1.pdf PDF
Atch_02_Nellis_Creech_ID2_Handbook_201108.pdf PDF
Atch_12_AFI_32-1021_Planning_and_Programming_MILCON_Projects.pdf PDF
Atch_08_ACC_Architectural_and_Interior_Design_Stds_200201.pdf PDF
Atch_17_AFI_32-7086_Hazardous_Materials.pdf PDF
Atch_32_UM17-2_XFMR-Profile_A-size.pdf PDF
Atch_54_Demolition_Plan _RKMF_16-0062_Rpr_Courtroom _Bldg_16.pdf PDF
Atch_18_NAFB_Plan_32-7086_Hazardous_Materials_Management_Plan.pdf PDF
Atch_51_Sample_Client_Authorization_Letter.doc DOC document
FA486116RA100_Solicitaion.pdf PDF
Atch_20_AFI_40-201_Radioactive_Materials_Management.pdf PDF
Atch_14_AFI_32-1044_Visual_Air_Navigation_Systems.pdf PDF
Atch_15_AFI_32-7044_Storage_Tank.pdf PDF
Atch_07_Communication_Installation_Stds_20140320.pdf PDF
Atch_47_WD_NV160034_20160108.pdf PDF
Atch_26_3PH__CJE-Profile_A-size.pdf PDF
Atch_27_1728F-806_UG__Main_VEA_standard.pdf PDF
Atch_53_Statement_of_Work _RKMF_16-0062_Rpr_Courtroom _Bldg_16.pdf PDF
Show all 50

Nellis AFB Multiple Award Construction Contract (MACC) Solicitation has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Nellis and Creech AFB Energy Efficient Lighting Fixture Requirements

28 May 2015

1. Codes and Standards: All design and construction must be in compliance with the most recent versions of the following:

Unified Facilities Criteria (UFC) 3-530-01 Design: Interior, Exterior Lighting and

Controls.

Unified Facilities Guide Specification (UFGS) 26 51 00.00 40 for interior lighting

UFGS 26 56 00 for exterior lighting

UFGS 26 56 19.00 40 for roadway lighting

UFGS 26 56 23.00 40 for area lighting

UFGS 26 56 36 00 40 for flood lighting

UFGS 26 56 20.00 10 for airfield and heliport lighting

AFI 31-101 Integrated Defense for security applications

Nellis/Creech Installation Development and Design (ID2) Handbook dated AUG 2011.

Any discrepancies between code or standards provisions and the contract documents shall immediately be brought to the Contracting Officer’s attention, and the more stringent requirements shall apply unless otherwise directed. Contractor shall comply with and implement all applicable design goals, technical constraints, considerations, and policies stated in the Nellis-

Creech Installation Development and Design (ID2) Handbook (August 2011) unless an alternate approach is stated in project scope of work or approved by Contracting Officer. UFC 3-530-01 supersedes any applicable requirements stated in the ID2. Contractors shall be responsible for obtaining any copies of all items referenced in this paragraph. The most current versions of

UFCs, UFGS and ETLs can be found at http://www.wbdg.org/ccb/ccb.php.

2. Per UFC 3-530-01 sec. 5-3.7 Light-Emitting Diode (LED), LED’s may only be considered for:

2.1 Exit signs, other lighted information signs and traffic signals.

2.2 Step lighting, nightlights, task lighting, cove lighting, wall washing, downlighting, canopies, high bays, parking garages, and red lighting systems for guard stations.

2.3 Street, parking, roadway, area and façade lighting.

2.4 For Visual Air Navigation Systems, such as airfield approach, runway and taxiway lighting systems, please refer to UFC 3-535-01 and AFI 32-1044. Visual Air Navigation

Systems are not covered in this specification.

3. ALL lighting fixtures shall comply with below except “Interior Lighting Fixtures

20 feet or less above finished floor.”

3.1 Luminaires shall be solid-state LED Luminaires.

3.2 Fixtures shall have a color temperature in KELVIN of between 4000K and 4500K.

3.3 Ballasts and lamps shall have a minimum warranty of 5 years.

http://www.wbdg.org/ccb/ccb.php

3.4 Ballasts and lamps shall have a minimum rated life of 50,000 hours.

3.5 Fixtures shall be rated to operate at ambient temperatures between 0 degrees F and

120 degrees F or higher. This requirement does not apply to Interior Recessed, Downlight, and

Wall Wash Fixtures.

3.6 Power Factor shall exceed 98%.

3.7 All exterior light fixtures shall have an Efficacy > 100 lumens/watt and upward

Efficiency < 10%

3.8 T-5 fixtures are prohibited.

3.9 All interior facility lighting fixtures shall be controlled by motion detectors. Any exceptions shall be requested by Contractor for approval by the Contracting Officer. No exceptions will be made for restroom and conference room fixtures. However, a wall switch shall be installed to turn sensors/lights on and off as needed (i.e. lights off in a conference room in order to view wall screens). Sensors shall be placed in a location not affected by movement outside of open doorways.

4. Interior Lighting Fixtures located 20 feet or less above finished floor.

4.1 Luminaires shall be 32 watt T-8 fluorescent lamps.

4.2 LEDs shall not be used in linear fluorescent luminaires such as linear direct / indirect pendants and 2x4 or 2x2 troffers.

4.3 Luminaire Efficiency Ratio (LER) shall be > 77.

4.4 Fixtures shall have a color temperature in KELVIN of 4100K. Other color temperatures may be considered in housing applications, hospitality applications, and in maintenance facilities. See UFC 3-530-01 for additional information.

4.5 Ballasts shall be electronic.

4.6 Provide wire guards for all open fluorescent lamps.

5. Interior High Bay Fixtures located higher than 20 feet above finished floor

5.1 Luminaire Efficiency Ratio (LER) shall be > 50.

5.2 Daylighting controls shall be utilized for energy savings.

6. Exterior Street and Parking Lot Fixtures

6.1 All street and parking lot lighting shall include dusk till dawn photocells. Include one photocell per light circuit.

6.2 Automatic Bi-level dimming with occupancy sensors shall be used in parking lots to allow energy savings when parking lots are used infrequently.

6.3 Fixture lens shall be glass.

7. Exterior Wall Pack and Walkway Lighting Fixtures

7.1 All wall packs and walkway lighting fixtures shall include dusk till dawn photocells.

Include one photocell per light circuit.

7.2 Fixture lens shall be glass.

7.3 Light bollards shall be vandal resistant type and electrical service shall be 208v maximum with 120v to ground.

8. Exterior Area, Flood, Canopy, and Security Lighting Fixtures

8.1 Contractor shall obtain the written approval of the security lighting fixtures from base

Security Forces and Anti-terrorism Force Protection (ATFP).

8.1.1 Fixtures shall be compatible with CCTV, and night vision goggles.

8.1.2 Fixtures shall meet illumination requirements for security and ATFP.

8.2 Automatic Bi-level dimming with occupancy sensors shall be used to allow energy savings when lights are used infrequently. Maintain illumination levels for adequate security when lights are dimmed.

9. Exterior Apron Airfield Lighting Fixtures

9.1 Contractor shall obtain written approval of the LED fixtures from base Security

Forces and ATFP.

9.1.1 Fixtures shall be compatible with CCTV, and night vision goggles.

9.1.2 Fixtures shall meet illumination requirements for security and ATFP.

9.2 Fixture lens shall be glass. Plastic and Acrylic are prohibited.

9.3 Ballasts shall be located between 10 and 15 feet above ground level and shall be easily accessible for maintenance.

9.4 Automatic Bi-level dimming with occupancy sensors shall be explored to allow energy savings when lights are used infrequently. Maintain illumination levels for adequate security when lights are dimmed.

END OF SPECIFICATION