Statement of Work Summary

This is a Statement of Work (SOW) for repair or replacement of a power divider assembly on a 2008 P-19 Oshkosh 1,500-Gallon Aircraft Rescue & Fire Fighting (ARFF) firetruck located at Moody Air Force Base, Georgia. The solicitation number is FA483026Q0063, issued by the 23d Contracting Squadron for the 23d Logistics Readiness Squadron.

The contractor must remove, inspect, and repair or replace the Oshkosh power divider (Part Number 3811870) to Original Equipment Manufacturer (OEM) standards using genuine OEM parts. The work includes comprehensive system inspection to identify and address metallic contamination and internal component failures discovered during routine maintenance, including fragmented spring assemblies and debris. The contractor is responsible for providing flatbed transportation to pick up the vehicle from Moody AFB Vehicle Management Compound (buildings 977/983) and return it upon completion, maintaining vehicle batteries throughout the repair period, replacing all damaged or out-of-specification components, resealing the unit with OEM sealants, torquing all fasteners to OEM specifications, and inspecting all connected system components including mating surfaces, internal drive gears, and threaded holes. Additional requirements include careful removal and reinstallation of body panels with proper alignment and torque specifications, hose routing and pressure testing with replacement of any damaged components at contractor expense, electrical harness routing and functionality verification, and comprehensive post-repair operational testing to ensure zero fluid or air leaks and full pump system performance.

The contractor must complete initial inspection and provide a repair course of action within 14 calendar days of vehicle receipt, with an expectation of 120 days for completion of repairs and return delivery. A 12-month warranty covering all parts and labor is required, with contractor obligation to respond to and complete warranty claims within 10 working days. This is a Small Business Set Aside (FAR 52.219-14), allowing small businesses to serve as prime contractors with experienced Oshkosh-qualified technical subcontractors, provided that no more than 50 percent of the government-paid service portion amount is subcontracted to non-similarly situated entities (those with annual revenues exceeding $9 million under NAICS 811111). Any over-and-above work discovered during inspection requires itemized pricing submission categorized by labor, labor positions, and materials for government approval prior to performance.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No.: FA483026Q0063 Contract No.:

Contract Title: Crash 15 power divider

CUI

23d Logistics Readiness Squadron

Crash 15 Power Divider Repair/Replace

Statement of Work (SOW)

Current as of: 1 2 August 2026

23d Contracting Squadron

Moody AFB, GA

STATEMENT OF WORK

Fire Truck Repair Moody AFB, GA

1. Description of Work:

1.1 Project Overview

A repair or replacement is necessary for the Flightline Crash Firetruck 2008 P-19 Oshkosh 1,500- Gallon Aircraft Rescue & Fire Fighting (ARFF), Serial Number: 10TBKAK168S104292 power divider assembly. Specifically, the proposed work includes the removal, inspection, and repair or replacement of the Power Divider assembly to OEM standards using genuine OEM par

1.2 Technical Background and Justification for Repair/Replacement During routine scheduled maintenance performed by Vehicle Maintenance personnel, a critical internal failure was identified within the vehicle's power divider. Diagnostics revealed the following discrepancies:

• Metallic Contamination: Upon draining Power Divider system fluid, substantial metallic shavings & debris were found adhered to the magnetic drain plug, indicating excessive wear or component disintegration.

• Internal Component Failure: Subsequent removal of the power divider oil pan revealed fragmented spring assemblies.

Based on these findings, a complete removal, teardown, and inspection of the Power Divider is mandatory to prevent catastrophic system failure, personnel safety mishaps, and to restore the vehicle to full-mission-capable status.

1.3 Primary Objective

The primary objective of this requirement is the complete restoration or replacement of the Power Divider to Original Equipment Manufacturer (OEM) standards. The Contractor shall ensure that all internal debris is cleared and that all failed, compromised components, and fasteners (i.e. bolts, screws, nuts, etc.) are replaced with genuine OEM parts to ensure the reliability of the ARFF mission-critical pumping and propulsion systems.

HAJEK, JAMES M TSgt USAF ACC 23 LRS/LGRV Maybe specify the Power Divider System Fluid

Does the OEM standards need to be specified? We should clarify this with 23d CONs. This is what they said in the email: “The requirement should clearly explain what needs to be repaired or rebuilt so interested contractors can understand the scope of work without already being familiar with the equipment”

1.4 Vehicle & Power Divider Specifications

The Power Divider specifications are as follows:

• Manufacturer: Oshkosh

• Nomenclature: POWER DIVIDER, OSHKOSH, SERVICE

• Part Number: 3811870

• Quantity: 1 Each

The Vehicle Specifications are as follows:

• Flightline Crash Firetruck 2008 P-19 Oshkosh 1,500-Gallon Aircraft Rescue & Fire Fighting

(ARFF)

• VIN - 10TBKAK168S104292

• Registration – 08L00862

2. Scope

2.1 Vehicle Transport

The Contractor shall provide transportation to and from Moody AFB 31699 and the Contractor’s facility for all necessitated repairs to the power divider regarding one (1) Flightline Crash Firetruck 2008 P-19 Oshkosh 1,500-Gallon ARFF, Serial Number: 10TBKAK168S104292. ATTLA attached as exhibit 1 for shipping reference. The Customer will remove spray foam from the ARFF, and will configure the vehicle to conform with safe transportation standards.

2.1.1 Vehicle Transport (Contractor Pickup)

The contractor shall provide flatbed transportation to pick up one (1) Flightline Crash Firetruck, 2008 P-19 Oshkosh Legacy 1,500-Gallon ARFF, Serial Number: 10TBKAK168S104292 vehicle from Moody AFB, Vehicle Management Compound located near buildings 977/983 and transport it to the contractor’s facility.

2.1.2 Vehicle Transport (Return Delivery)

Return transportation of the repaired 2008 P-19 Oshkosh Legacy 1,500-Gallon ARFF shall be provided by the contractor upon successful completion of testing and final inspection to: Moody AFB, Vehicle Management Compound, buildings 977/983.

2.2 Battery Maintenance

The Contractor shall maintain or disconnect the vehicle’s batteries for the entire duration the vehicle is onsite at the Contractor's facility to ensure good battery serviceability. Failure to maintain proper battery condition will require the Contractor to supply and install new replacement batteries at no additional cost to the Government.

2.3 Power Divider Repair/Replacement

The Contractor shall remove, inspect, and repair/replace the vehicle's power divider with genuine OEM parts. The Contractor shall determine the specific parts required for the repair or replacement.

This process shall include resealing the unit using Original Equipment Manufacturer (OEM) recommended sealants and torquing all bolts and nuts to strict OEM specifications. The Contractor shall replace any components that are damaged or outside of OEM tolerances with Original Equipment (OE) components; including but not limited to bolts, nuts, screws, etc.

2.4 Power Divider System Inspection

The Contractor shall comprehensively inspect every component connected to the power divider system. All mating surfaces must be verified to be free of cracks, deep scoring, or other defects.

Additionally, the Contractor shall inspect the internal drive gears within the power divider to ensure there is no damage, wear, or pitting on the gear teeth. Furthermore, the Contractor shall repair any threaded holes that are damaged or found to be out of specification during the repair process.

2.5 Body Panel Alignment and Installation

The Contractor shall carefully remove and reinstall any body panels necessitated by the repair process. All panels must be realigned, and mounting hardware must be torqued to OEM specifications. The Contractor shall ensure that all compartment doors close, latch, and seal properly following the realignment and installation of body panels.

2.6 Hose Routing and Replacement

The Contractor shall carefully remove and reinstall any hoses required to complete the repair. Upon reinstallation, all hoses shall be rerouted to their original OEM locations, properly tightened, and pressure-tested to ensure zero leakage. The Contractor shall replace, at their own expense, any hoses or fittings that are damaged, rounded, or stripped from mechanic error during the maintenance process.

2.7 Electrical Harness Routing and Functionality

The Contractor shall safely disconnect, remove, and reinstall any electrical wiring harnesses required to complete the repairs. All harnesses shall be securely routed to their original OEM locations to prevent chafing or thermal damage. The Contractor shall verify the full functionality of every electrical component and system that was disconnected during the repair phase.

2.8 Over And Above Work

Upon inspection, if additional items require repair or replacement – (Over and Above Work), the Contractor will submit itemized pricing, in writing, to the government before purchasing materials and before applying any additional labor. Pricing shall be categorized by labor, positions of labor, and materials. At that time, the government will evaluate if any or all additional labor and parts are needed, and will notify the Contractor how to proceed. Over and above work must be negotiated prior to performance of work and are within the scope of the contract. Refer to Clause 252.217-7000.

Should we specify exactly which components we want them to inspect? (i.e. Pump Drive & PTO assemblies)

2.9 Post-Repair Testing and Quality Assurance

Upon completion of all repairs, the Contractor shall perform comprehensive operational testing of the vehicle. The Contractor shall ensure there are no fluid or air leaks from any serviced component and verify that the pump system performs to OEM standards. The vehicle must be fully operational and ready to be placed into immediate service upon return to Moody AFB.

2.10 Warranty Requirements

The Contractor shall provide formal documentation for a comprehensive 12-month warranty covering all parts and labor associated with this repair. This warranty documentation must be signed, dated, and delivered upon completion of the vehicle. If a covered part or labor claim is initiated by the customer, The Contractor must respond to, initiate, and complete necessary repairs within ten

(10) working days – setting aside any parts delays.

2.11 Lead Time Requirements

Upon receipt of the vehicle, the Contractor is required to inspect the vehicle, provide Moody AFB with a repair/replacement course of action, and order necessary parts (subject to availability) within 14 calendar days. 120 days is the expectation for completion of repairs and return delivery. The Contractor shall promptly provide lead time information on status of repairs, especially if there are any delays in receiving parts or delays in delivering installation/repair requirements.

3. Deliverables: The vehicle has been restored to fully operational condition with all listed and necessary repairs completed IAW OEM standards. Contractor has performed all pre- and post-testing IAW OEM standards and ready to be placed into service.

4. Sub-Contracting: A Small-business may act as prime contractor and use an experienced Oshkosh qualified technical subcontractor to perform the specialized ARFF power-divider repair work and vehicle transportation. FAR 52.219-14 applies since this RFQ is a Small Business Set Aside. If you are subbing out more than 50 percent of the amount paid by the government for the service portion of the contract, you must use a “similarly situated” business, as in, another small business venture that also has annual revenues under $9M (per NAICS 811111). See below…

52.219-14 (e) - By submission of an offer and execution of a contract, the Contractor agrees that in performance of a contract assigned a North American Industry Classification System (NAICS) code for—

52.219-14 (e)(1) - Services (except construction), it will not pay more than 50 percent of the amount paid by the Government for contract performance to subcontractors that are not similarly situated entities. Any work that a similarly situated entity further subcontracts will count towards the prime contractor's 50 percent subcontract amount that cannot be exceeded. When a contract includes both services and supplies, the 50 percent limitation shall apply only to the service portion of the contract.

This is where you could add it “ operational IAW NFPA 1911, section … etc”