Site Visit Questions B190 28 Mar 22 (Amend 1).xlsx

XLSX spreadsheet 10 KB Posted

Attached to
B190, Rpr Doors, Sprinklers, VCT, Carpet, New Briefing Rm
Solicitation number
FA485522B0002
Issued by

View the file

Other files

File Type Posted
SF 1409 Abstract 20 Apr 22.pdf PDF
Site Visit Questions B190 Updated 13 Apr 22.xlsx XLSX spreadsheet
Amendment 2 - FA485522B00020002 SF 30.pdf PDF
Atch 1 SOW - CZQZ160061 6 April 22 (Amend 1).pdf PDF
A. B190 35% Revised Drawings (Amend 1).pdf PDF
Amendment 1 - FA485522B00020001.pdf PDF
B190 Site Visit Sign In 25 Mar 22 (Amend 1).pdf PDF
Solicitation - FA485522B0002-17 Mar 22.pdf PDF
C. CZQZ160061 Draft DD 1354.pdf PDF
D. CAFB Architectural Compatibilty Guide-2013.pdf PDF
C. RFI FORM Template.pdf PDF
Atch 1 SOW CZQZ160061-15 Mar 22.pdf PDF
C. AF 3065 Progress Report Template.xlsx XLSX spreadsheet
D. AEC CAD Standards 6_1-Aug 2019.pdf PDF
A. Pic 3.jpg JPG image
A. Pic 2.jpg JPG image
B. Specifications-16 Mar 22.pdf PDF
D. Contractor Base Briefing Pamphlet-Mar 16.pdf PDF
C. AF 3000 Template.pdf PDF
A. Pic 1.jpg JPG image
D. CAFBI 32-201, June 2020.pdf PDF
A. Pic 4.jpg JPG image
C. AF3064 Schedule Template.xls XLS spreadsheet
A. Existing SPRINKLER (2).jpg JPG image
A. Existing SPRINKLER (3).jpg JPG image
A. Existing SPRINKLER (1).jpg JPG image
A. B190 35% Drawings.pdf PDF
A. As-Built Riser_Diagrams_Details.pdf PDF
D. As-Built Submittal Guidelines-2014.pdf PDF
Atch 2 SOMS - CZQZ160061.xls XLS spreadsheet
D. WD_NM20220016-25 Feb 22.pdf PDF
A. As-Built Fire_Protect_Floor_Plan.pdf PDF
Show all 32

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Sheet1

FA485522B0001, B190, Repair Doors, Sprinklers, Tile Briefing Rm COR Nomination
ItemDateQuestionGov't Response
128-Mar-22Removal of hard ceiling (S128, S128A):The existing fixture are of a surface mount type and will not work for a grid ceiling. What type of fixtures are to be supplied? LED flat panel or T8, 2’X4’ or 2’X2’ troffer, 30k or 40k/ or 50k if LED, dimmable?LED 2'x4'
2S115A room enlargement: Do the light fixtures need to match the new fixtures in (S128, S128A) or match existing fixture?Match existing fixture
3Existing PDS (S128, S128A): The existing PDS is piped on the existing ceiling (to be removed and replaced with a grid ceiling). Will new PDS need to be installed or install hangers to remount the existing pipe? PDS will not be available in this area during construction.Install hangers to remount the existing pipe. Protect PDS system in place so it can remain operational.
4
5
6
7
8
9