Amendment 03. Revised Statement of Work Questions and Answers Waterline Drawings and GeoTechnical Report.
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RKXF 09-8017
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to add a revised Statement of Work dated 26 July 2010 and to incorporate the questions and answ ers, w aterline draw ings and GeoTechnical Report from the 22 July 2010 Site Visit. Additionally, the proposal due date has been extended
FROM 09 August 2010 TO 13 August 2010.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 03-Aug-2010
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X FA4861-10-R-A004
X 9B. DATED (SEE ITEM 11)
01-Jul-2010
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
03-Aug-2010
CODE
99 CONS/LGCA
5865 SWAAB BLVD, BLDG 588
NELLIS AFB NV 89191-7063
FA4861 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
FA4861-10-R-A004
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION A - SOLICITATION/CONTRACT FORM
The required response date/time has changed from 02-Aug-2010 04:30 PM to 13-Aug-2010 04:30 PM.
SECTION J – LIST OF DOCUMENTS, EXHIBITS, AND OTHER ATTACHMENTS
Changed FROM:
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 01 RKXF 09-8017, Statement of Work 38 26-MAY-2010
Attachment 02 Ehibit "A" Design Requirement 8 06-MAY-2010
Attachment 03 Nellis Design Requirements 110 01-AUG-2006
Attachment 04 UFC 3-580-01 45 22-JUN-2007
Attachment 05 UFC 3-600-01 129 26-SEP-2006
Attachment 06 UFC 4-021-01 96 09-APR-2008
Attachment 07 Section 27 10 00 36 21-APR-2009
Attachment 08 38 EIG Handbook 33-01 81 01-MAY-2005
Attachment 09 Engineer Tech Letter 25 27-JUN-2002
Attachment 10 Site Map 1 03-JUN-2010
Attachment 11 Wage Determination 6 04-JUN-2010
Attachment 12 Financial Information Request 2 03-JUN-2010
Attachment 13 Past Performance Questionnaire 8 03-JUN-2010
Attachment 14 Cost Estimate Breakdown 2 03-JUN-2010
Attachment 15 Performance Information Form 1 07-JUN-2010
TO:
DOCUMENT TYPE DESCRIPTION PAGES DATE
Attachment 01 RKXF 09-8017, Statement of Work 38 26-MAY-2010
Attachment 02 Ehibit "A" Design Requirement 8 06-MAY-2010
Attachment 03 Nellis Design Requirements 110 01-AUG-2006
Attachment 04 UFC 3-580-01 45 22-JUN-2007
Attachment 05 UFC 3-600-01 129 26-SEP-2006
Attachment 06 UFC 4-021-01 96 09-APR-2008
Attachment 07 Section 27 10 00 36 21-APR-2009
Attachment 08 38 EIG Handbook 33-01 81 01-MAY-2005
Attachment 09 Engineer Tech Letter 25 27-JUN-2002
Attachment 10 Site Map 1 03-JUN-2010
Attachment 11 Wage Determination 6 19-MAR-2010
Attachment 12 Financial Information Request 2 03-JUN-2010
Attachment 13 Past Performance Questionnaire 8 03-JUN-2010
Attachment 14 Cost Estimate Breakdown 2 03-JUN-2010
Attachment 15 Performance Information Form 1 07-JUN-2010
Attachment 16 Statement of Work 38 26-JUL-2010
Attachment 17 Site Visit Q & A 6 28-JUL-2010
Attachment 18 Waterline Drawings 4 28-JUL-2010
Attachment 19 GeoTechnical Report 19 19-NOV-2008
(End of Summary of Changes)