Site Visit Questions B190 28 Mar 22 (Amend 1).xlsx
XLSX spreadsheet 10 KB Posted
- Solicitation number
- FA485522B0002
View the file
Other files
Show all 32
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| FA485522B0001, B190, Repair Doors, Sprinklers, Tile Briefing Rm COR Nomination | ||||
| Item | Date | Question | Gov't Response | |
| 1 | 28-Mar-22 | Removal of hard ceiling (S128, S128A): | The existing fixture are of a surface mount type and will not work for a grid ceiling. What type of fixtures are to be supplied? LED flat panel or T8, 2’X4’ or 2’X2’ troffer, 30k or 40k/ or 50k if LED, dimmable? | LED 2'x4' |
| 2 | S115A room enlargement: Do the light fixtures need to match the new fixtures in (S128, S128A) or match existing fixture? | Match existing fixture | ||
| 3 | Existing PDS (S128, S128A): The existing PDS is piped on the existing ceiling (to be removed and replaced with a grid ceiling). Will new PDS need to be installed or install hangers to remount the existing pipe? PDS will not be available in this area during construction. | Install hangers to remount the existing pipe. Protect PDS system in place so it can remain operational. | ||
| 4 | ||||
| 5 | ||||
| 6 | ||||
| 7 | ||||
| 8 | ||||
| 9 |
File details come from the government source that posted it. Updated .