This is a Questions and Answers document responding to an RFI for Vindicator Intrusion Detection System Installation Services at Tyndall Air Force Base, Building 503.

The project involves design, procurement, and installation of a new Honeywell Vindicator-branded IDS to replace an aging system installed in 2005. The facility is approximately 2,500 square feet with concrete perimeter walls, suspended ceilings (except in Comm Room 100 and Room 208), and 100% stable power via UPS and generator backup. The contractor must provide all equipment, conduit, junction boxes, pull boxes, and new cabling infrastructure while installing in parallel with the existing system to avoid operational disruption. Installation shall comply with ICD 705 standards, IFC requirements, and DoD security directives. Key deliverables include 5 Building Management Systems (BMS), 2 access control devices with new technology, motion sensors, glass break sensors, cipher locks meeting DoD authorization requirements, and complete system programming and integration with the existing Electronic Security System (ESS). The government will provide 15 minutes of UPS support for system reporting, coordinate network connectivity through SimpleSENCE and BDOC, supply base communications for new IP addresses and switch ports, and furnish escort personnel during duty hours. The contractor is responsible for the Acceptance Test Plan with government oversight and approval, system programming, as-built documentation following government-specified naming conventions, and credential delivery via DBIDS submission process. Work access is limited to Monday-Friday, 0700-1800 hours with 14-day advance notice required (adjustable to maintain schedule if parts are available), except the 72-hour advance notice for IDS and VCC programming is non-negotiable. The estimated project completion timeline is 150 days after receipt of order, with anticipated base access approval within 10 days pending SFS requirements.

View the file

Other files for this federal contract opportunity

Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Questions & Answers Vindicator Intrusion Detection System Installation Services, Tyndall AFB, FL.

– SAM Notice ID FA481926Q0011

No.
Questions
Government Responses
1.
How old is the facility?
CSA ~1984 SAPF ~1994 with Renovation in 2023
2.
How much square footage is in the facility?
Approximately 2500 sq ft
3.
How stable is the power?
100% stable – Whole facility UPS and Generator Power
4.
Is there a dropped ceiling in all areas of installation?
All rooms with the exception of Comm Room 100 and Room 208
5.
What type of walls are in the perimeter areas?
Concrete
6.
Do we need to drill between the walls, to run our cable infrastructure?
It depends – existing holes with fire caulk – new drilling will need MAJCOM coordination/approval as long as it is IAW with 705 standards.
7.
Do we need to use conduit?
The contractor must provide all additional conduit, junction boxes, and pull boxes where required. All installation shall be IAW the approved equipment list, regulations and codes
8.
If yes, what do you estimate the total conduit footage will be?
Depends on your runs
9.
Are the door frames metal and concrete filled?
Yes
10.
Please provide a comprehensive list of quantities of all IDS items needed (e.g. total number of motion sensors, glass breaks, etc.) per location.
It will be a 1 to 1 swap. Contractor will decide if more equipment is needed to ensure complete coverage and all installation shall be IAW the approved equipment list, regulations and codes.
11.
Do you currently have existing IDS Sensors in your doors?
Yes
12.
Please specify which doors.
All exterior doors
13.
What is the manufacturer of the existing IDS system?
Honeywell Vindicator
14.
Will we be able to reuse the existing cable?
NO, must install without impact to current system
15.
Are Ceilings Suspended?
Yes, Suspended. All rooms with the exception of Comm Room 100 and Room 208
16.
Are there existing Cable Trays for wiring above ceilings?
Yes and No
17.
Can Existing Wiring be utilized?
NO
18.
Is a “UPS” required?
Yes but depending on Manufacturer requirements, please see approved listed attached in sow. Building will always have electricity.
19.
If so, What Time/Power Duration is required?
15 minutes to fully support the system and reporting
20.
Are “Or Equal” Equipment substitutions allowed?
Depending on which equipment, IAW approved list attached and must be legal.
21.
Is “Plenum Wire” acceptable?
Depends on manufacturer requirements IAW approved list attached.
22.
Is “After Hours Access” for said work, available to contractor at no add’l cost to the Gov’t?
NO, see SOW for hours. During burn-in a technician should be in local area to respond.
23.
What is the height of Exterior Cameras? (If any)
N/A (none required)
24.
Please provide/post other “Q & A” requests.
Yes
25.
Please provide a list of equipment and parts # that are to be installed.
All items on SOW are suggested and approved from gov’t.

· 5 BMS

· 2 access control devices with new technology IAW IFC (eg strike or mortis) See attachments 2 and 3 for 1-1 swap and at the contractor's discretion as area needs to be ADEQUATELY covered (new solutions are ok).

26.
Are there pipe chases between floors?
Single floor only
27.
What is the range of the budget for this project, and is it already appropriated?
Cannot answer this question
28.
Because of the high cost of the parts can we bill when parts arrive on site, or in the alternative are progress payments allowed?
No
29.
How many feet of new wire will have to be run?
Depends on how your company designs the system. As-builts are provided in SOW with intended locations for the hardware to be installed
30.
What kind of cipher lock and quantities are required e.g. X-10 Newest Authorized by DoW
Newest Authorized by DoW, meeting 705 and 1404 requirements.
31.
Please post the sign in sheet and Q&A's from the site visit.
posted
32.
Please post the drawings and the key for the drawings.
Listed in SOW
33.
Will Base Communications have network pathways built/configured for the new systems?
Coordinate with simpleSENCE & BDOC to plug into OT switch.
34.
Will Base Communications provide new IP addresses assigned for this project with prior coordination and provide the switch with at least 6 available ports (2 in open storage, 4 in SCIF)?
NOT A SCIF, it’s a SAP Annex. Will need coordination with simpleSENCE & BDOC.
35.
Will Base Communications personnel install conduit and data cabling from communications closets to the new panel locations?
No
36.
If the vendor is responsible for new data connections, are there specified cable color coding standards that must be followed?
No as long as its within cable rules and IAW security directives and instruction
37.
What is the distance between the electrical panel source and each new panel installation location?
It depends. Contractor to provide solution.
38.
Is the new security installation required to comply with ICD 705 for all wiring and conduit?
Yes
39.
Are all wired junctions required to include tamper protection?
Yes
40.
Is the use of JB Weld (or an equivalent) required for securing all conduit connections?
As long as it complies with approved list
41.
Will the ESS section provide all additional alarm points required to meet installation requirements?
Yes
42.
Will you waive the 72-hour prior notice request to the vendor to the ESS section for preprogramming activities?
No
43.
Will the vendor have access to existing ACS programming, or will this information be provided by the government?
Yes, requires comms approval
44.
Is the vendor responsible for all system programming and setup, or will ESS handle any portion of the configuration?
Yes, installation and programming.
45.
The SOW states that advance requests are required for access to ESS and the installation site; Will the vendor be allowed to request specific blocked dates and times for access?
Yes, and access will have to be approved by customer – normal duty hours
46.
Is the 14-day advance notice requirement for site access still mandatory for all personnel, and can this be adjusted to avoid project delays?
Adjustable to keep on timeline if all parts are available
47.
Will the 72-hour advance notice requirement for IDS and VCC programming be flexible to accommodate testing and necessary adjustments during installation?
No
48.
What is the current ESS/BDOC firmware or system version in use?
Yes, we will provide upon award.
49.
Due to space constraints with parallel systems, would the end user consider a phased installation approach (e.g., panel configuration completed first)?
It depends – This is a new independent system installed separately from current system. User will make additional space available as required depending on need (plenty of available space).
50.
Will a SAW or separate V5 system be provided for the new installation, given that SCIF systems cannot reside on open storage systems, or is the vendor responsible for providing this?
Contractor will provide equipment, it's not a SCIF
51.
Will DBIDS include including weekend coverage for the one-year warranty support period, to meet emergency service requirements as outlined in Section 1.2.1?
DBIDS only cover the installation period – any warranty work will require additional coordination for base access.
52.
What is the expected project completion timeline?
Estimated completion by 150 days ARO.
53.
Can the Government provide additional details on the current ESS architecture and BDOC head-end configuration?
No
54.
Are there any known limitations to integrating new PCUs and Site Commanders into the existing system?
No
55.
Will the Government provide access to existing system configuration files or databases?
Yes, as required after receipt of award
56.
Can the Government provide the current Honeywell Vindicator firmware versions to ensure compatibility?
Yes, we will provide upon receipt of award
57.
Can the Government confirm whether the V3 platform can support the number of additional IDS sensors required, given the Premise Controller point limitations?
Vendor shall provide new parallel installation. Replace and then remove – system can not be shut down at any time.
58.
Can the Government confirm whether tamper circuits must remain discrete, or if a multistate configuration within the Honeywell Vindicator system is acceptable?
Listed IAW ICD 705 and 1404
59.
Can the Government confirm that existing penetrations through the concrete envelope may be reused for this effort?
On a non-interference basis and at no risk to current system. New penetrations shall require MAJCOM approval
60.
Can the Government confirm that there is no motion alarm system located beneath the raised floor?
No motion sensor beneath the raised floor
61.
Will the Government be responsible for provisioning the new system?
No
62.
Can the Government confirm that the existing badge readers are HID or equivalent and compatible with the proposed Honeywell system, and that they will not be covered under warranty?
Treat like new build system w/ new badge readers required, no repurposed parts
63.
Will the Government be responsible for all required connections to BDOC?
Yes, coordination through simpleSENCE will be required. Government will connect.
64.
Are there any asbestos or hazardous material concerns in Building 503?
No - all hazardous materials have been remediated in the facility.
65.
Will the Government provide access to existing conduit pathways, or should the Contractor assume new conduit runs?
Yes, new conduit will be required. All installation shall be IAW the approved equipment list, regulations and codes
66.
Does the existing conduit have enough spare capacity for new cabling, or should the Contractor assume replacement?
Assume replacement if required
67.
For Rooms 205/206 and 119, where walls were removed, is the Government amenable to reinstalling only one PIR per room?
Only if sufficient coverage is realized. Rooms 205/206 and 119 should have a one for one replacement. Rooms 100 and 208 require a mounting solution that does not require a suspended ceiling.
68.
Should the Contractor install a new ceiling grid to permanently affix components?
Rooms 205/206 and 119 should have a one for one replacement. Rooms 100 and 208 require a mounting solution that does not require a suspended ceiling. Replacement required if damaged by contractor.
69.
What are the expectations for maintaining continuous IDS coverage during installation?
Ensure full system control and coverage with current IDS until the new system is certified, approved, and released to the customer.
70.
Are temporary systems or phased cutovers required?
No - current system will provide coverage until the new system is in place and certified.
71.
Are there blackout periods or operational constraints?
No access outside of normal business hours; Monday through Friday 0700-1800 Access will not be allowed on Weekends, Holidays, and/or Goal days
72.
Will the Government provide a formal Acceptance Test Plan (ATP), or must the Contractor provide one?
Contractor will provide test plan with government oversight and approval
73.
Who is the approval authority for verification testing, Government acceptance, and 72-hour burn-in?
3- part approval required:

Alarm

CDN

End User

74.
Can the Government clarify interface requirements between the IDS and ACS V3?
Yes, after receipt of award
75.
Will ACS programming changes be required?
Yes
76.
Are RMF or ATO requirements applicable?
Yes, in coordination with SimpleSENCE
77.
Will the Government guide network accreditation and authorization?
Vendor will provide test plan with government oversight and approval
78.
Are specific naming conventions or CAD standards required for as-builts?
Yes, will be provided after award and in coordination with SimpleSENCE
79.
Should credentials be delivered in a secure, specific format?
Yes. Follow DBIDS submission process
80.
Can the Government provide any existing as-built drawings?
Check updated SOW for new as-builts
81.
What is the expected Period of Performance?
Estimated completion by 150 days ARO
82.
Are there known long-lead items?
Vendor to identify long lead times for items
83.
Will sales tax be required?
Sales tax for products delivered under this may be waived with exemption
84.
What is the anticipated timeline for base access approval?
Typically,10 days and IAW SFS approval requirement
85.
Will the Government issue a DD254 to allow SCI/SAP-eligible personnel to work unescorted?
CI/SAP-eligible personnel will be preferred but not required
86.
If no DD254 is issued, will escorts be required, and who will supply them?
Escorts will be required as necessary; Gov’t will provide escort personnel during duty hours