Attachment 1- SOW Demo Airfield Support Facilities.pdf

PDF 469 KB Posted

Attached to
Demo Airfield Support Facilities
Solicitation number
FA4861-13-R-A015
Issued by

About this file

Statement of Work

View the file

Other files

File Type Posted
13579_-_Bldg._82_Report.pdf PDF
13582_-_Creech_Bldg._80.pdf PDF
13580_-_Creech_Bldg._95.pdf PDF
13581_-_Creech_Bldg._81.pdf PDF
Attachment 4- Nellis-Creech ID2 Handbook.pdf PDF
APPENDIX E Project Area View - Creech Demo Bldgs.pptx PPTX presentation
Attachment 16- Past Performance Survey.doc DOC document
Attachment 11- UFC 1-300-08 Criteria for Transfer and acceptance of DoD real property.pdf PDF
Attachment 8- AF Form 3065 Progress Report.xfdl XFDL file
FA4861-13-R-A015.pdf PDF
Attachment 7- AF Form 3000 Material Approval Submittal.xfdl XFDL file
Attachment 5- AF Form 66 Schedule of submittals.doc DOC document
Attachment 14- Bldg 81 drawing.pdf PDF
Attachment 10- DD 1354 Transfer and Acceptance of DoD Real Property.pdf PDF
Attachment 9- UFC 3-600-01 Fire Protection Engineering for Facilities.pdf PDF
Attachment 6- AF Form 3064 Contractor Progress Schedule.xfdl XFDL file
Attachment 3- AF Form 3052 Cost Estimate Breakdown.xls XLS spreadsheet
Attachment 12- UFC 4-021-01 Design and O M Mass Notification Systems.pdf PDF
Attachment 2- WD NV130022 NV22.docx DOCX document
Attachment 13- UFC 4-022-03 Security engineering fences gates and guard facilities.pdf PDF
Attachment 15- Bldg 82 drawing.pdf PDF
APPENDIX D Utility Connections for Creech Demo Bldgs.pptx PPTX presentation
Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

LKTC 13-1032

Demo Airfield Support Facilities Solicitation FA4861-13-R-0015

STATEMENT OF WORK

FOR

Demo Airfield Support Facilities

CREECH AIR FORCE BASE, NEVADA

OFFICE OF THE BASE CIVIL ENGINEER

14 August 2013

SPECIFICATION INDEX

(14 August 2013)

SPECIFICATION INDEX

DIVISION 1 GENERAL REQUIREMENTS DATED PAGES

01 11 00 Summary of Work 16 July 2013 37

01 33 00 Submittal Procedures 16 July 2013 5

APPENDIX DATED PAGES

A – Demo Building Locations

16 July 2013 1

B - VEA Connection Charge Agreement 16 July 2013 2

C – Earthwork Specs 16 July 2013 4

D – Utility Connections (attachment) 16 July 2013 5

E – Project Area Overview (attachment) 16 July 2013 9

Summary of Work SPECIFICATION INDEX

SECTION 01 11 00

SUMMARY OF WORK

14 August 2013

1. PART 1 – GENERAL

1.1 SUMMARY

Description: Contractor shall furnish all design, labor, equipment, material, manufactured articles, transportation, supervision, and all else necessary to perform all operations in connection with successfully completing the project LKTC 13-1032 Demo Airfield Support Facilities as specified herein, as required per attached specifications and referenced documents, and as shown on attached project drawings. The Contract will govern in the case of any conflicts with this section.

1.1.1 Definitions:

1.1.1.1 Contracting Officer: The term Contracting Officer refers to the Contracting Officer or his/her contract specialist, and the term Contractor refers to the general contractor. The general contractor is responsible for all subcontractors, suppliers, and consultants under his employ.

1.1.1.2 Contracting Officer’s Representative: The Base Civil Engineer or his authorized representative is designated as the Contracting Officer's Representative (COR) (Construction Manager), for the purpose of technical surveillance and evaluation of the work performed under this contract. This designation in no way authorizes anyone other than the Contracting Officer to commit the Government to changes in the terms of the contract.

1.2 LOCATION: The project site is located at Creech AFB.

1.2.1 Creech AFB is located approximately 55 miles north of Las Vegas, Nevada on Highway US-95. The specific project location is indicated on building location images accompanying this contract.

1.3 DESCRIPTION OF WORK

1.3.1.1 SCOPE OF WORK: LKTC 13-1032, Demolish four airfield support facilities at Creech Air Force Base, Nevada. Must maintain a separate work area to ensure traffic and/or debris does not interfere with adjacent airfield operations. Will also need to cap all connecting utilities (electric, water, sewer, communications) at closest primary distribution. Two areas will need permanent fencing installed to provide flightline security after buildings 81 and 82 have been removed.

1.3.2 DEMOLITION SEGMENT:

1.3.2.1 Contractor cannot start work prior to 1 December 2013.

1.3.2.2 After abatement and proper disposal of hazardous materials, Contractor is required to demolish the structures completely. Locations of buildings are shown on Appendix A. Hazardous material abatement shall be completed before the contractor will be able to commence demolition of the buildings.

1.3.2.3 Prior to any utility outages, Contractor shall apply for and obtain an approved AF 103, Base Civil Engineering Work Clearance Request. Clearance is required prior to start of demolition. Contractor shall be responsible for processing the AF Form 103 (allow at least 28 days to process).

1.3.2.4 Temporary construction sign to include Dust Control permit shall be provided and installed within the site. Dust Control permit to be obtained at Clark County.

1.3.2.5 Maintain work-site perimeter with temporary fencing to ensure debris and/or equipment does NOT interfere with flightline use and/or aircraft adjacent to demo projects.

1.3.2.6 Demo gas lines, sewer lines and other utilities in the area during demolition. Disconnect and cap all utilities appropriately back to the main. If main is in the street, Contractor shall sawcut and patch back any pavement with like material after capping lines. Patch shall be a minimum of 2’ wider than trench on both sides, i.e. if trench is 2’ wide the patch will be 6’ wide. Road closures will be limited to one lane at a time if required.

1.3.2.7 Ensure continued utility connections to other facilities in the area.

1.3.2.8 Demo all electrical circuits back to High Voltage Riser at power pole. Also demo all transformers, disconnects and concrete pads. WILL REQUIRE USING VALLEY ELECTRIC

ASSOCIATION (VEA) FOR ALL ELECTRICAL DISCONNECTS, SEE PARAGRAPH 1.17.4

FOR ADDITIONAL INFO.

1.3.2.9 Remove and dispose of all the existing HVAC system. The removal of the HVAC must be accomplished by a certified person and the coolant must be disposed of according to all applicable codes.

1.3.2.10 Must provide all dump receipts prior to project completion.

1.3.2.11 Backfill areas must be compacted to at least 90 percent laboratory maximum density, per attached specification. Provide proper surface drainage for the site after demolition, grade the compacted earth so that it drains properly away from the flight line and to the nearest roadway (Third Street). There is no borrow area for fill dirt on base. 2" minus crushed concrete is not acceptable fill material.

1.3.2.12 Cover the area after removal of building 81 with ¾” Rebel Red granite rock mulch, 3” deep. Spray herbicide and provide weed-block fabric under the rock mulch. Weed-block fabric shall be a minimum weight of 3 oz/SY.

1.3.2.13 Repave areas after removal of buildings 80, 82 and 95. Provide striping for parking to match adjacent parking lot stall sizes and pattern.

1.3.2.14 Install approximately 200 LF of chain link fence to secure flightline after building(s) removal. Fencing must match adjacent/existing fencing in material, height and color. Must also meet Force Protection requirements IAW Antiterrorism/Force Protection Standards (UFC 4-022-03). Must use temporary fencing to secure area and prevent traffic/debris from interfering with adjacent flightline/operations.

1.3.2.15 Irrigation lines shall be reconfigured as necessary to maintain proper irrigation to surrounding areas still requiring water.

1.3.2.16 LKTC 13-1032 DEMOLISH AIRFIELD SUPPORT FACILITIES, BLDGS 80, 81,

82 & 95. This project involves the demolition of a total 3,700 SF. This includes demo of structures, removal of concrete pads and disconnecting utilities.

1.3.2.17 Building 80 is a 17’ x 20’ carport made of wood framing with wood roofing. The interior walls and ceilings are uncovered wood framing members.

1.3.2.18 Building 81 is a 24’ x 56’ double-wide mobile home made of wood framing with stucco exterior and shingle roofing. The interior walls and ceilings are covered with finished sheetrock.

1.3.2.19 Building 82 is a 24’ x 56’ double-wide mobile home made of wood framing with plywood paneling exterior and shingle roofing. The interior walls and ceilings are covered with finished sheetrock.

1.3.2.20 Building 95 is a 24’ x 28’ former airfield lighting vault made of concrete with textured exterior and shingle roofing. The interior walls and ceilings are covered with finished sheetrock and/or painted concrete.

1.4 DESIGN LEVELS AND REQUIREMENTS

1.4.1 100% Draft and Final Design required: Please see requirements below. Design shall include demolition drawings and construction drawings depicting what is being removed from the site and what it is being replaced with. i.e. Site drawings, utilities removed and reconfigured as required, pavement details, landscape details, drainage requirements, etc.

1.4.2 The documents will include the following minimum information, as applicable to each project: drawings, contractor shall provide four (4) hard copies and four (4) electronic copies (Adobe Acrobat PDF) of the submittal documents, a list showing sections to be incorporated in the specifications, and any other design components relating to the 100% design as identified in the TO.

All utilities and structures shall be shown, as well as, the paving/ grading/drainage plan, haul route, and contractor’s storage site.

1.4.2.1 Drawings: Drawings shall also include the following, as applicable:

1.4.2.1.1 Site Plans: All required controlling dimensions. Site plan showing proposed location of work including benchmarks, access from main roads, and surface or sub-surface drainage concepts.

Utilize scale which shows building site, relation to adjacent structures, existing utilities, additional utilities required, and other major site features. Scales for site plans shall be sufficiently large to clearly delineate building location, topographical, utilities, streets, roads and parking, vegetation and other pertinent data. Show new and existing site amenities.

1.4.2.1.2 Plans and Elevations: All plans and elevations shall portray general layout and interfacing features even if such features are not in the contract area.

1.4.2.1.3 Other Drawings: Shall depict the project accurately and shall show sufficient detail to convey the intended appearance and work scope of the project. Detail references, notes, and material indications shall be sufficient to thoroughly describe and index the work. Provide demolition drawings as required.

1.4.2.1.4 Structural, Mechanical, Plumbing, Fire Protection, Electrical, and Tele-Communications:

Provide general layout of major systems, utility support, and major design features. Clearly show and note project scope. Disconnection and any connection points to existing utilities shall be shown.

1.4.2.1.5 Contractor must include all comments from the previous design review in the following design submittal. Contractor shall not submit the next design until the previous has been approved by the Government.

1.4.2.1.6 Scales: Shall be sufficiently large to clearly portray the work and include detailed schedules and legends appropriate to describe the design. Mechanical and electrical schematics shall be large enough so that relative features are proportionate and easily related to architectural plans and features. Hard copies shall be clearly readable. The use of redline schematics shall not be acceptable. Submission of drawings in the incorrect scale shall result in disapproval of the submittal.

1.4.2.2 Technical Analysis: A detailed technical analysis shall be included with each submittal.

The technical analysis shall include all applicable items as listed below. The basic calculations needed to size the components of the project must be included. It is the responsibility of the Contractor to verify all recorded as-built conditions before the start of work; the Contractor shall include a survey of such conditions in their initial design analysis.

1.4.2.2.1 Problem Identification: Description of work and how the proposed design will meet the objective(s).

1.4.2.2.2 Site Description:

Earthwork calculations

Description of project landscaping, vegetation, and trees Any applicable site restrictions Building utility connections to utility runs Storm drainage (Calculations and materials rationale) Parking and paving Topographical survey Soils test and reports

1.4.3 100% Draft: Documents shall build upon the prior design submittal. This will include, for review, final and complete drawings, and specifications. All project requirements identified in the most current contract revision, site visit minutes, modifications, and review comments must be incorporated. The Contractor shall provide four (4) hard copies and four (4) electronic copies (Adobe Acrobat PDF) of the submittal documents.

1.4.3.1 Drawings: Shall provide a package of drawings, complete in all respects. The submitted drawings shall be dated with the date of the submittal and the cover sheet shall state that it is a 100% design submittal. Drawings shall include all applicable drawings from the following list:

Cover Sheet/Project Location Maps Index of drawings Haul routes Project location Site Plans:

o Building location and orientation o Existing topographic conditions plan o Grading and drainage plan including subsurface o Airfield data within 100’ of project site o Exterior utilities. Details of disconnection from previous facilities.

o Landscape Plan and Plant Schedule (if applicable)

1.4.3.2 Specifications: Shall provide a set of technical specifications complete in all respects, including bid schedule, material submittal schedule (AF Form 66), and a schematic construction schedule. The specifications, including all technical and special conditions, will be prepared to meet Government standards. References will be made to Federal Specifications, ASTM, ANSI, and trade standards when applicable to establish a uniform standard. The specifications will be tailored to define each test and submittal items required and fully describe all work to be done. When Government-furnished material or equipment is to be used, a schedule of property or equipment will be prepared listing the item, description and quantity. If no Government-furnished material is to be used, the statement of work will include a statement that no Government-furnished will be used.

Mandatory contract clauses or special provisions shall not be duplicated or modified by inclusion of similar or supplementing provisions in the specifications. A set of these provisions is available for review upon request.

1.4.3.3 Material Submittal Schedule: Shall identify on AF Form 66, "Schedule of Material Submittals", each item required to be submitted.

1.4.3.3.1 Items shall be separated in applicable CSI divisions, and appropriately headed.

1.4.3.3.2 Each shall identify clearly what is being submitted, the specification/drawing reference requiring the submittal, the number of copies required, and the required submission date (e.g., a submittal required within 10 days after the Notice to Proceed (NTP) for Construction is issued, shall be shown as "NTP + 10").

1.4.3.3.3 If more than one type of an item is to be submitted (e.g., Kitchen and Entry doors), each shall have a separate line item number.

1.4.4 Final Design: Documents building upon the prior design submittal which include final contractor accomplished corrections based on the Government's review of the prior design documents (drawings and specs). Contractor shall not start construction until directed by the Contracting Officer in writing to begin by means of a Notice to Proceed.

1.5 SITE VISIT: Contractors are urged to attend the site visit that will be scheduled by Base Contracting prior to the bid opening.

1.6 SINGLE, PRIME CONTRACT: The work will be constructed under a single, prime contract.

1.7 PERFORMANCE PERIODS & NOTICE(S) TO PROCEED:

1.7.1 The performance period for the design segment of this project is 30 calendar days after receipt of the Notice to Proceed. At the beginning of a project, after bonding has been submitted and approved, the Contracting Officer shall initiate a Notice to Proceed #1 (NTP1) so that the Contractor can perform design, initial material tests, get submittals approved, and mobilize equipment. This shall not occur until after the appropriate bonds have been received by the Contracting Officer after contract award. The Government review period for 100% design is two weeks. The Contractor shall include review time in their design segment performance period.

1.7.2 The performance period for the construction portion of this project is 59 calendar days after receipt of the Notice to Proceed. Notice to Proceed will not be issued prior to 1 Dec 2013 but work must begin prior to 31 Dec 2013. At the beginning of the construction performance window, and if all necessary submittals have been approved by the Contracting Officer, the Contracting Officer shall initiate Notice to Proceed #2 (NTP2) to allow actual demolition work to begin.

1.8 CODES & STANDARDS: All design and construction must be in compliance with the International Building Code (IBC) latest Edition, Department of Defense Unified Facilities Criteria Standards (UFC), all Public Laws (P.L.), Executive Orders (E.O.), Code of Federal Regulations (CFR), Department of Defense Instructions (DODI), Department of Defense Directives (DODD), and Clark County, State of Nevada, and Federal standards, codes, and laws or other higher authority documents as applicable. Any discrepancies between code or standards provisions and the contract documents shall immediately be brought to the Contracting Officer’s attention, and the more stringent requirements shall apply unless otherwise directed.

1.8.1 COMMUNICATIONS SPECIFICATIONS: The design and construction of the communications system shall comply with the requirements stated in the following documents:

Section 271000 Building Telecommunications Cabling System; 38 EIG Handbook 33-01

Communications and Information FIRST FOUR HUNDRED FEET; Engineering Technical Letter (ETL) 02-12: Communications and Information System Criteria for Air Force Facilities; UFC 3-580- 01 Telecommunications Building Cabling Systems Planning and Design; Telecommunication Industry Association (TIA) Standards; Comm Room Wiring Plan. All communication work in this project shall be performed by and all equipment shall be furnished and installed by a Building Industry Consulting Service International (BICSI) certified telecommunications contractor. Any conflicts between standards must be brought to the Contracting Officer’s attention and will be resolved through the appropriate 99 CS Plans and Programs office.

1.8.2 OTHER STANDARDS: All project design and construction shall meet the requirements stated in the following documents: All applicable design goals stated in the Nellis-Creech Installation Development and Design (ID2) Handbook (August 2011), Contractor shall comply with and implement all applicable technical constraints, considerations, and policies stated in the ID2 Handbook unless an alternate approach is stated in project scope of work or approved by Contracting Officer; Unified Facilities Criteria (UFC) 3-600-01 Fire Protection Engineering for Facilities; UFC 4-021-01, Mass Notification Systems; UFC 4-022-03,Antiterrorism/Force Protection Standards.

1.8.3 Contractors shall be responsible for obtaining copies of all items referenced in this document.

Department of Defense criteria can be retrieved at: http://cbbs.spk.usace.army.mil.

1.9 WORKING HOURS: Standard working hours are from 7:00 a.m. to 4:00 p.m. Monday through Friday excluding Federal Holidays and the day after Thanksgiving. Contractor requested deviations to this schedule will be considered if it is in the best interest of the government as determined by the Contracting Officer. If the Contractor desires on working hours other than 7:00 am to 4:00 pm, Monday through Friday, he must submit to the Contracting Officer a work schedule at least five working days prior. The schedule shall note the activities planned, the planned hours of work, and the reason for the additional hours so that the construction inspectors can plan their work schedule.

1.10 AIR FORCE BASE ENTRY, REGULATIONS, & RESTRICTIONS

1.10.1 Conformance with Regulations/Directives: The Contractor shall conform to base regulations and directives pertaining to security, safety, traffic, fire and personnel clearances, insofar as they pertain to the Contractor's activities as directed by the Contracting Officer. Contractor employees and visitors are subject to the same restrictions as government personnel. Some of these are noted in the following paragraphs.

1.10.1.1 Smoking: Smoking is permitted in designated, outside smoking areas only. No smoking will be allowed within any base facility.

1.10.1.2 Seatbelts: The use of seatbelts by all vehicle operators and passengers is mandatory on Nellis AFB and in the state of Nevada. On Nellis AFB, vehicle operators and passengers not wearing their seatbelt will be issued a traffic citation and may lose on-base driving privileges.

http://cbbs.spk.usace.army.mil.been/

1.10.1.3 Firearms/Illegal Drugs: No firearms or illegal drugs are allowed to be brought onto Nellis AFB. By accepting a vehicle pass, each person gives their consent to a search of their vehicle while it is entering, while on, or while leaving Nellis AFB.

1.10.1.4 Speed Limit: Unless otherwise posted, the speed limit on base is 25 MPH and in base housing areas and flightline it is 15 MPH.

1.10.1.5 Cell Phones: Use of hands-free cell phones while driving on an AF installation is required.

1.10.1.6 Parking: Contractor vehicles and equipment will be parked in common parking areas or as otherwise approved in writing by the Contracting Officer.

1.10.2 Enhanced Security Measures: During elevated force protection levels there may be increased security and more restricted access to Nellis AFB.

1.10.3 Additional Information: The following procedures and requirements for construction contractors requiring access, if followed, will assist in reducing delays in gaining access to work areas.

1.10.3.1 At Creech AFB, construction contractors may access the base through the Main Gate.

1.10.3.2 Upon arrival at a gate, all vehicle occupants will be required to show identification. A pictured identification such as a driver’s license will be required. The person will be required to identify himself/herself and the firm he/she works for and the information will be verified against the Entry Authority List (EAL) and may then proceed to obtain their long term pass.

1.10.3.3 Personnel cannot show up at the gate without prior notification for access and expect to gain access. Verbal access cannot be provided.

1.10.3.4 Each employee and their vehicle may be subjected to search before entry. Each employee will be expected to comply with all directions provided by security personnel at the access gate. Failure to fully comply with directions provided by security personnel will result in access being denied. Before attempting access, ensure there are no weapons or other prohibited items in the vehicle as they will be confiscated if found. Further, no practical jokes or wise remarks will be tolerated. Security of Creech AFB is treated as serious business and full cooperation is required.

1.10.3.5 Once access to the base has been granted, each contractor employee will be expected to proceed to the work site and not go to other facilities except in the performance of their work.

Access to the flightline can only be allowed through additional authorization.

1.10.3.6 Expect some delays in gaining access to the base especially between the hours of 6:30 AM to 8:00 AM due to heavy traffic.

1.10.3.7 Gate Hours: Gate hours are subject to change by the Government at any time due to military activities. Contractor shall be responsible for coordinating with the Contracting Officer for base access.

1.10.4 Unauthorized Activity: The contractor shall inform all personnel working under his/her jurisdiction (including subcontractor and supplier personnel) that access to areas outside of the immediate work area (excluding cafeterias and restrooms near the work site, direct haul and access routes, Contracting and Civil Engineering offices, and points of supply and storage) is prohibited.

Circulation of said personnel will be limited to official business only. Persons engaged in unauthorized reconnaissance of other contractor or government activity will be referred to the Contracting Officer for disposition. Infractions involving possible compromise of national security will be turned over to the FBI for disposition.

1.10.5 FAA Notification: Contractor will submit the required FAA Form 7460-1 to the FAA via https://oeaaa.faa.gov/oeaaa/external/portal.jsp for all new construction, work on the exterior of existing facilities, and all crane usage. Contractor will follow any and all requirements dictated by the FAA or Nellis AFB Airfield Operations personnel in response to the FAA Form 7460-1 submittal.

1.10.6 AIRFIELD CONTROLLED AREA RESTRICTIONS:

1.10.6.1 The airfield controlled area is defined as all the areas on and adjacent to airfield features, within a flightline perimeter fence, the flightline side of facilities, or as otherwise defined in specific project documents.

1.10.6.2 CONTROLLED AREA ESCORTS: The Contractor shall provide his own escorts with appropriate security clearance & badges required for work in controlled areas at Nellis AFB and Creech AFB. The Contractor & Subcontractor employees shall be accompanied by their escort at all times in the controlled area jobsites. Line badge areas numbers required are: Nellis AFB – 4 & 20;

Creech AFB – 8. These escorts will be required to obtain a temporary flightline license from the respective Airfield Operations office. Radio contact with the Airfield Control Tower and Security Forces BDOC will be made before entry, monitored while in the controlled area and contacted at departure from the controlled area. Possible escorts may include active duty or retired military or DOD civilian personnel who possess the appropriate clearance and badges and are familiar with the controlled areas and its restrictions.

1.10.6.3 Aircraft and emergency fire department vehicles always have the right of way.

Construction personnel, vehicles and equipment must yield to taxiing aircraft at all taxiway crossing points.

1.10.6.4 The Contractor must only use designated taxiway crossing points, unless otherwise directed.

1.10.6.5 Runways must be cleared of equipment and personnel and be operationally ready within five minutes in the case of In-Flight Emergencies (IFEs), unless the runway is physically unable to accept aircraft. No contractor vehicles, equipment, or personnel shall be on or crossing any active https://oeaaa.faa.gov/oeaaa/external/portal.jsp runway, except during construction period closures as outlined above or when clearance is requested from and granted by the control tower. This must be coordinated through Nellis Contracting and Civil Engineering to the control tower.

1.10.6.6 When performing work on the runway and/or taxiways, the Contractor will be issued a hand held radio by the government in order to be able to communicate with the airfield control tower. The on-site project manager shall be expected to continuously monitor the airfield frequency.

1.10.6.7 Unless authorized by the Contracting Officer, no contractor vehicles, equipment or personnel shall cross the painted red security lines located at various locations on the Airfield.

Security Police are authorized to use deadly force in such breaches of security.

1.10.6.8 Other airfield contracts may be underway at the same time as this contract, and therefore the contractors may have to share haul routes, and work in the proximity of one another.

1.10.6.9 The Contractor may be required to cease project operations on the airfield during In Flight Emergencies (IFEs) or as directed by the Installation Commander. These delays typically are for one to two hours at a time. Every effort will be made by Base Operations, Civil Engineering, and the Contracting Office to minimize all potential delays and to inform the Contractor as early as possible of such delays so that critical work can be effectively scheduled around such events. For bidding purposes, assume work stoppages will occur minimally.

1.10.6.10 All contractor personnel shall be briefed by Base Operations prior to being allowed to drive out onto the airfield. Assume the runway on which the Contractor is scheduled to work will be closed to normal aircraft traffic or shall have one end closed by using a displaced threshold.

However, the Contractor shall clear the runway as directed by the tower for IFE’s or for other circumstances. Assume one occurrence per day on average. Flying activity is minimal on weekends.

The Contractor will have to clear the runway as directed by the tower for inbound and outbound flights.

1.11 COORDINATING AND SCHEDULING

1.11.1 Work Coordination: In order for the work to progress smoothly and cause minimal difficulties, it will be necessary for the contractor, construction inspector, project engineer, and Contracting Officer to maintain close and active coordination. At all times, the Contractor shall keep the Government informed of when and what work will be accomplished. All work schedules will be coordinated with the appropriate representatives of the Contracting and Technical offices.

1.11.1.1 All work shall be accomplished in such a manner with upmost regard to Nellis, Creech and NTTR ongoing missions and cause minimum disruption to those missions.

1.11.1.2 At least two (2) calendar days prior to testing or closing hidden work, the Contractor shall identify such work and notify the Contracting Officer and Technical Representative when it will be accomplished. If proper inspections are not accomplished as a result of such lack of notification, the Contractor bears the risk of possibly removing completed work and reaccomplishing such uninspected work at no cost to the government.

1.11.2 Progress Schedule: The schedule shall be accomplished on and in accordance with the instructions pertaining to AF Form 3064 (AF3064), Contract Progress Schedule, and as specified herein.

1.11.2.1 Work percentages shall be plotted weekly, from Sunday through Saturday, beginning with the date of receipt of the Notice to Proceed (NTP) through the contract completion date. Once approved, schedules will not be changed without Contracting Officer direction and/or approval.

1.11.2.2 The Work Elements, column B on the AF3064. Each element shall be identified by the applicable, major element of work (e.g., Site Work, Concrete, Electrical, etc.).

1.11.2.3 The percentage of each listed work element of the job shall be shown opposite each major work element in Column C of the Contract Progress Schedule and may be expressed in whole numbers or may be carried out to two (2) decimals.

1.11.2.4 In order to assist in evaluating the AF3064, as well as the progress of construction, the contractor shall supplement the AF3064 with a Schedule of Values worksheet which will identify each sub-element of work along with its dollar and percentage values of the project work. A "network analysis system" may be used to supplement the proposed progress schedule.

1.11.3 Progress Reports: The report shall be accomplished on and in accordance with the instructions pertaining to AF Form 3065 (AF3065), Contract Progress Report, and as specified herein.

1.11.3.1 Progress Reports shall be submitted weekly by close of business on the Monday following completion of the previous work period.

1.11.3.2 Whenever the cumulative percentage of the work is 5% or more below the scheduled percentage, the Progress Report shall be accompanied by a letter of explanation for the delay and a plan detailing how the contractor intends to get back on schedule.

1.11.3.3 Each AF3065 shall be reviewed by the project inspector and CO for accuracy. Payment shall be authorized based on the Contracting Officer’s determination of percentage complete as reflected on the approved AF3065.

1.12 SUBMITTALS

1.12.1 AF Form 66 (AF66), Schedule of Material Submittals:

1.12.1.1 If an AF66 listing required submittal items was included with the project documents:

Within 10 calendar days after receipt of the Notice to Proceed (NTP) with construction, the Contractor shall identify a not later than “required submission date” for each item specified on this form. Contractor shall ensure the specified dates provide adequate time to process the requirement and allows sufficient order/receipt time prior to the projected installation date.

1.12.1.2 If an AF66 is required to be developed with the design documents for the project: The contractor shall develop and provide the AF66 within the timeframes specified. Required submission of the material items listed shall be identified as NTP + XX calendar days. Contractor shall ensure the specified dates provide adequate time to process the requirement and allows sufficient order/receipt time prior to the projected installation date.

1.12.2 AF Form 3000 (AF3000), Material Approval Submittal:

1.12.2.1 Each submittal shall be transmitted under an AF3000 and shall be prepared in accordance with the Instructions on the reverse of the form and in Section 013300, Submittals and Substitutions.

1.12.2.2 Variance from contract requirements: Whenever materials or drawings are required to be submitted by the Contractor for approval, and the material or drawings submitted are at variance with the specifications or Government drawings, but are approved by the Contracting Officer inadvertently and without consciousness of the variance, then the approval shall not be final unless the Contractor expressly noted on the submittal that "This material or drawing varies from specifications in the following aspects."

1.13 GOVERNMENT-FURNISHED-PROPERTY (GFP): Government Furnished Property (GFP) includes both Government-Furnished-Material (GFM) and Government-Furnished Equipment (GFE) and is defined as material or equipment owned by the Air Force that is being furnished to the Contractor to be used in the execution of the contract. If authorized and provided under the contract:

1.13.1 Inventory: GFP shall be inventoried jointly by the Contracting Officer, or their specialist, civil engineer and the Contractor to document the condition, quantity, etc. prior to exchange.

1.13.2 Responsibility: Once the Contractor takes possession, GFP becomes the Contractor’s responsibility and they will be held liable for loss, damage, destruction, or theft of GFP.

1.13.3 Return: GFE shall be promptly returned to the government upon completion of the activity.

1.13.4 Excess: All excess GFM (i.e., property that may be consumed or expended during the performance of a contract) shall be returned to the government, unless otherwise noted in the contract documents.

1.14 HAUL ROUTE

1.14.1 Specified Haul Route: The Contractor shall follow specified haul routes for this project, unless otherwise directed. The Contractor may make changes to the route only with the prior approval of the Contracting Officer at no additional cost to the Government. The Contractor shall restore the area to its original condition at the end of the contract period unless specific, written approval has been granted by the Contracting Officer.

1.14.2 Haul Route Cleanup: In an effort to minimize Foreign Object Damage (FOD) potential to aircraft, all mud, dirt, debris, foreign objects, or spills of any kind from the Contractor's operations

(including subcontractors and suppliers) on taxiways, runways, parking aprons, hard surfaces, streets, and parking lots used as access to the work or staging areas, shall be cleaned immediately after use. Cleanup shall be performed to the satisfaction of the Contracting Officer and the Airfield Manager. Contractor may be held responsible for FOD to aircraft, if the FOD is attributable to his negligence or failure to comply with contract requirements.

1.15 MATERIAL STORAGE

1.15.1 Storage Area: Unless otherwise indicated, no on-base storage facilities are available for contractor owned supplies, tools, materials or equipment. Buildings and structures which are part of the contract may be used for storage provided the space is not required for government occupancy and the contractor accepts full responsibility for the material stored therein. The Contractor shall be responsible for protecting all construction materials from weather damage.

1.15.2 Storage Site: the Contracting Officer shall designate a storage site for contractor-owned supplies, tools, materials, and/or equipment in close proximity to the jobsite. All job equipment and material not in use, but to be installed in or used on the project by the Contractor may only be stored in this area. Security for the equipment and material storage shall be provided by the Contractor at his risk. Contractor shall install and maintain temporary fencing around storage area. Fence shall be a minimum of six feet high and have tan screening material so visibility through fence is obstructed.

Fence shall be of sufficient strength to withstand high wind loads, shall remain in place for the duration of the contract, and be removed at the end of the contract at the contractor’s expense. Site shall be returned to its original condition.

1.16 UTILITIES SERVICES CREECH

1.16.1 Water and Electricity: All reasonable amounts of domestic water and electricity will be made available to the Contractor by the Government from existing system outlets and supplies.

Normal quantities of electricity and water necessary to make final tests of completely installed systems will be furnished by the Government. With prior coordination with the Contracting Officer, the Contractor shall be given access to water hydrants to obtain water for construction activities.

The Contractor shall provide and install a double back flow preventer with meter to all water hydrants made available to them for project use.

1.16.2 Telephone: Commercial telephone lines are not available to the contractor. Separate communication arrangements must be made by the Contractor as necessary.

1.16.3 Temporary Water Connections: The Contractor shall, at his own expense, make all temporary connections and install distribution lines. The Contractor shall furnish to the Contracting Officer a complete system layout drawing showing type of materials to be used and method of installation for all temporary electrical systems. All temporary lines shall be maintained by the Contractor in a workmanlike manner satisfactory to the Contracting Officer and shall be removed and the area restored to its original (or better) condition by the Contractor prior to final acceptance of the construction. The point of connection shall be coordinated with the Government technical representative prior to connection. If additional outlets are needed, they will be provided at the Contractor's expense.

1.16.4 PRIVATIZED ELECTRICAL UTILITY SYSTEM: The electrical distribution utility system at Creech AFB, Point Bravo and Range 63C has been sold to Valley Electric Association, Inc. ("utility owner") as part of the USAF utilities privatization (UP) effort. Therefore, the utility owner is the sole provider of this utility service to the installation and should be viewed just like any other local utility Contractor. The word “Contractor” below refers to the prime contractor and NOT VEA the utility owner.

1.16.4.1 Newly installed system infrastructure and modifications of or connections to existing system infrastructure identified in the specifications and drawings must be coordinated by the Contractor with the utility owner prior to the contract start date. The utility owner must be integrated into the design, inspection of construction, tie-in to existing utilities, and conveyance of any exterior utilities. The preferred process for connecting facilities is to request that the utility owner install the infrastructure required to connect facilities, up to a point of demarcation to be identified by the Government, as a connection charge. However, if infrastructure work cannot be negotiated, work may be accomplished by the prime contractor and later connected to the utility owner's system, provided that the utility owner's connection criteria, as set forth in their utility services contract with the Government, are met. Any utility owner inspection and connection fees associated with installation and final connection of Contractor constructed infrastructure to the utility owner's system must be negotiated with the utility owner and shall be the responsibility of the Contractor. All work on the system or facilities expected to connect to the system shall comply with the utility owner's specifications. IN NO EVENT SHALL CONTRACTOR CAP, CONNECT TO, OR

OTHERWISE TOUCH THE UTILITY OWNER'S INFRASTRUCTURE WITHOUT THE

UTILITY OWNER'S EXPRESS WRITTEN PERMISSION.

1.16.4.2 A “Connection Charge Agreement” (see appendix B) needs to be signed between the Contractor and VEA. A copy of the final signed agreement shall be provided to the Contracting Officer prior to issuing Notice to Proceed for construction.

1.16.4.2.1 VEA IS NOT A CONSTRUCTION SUB-CONTRACTOR BUT RATHER IS THE

UTILITY SERVICES PROVIDER.

1.16.4.2.2 Contracting regulations like the DAVIS-BACON Act will not apply to VEA. The terms and conditions of the utility services contract between the Government and the utility owner will apply.

1.16.4.3 Temporary Electrical Connections and Disconnections: The Contractor shall coordinate with the utility owner for all temporary connections/disconnections and distribution lines.

Any utility owner inspection and connection fees associated with requested temporary connections/disconnections to the utility owner's system must be negotiated with the utility owner and shall be the responsibility of the Contractor. The Contractor shall furnish to the utility owner a complete system layout drawing showing type of materials to be used and method of installation for all temporary electrical systems. All temporary lines shall be maintained by the Contractor in a workmanlike manner satisfactory to the utility owner and upon disconnection by the utility owner http://www.dol.gov/compliance/laws/comp-dbra.htm the area shall be restored to its original (or better) condition by the Contractor prior to final acceptance of the construction. The point of connection shall be coordinated with the Government technical representative and utility owner prior to connection.

1.16.4.4 The utility owner can be contacted at:

Kristin Mettke 800 E Highway 372 P.O. Box 237 Pahrump NV 89041 Direct: (775) 727-2164 Fax: (775) 727-2435 Email: kristinm@vea.coop

1.17 UTILITY SERVICE INTERRUPTIONS: If any utility will require interruption in service the following would apply:

1.17.1 Advance Notification: The Contractor shall submit written notification not less than 28 calendar days in advance of each interruption of each utility and/or communication service to or within existing buildings and facilities being used by others.

1.17.2 Duration: No single outage will exceed four (4) hours at a time or more than once in any two week period unless approved in writing by the Civil Engineering Customer Service Department. The time and duration of all outages will be coordinated with the Using Agency by Customer Service.

Utility outages required shall be scheduled so as to provide the minimum interference to the government. Outages shall occur on weekends and/or during non-standard work hours depending on facilities affected and Using Agency operations.

1.17.3 Clearance: No outage may begin until the Contractor has applied for and obtained an Air Force Form 103, Base Civil Engineering Work Clearance Request. The Contractor shall apply for the clearance on Nellis at Bldg 843, Civil Engineer Customer Service, and on Creech at Bldg 231, Civil Engineering. Permit application shall be submitted a minimum of four (4) weeks prior to any outage as the Air Force portion of the permit typically takes four (4) weeks to complete.

1.18 EMERGENCY MEDICAL TREATMENT: The Mike O’Callaghan Federal Hospital (MOFH) will provide emergency medical treatment to employees of the Contractor for injuries incurred while working at Nellis AFB, NV. The Contractor will be required to reimburse the Government at an established rate for non-beneficiaries in accordance with DoD Regulation

6010.15. After receiving initial emergency treatment, the Contractor will provide the hospital with the name of a physician and/or hospital to which injured personnel can be transferred for further treatment and care. Follow-on care after initial emergency treatment will not be provided. There are very limited medical services available at Creech AFB and on the NTTR.

1.19 SECURITY:

1.19.1 Physical Security: The Contractor shall provide physical security for the materials and work under his control, and shall immediately notify the Contracting Officer when equipment, material or work area is damaged.

1.19.2 Security Personnel: If the Contractor elects to provide security personnel, Contractor security personnel will not carry weapons on base (including MACE and night sticks). It is the responsibility of the Contractor to notify security police, through the Contracting Officer, of security personnel who will be in the area.

1.19.3 Communications: In accordance with Air Force Instruction 33-211, all communications with DoD organizations are subject to communications security (COMSEC) review. Contractor personnel will be aware telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. The DoD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DoD organizations. Therefore, civilian contractor personnel are advised any time they place a call to, or receive a call from, a USAF organization, they are subject to COMSEC procedures. The contractor will assume the responsibility for ensuring wide and frequent dissemination of the above information to all employees.

1.20 SAFETY AND ACCIDENT PREVENTION

1.20.1 General: Compliance with the current U.S. Army Corps of Engineers "Safety and Health Requirements Manual", EM 385-1-1; Occupational Safety and Health Act (OSHA) Public Law 1910 and 1926; Air Force Occupational Safety and Health (AFOSH) standards, and current Nellis AFB safety regulations is mandatory. The prime Contractor shall be held responsible to insure that his/her workforce and any subcontractor or supplier workforce comply with the above safety requirements.

1.20.2 Personnel Safety: Adequate protection of all persons shall be provided at all times. Work shall proceed in a manner to prevent hazard.

1.20.3 Temporary Barriers: Contractor shall install and maintain temporary barriers around construction work areas to prevent unauthorized personnel from area.

1.20.4 Road Closures/Lane Restrictions: The Contractor shall be responsible for submitting a closure/lane restriction plan to Contracting for approval at least 30 days in advance of any anticipated closure/restriction. All road closures and/or lane restrictions need to be properly advertised to base personnel and retirees which requires three weeks notice to be placed in the necessary publications. The Contractor shall be responsible for providing and placing all barricades, lighting, closure markers and safety devices during any road work.

1.20.5 Safety Briefings: Contractors operating on base will be responsible to brief and ensure their employees, subcontractors, and suppliers comply with all traffic rules and regulations, as well as entry procedures.

1.20.6 Security Police: All instructions given by Security Police personnel will be complied with immediately. All on-base traffic rules are contained in Air Force Instruction (AFI) 31-204, Motor Vehicle Traffic Supervision.

1.20.7 Equipment and Tools: Equipment to be used on the project shall be safe and in good operating condition. The Contracting Officer reserves the right to inspect any on-base equipment and reject such equipment if he considers it unsafe, in poor operating condition, or inappropriate for work.

1.20.8 Explosive Operated Hand Tools: The Contractor shall comply with OSHA (Occupational Safety and Health Act) Standard 1910.215(c) when utilizing explosive operated hand tools. Storage of explosive cartridges on the installation will be in metal containers and limited to one day’s supply.

The contractor will provide adequate controls to prevent loss/theft of cartridges used and stored on the installation. An explosive storage license must be obtained from the 99 Air Base Wing Safety Office prior to bringing explosives onto the installation as well as storing them.

1.20.9 Use of Radioactive Devices on Government Property: Under no circumstances will an unlicensed radioactive device be used on Nellis Air Force Base. Prior to using a radioactive device (i.e., soil or asphalt density meter) on government property, the contractor shall submit an application to the Contracting Officer for approval by the Base Radiation Protection Officer (99th Medical Group/SGPB). In accordance with Nellis AFB Instruction 48-101, and AF40-201 paragraph 3.4.5 the application shall be submitted forty-five (45) calendar days prior to the anticipated use and will consist of the following:

A copy of the appropriate NRC license or State Permit to operate/own the radioactive device.

A copy of the operator's qualifications and/or radiation safety training.

Radiation dosimetry results for the operator for the past calendar year.

A statement of the expected start date and the length of the contract (task order).

A statement of expected storage and security requirements or other peculiar needs of the contractor.

A statement allowing inspection of use and adherence to safety procedures by Government personnel while on base.

Copies of the last two leak tests.

1.21 FIRE PREVENTION AND PROTECTION

1.21.1 Nellis AFB Fire Regulations: The Contractor shall comply strictly with the Base fire regulations and become thoroughly familiar with and brief employees and subcontractors on the fire safety requirements applicable to this contract.

1.21.2 Welding Permit: No welding, cutting or open flame will be permitted without obtaining a Welding/Cutting/Burning Permit issued by the Base Fire Department, Bldg 277. This permit shall be requested by the Contractor a minimum of one workday prior to required need. A permit must be obtained each time any welding, cutting, or open flame is required.

1.21.3 Clean-Up: The Contractor shall at all times maintain good housekeeping practices to reduce the risk of fire damage. All scrap materials, rubbish, and trash shall be removed daily from, in, and about the site. No debris shall be permitted to be scattered on adjacent property.

1.21.4 Fire Extinguishers: The Contractor shall provide fire extinguishers in accordance with the recommendations of the base fire regulations. Proper type fire extinguisher shall be available at each location where cutting and welding is being performed.