SOW BAK-12 Clutch Repair Kits_06-Feb-26.pdf
PDF 215 KB Posted
- Attached to
- Clutch Repair Kits
- Solicitation number
- FA481926Q0001
About this file
This is a Statement of Work for the Air Force Civil Engineer Center (AFCEC/COMX) at Tyndall Air Force Base, Florida, dated 6 February 2026, requiring the production and delivery of 60 Barrier Arresting Kit (BAK)-12 Clutch Repair Kits. The contractor must furnish all required parts, equipment, material, freight, and labor to meet applicable codes, specifications, and industry/federal standards. The kits consist of eight component parts identified by specific drawing numbers: a repair kit (200037000), backing plate (200037001), pressure plate (200037002), stator plate (200037003), rotor plate assembly (200037004), rotor core (200037005), friction pad (200037006), and rivet (200037007). All assemblies must be new with no refurbished parts.
The contractor must satisfy one of two qualification pathways: possess existing FAT (First Article Testing) approval from the Air Force Life Cycle Management Center (AFLCMC) with successful production unit deliveries within three years prior to solicitation issuance, or successfully complete the FAT requirements outlined in the statement. For those pursuing FAT, the contractor must submit PDF drawings to AFCEC/COMX within 60 calendar days of contract award, deliver the first article within 180 calendar days of government drawing review, and obtain approval no later than 285 calendar days after award. Additional requirements include adhering to ASME standards Y14.1 and Y14.5 for design and tolerances, producing CAD drawings, utilizing water jet or laser cutting systems for precision parts, and following American Welding Society (AWS) D1.1 standards with certified welders and inspectors. The contractor must coordinate delivery 30 days in advance to AFCEC/COMX, 1001 Mississippi Road, Building 1141, Tyndall AFB, FL 32403, and equipment with structural, component, or excessive paint damage will be refused.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
6 February 2026
AFCEC/ COMX
Barrier Arresting Kit (BAK) -12 Clutch Repair Kits
Statement of Work
1. PURPOSE: The contractor shall furnish all required parts, equipment, material, freight, and labor to provide the following items in accordance with all applicable codes, specifications, and industry/federal standards to CEMIRT, AFCEC/COMX at Tyndall AFB, Florida.
2. SCOPE OF WORK: Prior to production of the required 60 each clutch repair kits; the contractor shall meet the requirements of either paragraph 2.1. or paragraph 2.2 of this Statement of Work. The contractor shall conform with all requirements of this Statement of Work, applicable codes, specifications, industry standards, and federal standards. The contractor is responsible for providing all required equipment, material, labor, and parts required.
2.1 The offeror shall possess FAT approval from the Air Force Life Cycle Management Center (AFLCMC) as an authorized vendor to source, produce, and supply the BAK-12 Clutch Repair Kits, and have successfully delivered production units within the last three
(3) years of the solicitation issuance date; or
2.2 Successfully complete the First Article Testing (FAT) requirements in accordance with the requirements of paragraph 4 of this Statement of Work, FAR clause 52.209-4 First Article Approval-Government Testing, and:
2.2.1 Adhere to the strict specifications, tolerances, codes, standards, and notes within USAF drawings (reference paragraph 3 of this Statement of Work)
2.2.2 Produce computer-aided design (CAD) drawings and comply with documentation practices per American Society of Mechanical Engineers (ASME) standard Y14.1, unless otherwise noted by AFCEC/COMX
2.2.3 Have all necessary tools, equipment, personnel, facilities, etc. to produce or acquisition parts, components, or hardware associated with BAK-12 Clutch Repair Kits.
2.2.4 Fabricate or acquisition parts, components, or hardware to specific dimensions and tolerances per ASME Y14.5
2.2.5 Fabricate or acquisition precision parts from large sheets of steel material with a water jet or laser cutting system. These parts will not be cut utilizing free hand methods.
2.2.6 Follow welding and inspection processes in accordance with American Welding Society (AWS) D1.1 for critically loaded structures. Additionally, welders and inspectors shall be certified in accordance with AWS D1.1.
3. TECHNICAL REQUIREMENTS: The detailed work required is to provide 60 new BAK- 12 Clutch Repair Kits. Each assembly must meet the specifications and notes within the following (attached) drawings and will not include any refurbished parts:
3.1 Parts Kit, Clutch
3.1.1 NATIONAL STOCK NUMBER (NSN): 3010-01-490-6666
3.1.2 PART NUMBER (P/N): 200037000-1
3.1.3 QUANTITY: 60 each
1557639663A Highlight
1557639663A Highlight
1557639663A Highlight
3.1.4 DRAWINGS: eight (8) attachments
3.1.5 Repair Kit, Clutch Drawing #: 200037000
3.1.6 Backing Plate, BAK-12 Clutch, Drawing #: 200037001
3.1.7 Pressure Plate, BAK-12 Clutch, Drawing #: 200037002
3.1.8 Stator Plate, BAK-12 Clutch, Drawing #: 200037003
3.1.9 Rotor Plate Assembly, Drawing #: 2000037004
3.1.10 Rotor Core, Drawing #: 200037005
3.1.11 Friction Pad, Drawing #: 200037006
3.1.12 Rivet, Drawing #: 200037007
3.2 Provide revised drawings that consolidate and fix any discrepancies.
3.3 Drawings must be approved by AFCEC/COMX prior to starting any work.
3.4 Upon approval of the drawing package, the drawings will become Air Force property.
The drawings will be used by the sole discretion of the Air Force and AFCEC/COMX.
4. FIRST ARTICLE TESTING (FAT):
4.1 Completion of the FAT process shall be required for any contactor that:
a. Does not possess FAT approval; and
b. Has not delivered production unit(s) within the last 3 years of the solicitation issuance date.
4.2 The first article shall be in accordance with the scope of work, and all applicable drawings, technical specifications, engineering and special instructions.
4.3 The FAT process shall be coordinated through AFCEC/COMX to meet the form, fit, function, and configuration conformity requirements. FAT Approval shall be obtained no later than 285 calendar days after contract award.
4.4 The contractor shall submit PDF file drawings to AFCEC/COMX within 60 calendar days after contract award. The government review will be completed within 15 calendar days of receipt of a complete drawing submission.
4.5 Contractor submission of the first article for the form, fit, function, and configuration conformity check in accordance with the following:
4.5.1 Contractor shall be responsible for delivering the first article to the address below, clearly marked with “First Article Test Exhibit” no later than 180 calendar days after receipt of government drawing review.
4.5.2 The first article will be considered “submitted” to the government on the date it arrives at AFCEC/COMX, Tyndall AFB, FL.
4.5.3 The contractor shall submit a copy of all applicable drawings, specifications, engineering instructions, certifications, and inspection sheets.
4.5.4 AFCEC/COMX will not accept any third-party results initiated, provided, or completed externally to the government. (except for para 4.6.1.1 and 4.6.1.2)
4.5.5 In the event the contractor submits the first article prior to 180-day suspense after receipt of Government drawing review, the contractor may use the remaining time to correct any deficiencies (if required) noted during the FAT.
4.6 Upon Government receipt of the initial first article, AFCEC/COMX will perform the form, fit, function, and configuration conformity check within 30 calendar days to verify all operational and configuration aspects of the first article.
4.6.1 In the event that the initial first article has deficiencies; the contractor shall assume responsibility for all costs associated with required third party verification to be conducted at the government designated facility. Government approval of the third party utilized must be obtained prior to the conduct of any third-party lab verification of all characteristics of items to include dimensions, materials, welds, hardware, and components. Upon receipt of the third party verification data, the Government will perform visual inspection, inspection of material certifications, inspection of welder’s certifications, and inspection of shipment invoices.
4.6.1.2 If the contractor fails any verification inspection, the contractor shall be responsible for all expenses associated with correcting the first article deficiencies, and any additional third-party verification inspections required to be conducted at the government designated facility, to include freight to/from Tyndall AFB, FL and the contractor’s facility.
4.6.1.3 AFCEC/COMX shall coordinate with the LSE Air Force Aircraft Arresting System Engineer to obtain rejection, conditional approval, or approval of the first article and must provide this documentation to the contracting officer.
4.7 The approved and conditionally approved first article shall be retained by the government for use. Retention of this item will qualify as the first production item.
5.0 DELIVERY/SHIPPING REQUIREMENTS
5.1 The contractor shall coordinate with the POCs below 30 days prior to delivery and will utilize the following address:
AFCEC/COMX
1001 Mississippi Rd; Bldg. 1141 Tyndall AFB, FL 32403
5.2 Any BAK-12 Clutch Repair Kits with structural, component, or excessive paint damage received during shipment will be refused. AFCEC/COMX is the authority to refuse equipment but will provide documentation to the contracting officer.
mailto:jason.frigon.2@us.af.mil mailto:gary.szekely.2@us.af.mil mailto:grant.kincaid.2@us.af.mil 1557639663A Highlight