Attachment 1 - SOW Honor Guard XLWU 21-8120 Sept 2022 - Rev C.docx

DOCX document 356 KB Posted

Attached to
Construct Honor Guard Facility
Solicitation number
FA481922R0032
Issued by

View the file

Other files

File Type Posted
Solicitation Amendment FA481922R00320004 SF 30.pdf PDF
Attachment 27 - Appendix S - Location of Primary Transformer.pdf PDF
Solicitation Amendment - FA481922R00320003.pdf PDF
Attachment 1- APPA Honor Guard XLWU 21-8120 - Sep 2022 - Rev D.pdf PDF
Solicitation Amendment FA481922R00320003 SF 30.pdf PDF
Attachment 21-XLWU 21-8120 Honor Questions and Answers Rev C - 30 Aug 2022.xlsx XLSX spreadsheet
Attachment 26 Electrical Lines.pdf PDF
Solicitation Amendment FA481922R00320002 SF 30.pdf PDF
Attachment 25 - FRCS Guide 22 Sept 2021.pdf PDF
Attachment 22 - APPA Honor Guard XLWU 21-8120 - Aug 2022 - Rev C.docx DOCX document
Attachment 23 -XLWU 21-8120 Site Utilities.pdf PDF
Attachment 24- 2022_0630_TAFBHonorGuard_ExEquip.pdf PDF
Solicitation Amendment - FA481922R00320002.pdf PDF
Attachment 19 Section L and M v2.pdf PDF
Solicitation Amendment - FA481922R00320001.pdf PDF
Solicitation - FA481922R0032.pdf PDF
Attachment 11 AF Form 3000.pdf PDF
Attachment 17 AF Form 813 Honor Guard Facility.pdf PDF
Attachment 7- SITE PLAN A Rev A.pdf PDF
Attachment 2 - Floor Plan 813 Construct Honor Guard Facility Rev A.pdf PDF
Attachment 4 - Conceptual A Construct Honor Guard Facility Rev A.pdf PDF
Attachment 15 Base Access Request EAL.xlsx XLSX spreadsheet
Attachment 14 Sample RFI.PDF PDF
Attachment 5 - Conceptual B Construct Honor Guard Facility Rev A.pdf PDF
Attachment 10 AF Form 66.xlsx XLSX spreadsheet
Attachment 20 Wage Determinations.pdf PDF
Attachment 1 SOW Honor Guard XLWU 21-8120 - Jun 2022 - Rev A.pdf PDF
Attachment 3 - COAs 813 Construct Honor Guard Facility Rev A.pdf PDF
Attachment 16 Proof of Financial Responsibility.pdf PDF
Attachment 19 Section L and M 21.pdf PDF
Attachment 13 AF3065.pdf PDF
Attachment 6 - HG Topo Area Rev A.pdf PDF
Attachment 18 Division Cost Estimate Worksheet.xlsx XLSX spreadsheet
Attachment 12 AF 3064.pdf PDF
Attachment 9 - Other Contract Requirements.pdf PDF
Attachment 8 - SITE PLAN B Rev A.pdf PDF
Show all 36

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

XLWU-21-8120

01 Sep 2022 Scope of Work For Honor Guard Facilities

TYNDALL AFB, FLORIDA

Project Number: XLWU 21-8120

TABLE OF CONTENTS

1.0 SCOPE OF WORK5
1.1 GENERAL REQUIREMENTS6
1.2 APPLICABLE DOCUMENTS10
2.0 GOVERNMENT PROPERTY INCLUDING GOVERNMENT FURNISHED INFORMATION, EQUIPMENT, AND PROPERTY (GFI, GFE, GFP)16
3.0 MANAGEMENT, PLANNING, AND REPORTING REQUIREMENTS16
4.0 SUBMITTAL FORMAT AND TIMING AND DESIGN17
4.1 Preliminary Design18
4.1.1 Site Visits:18
4.1.2 Pre-Design and/or Design Review:18
4.2 Project Design Phase18
4.2.1 Design Data:18
4.2.2 35% Initial Design Data Review/Comment:18
4.2.3 100% Design for Construction Review/Comment:18
4.2.4 100% Final Design with Red Line Changes (As-Build):19
4.3 Projected Design Timeline:19
4.4. Design Distribution:20
4.5 Government Review:20
4.5.1 Contractor Response to Review Comments:21
4.6 Verification of Existing Conditions and Site Survey21
4.6.1 Field Measurements:21
4.6.2 Site Survey21
4.7 Designer of Record:22
4.8 Contract Drawings:22
4.8.1 Drawing Standards:22
4.8.2 Primary Drawing List22
4.8.3 35% Initial Design:22
4.8.4 NONE22
4.8.5 100% Design for Construction:2322
4.8.6 100% Complete Design with Red Line Changes:23
4.9 Submittals23
4.9.1 WORK BREAKDOWN STRUCTURE (WBS)27
4.9.2 SCHEDULE AND PLANNING REQUIREMENTS27
4.9.3 PROJECT PLANNING CHART (PPC) and/or CONSTRUCTION PLANNING CHART (CPC)27
4.9.4 INTEGRATED MASTER SCHEDULE (IMS)27
4.9.5 CONTRACT PROGRESS SCHEDULE (AF 3064)27
4.9.6 CONTRACT PROGRESS REPORT (AF 3065)27
4.9.7 SUBMITTING SCHEDULES AND REPORTS28
4.8 STATUS REPORTING28
4.9 REPORTING REQUIREMENTS FOR FIRM FIXED PRICE (FFP)28
4.10 CONTRACTOR’S PROGRESS, STATUS, AND MANAGEMENT REPORT (CPSMR)28
4.11 HEALTH AND SAFETY PLAN (HSP) OR (APP)28
4.12 QUALITY SYSTEM PLAN (QSP)28
5.0 MEETING, CONFERENCE/TELECONFERENCE REQUIREMENTS29
5.1 RED ZONE MEETING29
6.0CONTRACTOR DOCUMENTATION30
6.1 NOTIFICATION REQUIREMENTS31
6.2 PERMITS31
6.3 PHOTO DOCUMENTATION33
6.4 PROJECT DATA/PROJECT DELIVERABLES34
6.5 PROTECTING UNCLASSIFIED DoD DATA34
6.6 SECURITY BREACH NOTIFICATION34
6.7 DATA COLLABORATION SITE34
6.8 CONSTRUCTION WORK PLAN34
6.9 TECHNICAL REPORTS34
6.10 TECHNICAL PLANS AND REPORTS34
7.0 SITE ACCESS BADGES34
8.0 WORKSITE ACTIVITIES AND COORDINATION36
8.1 REMOTE and/or AUSTERE SITES36
8.2 COORDINATION OF ACTIVITIES36
8.3 RADIOLOGICAL WASTE, HAZARDOUS MATERIAL AND HAZARDOUS WASTE PERMITTING AND REPORTING36
8.4 HAZARDOUS MATERIAL AND HAZARDOUS WASTE36
8.5 ENVIRONMENTAL PROTECTION37
8.6 ENVIRONMENTAL PERMITS37
8.7 NATIONAL ENVIRONMENTAL PROTECTION ACT (NEPA)38
8.8 ENVIRONMENTAL PROTECTION PLAN (EPP)38
8.9 FUEL TANKS38
8.10 AIR QUALITY38
8.11 HAZARDOUS WASTE39
8.12 HAZARDOUS MATERIAL INVENTORY AND TRACKING40
8.13 PETROLEUM, OILS AND LUBRICANTS (POL)/TANKS41
8.14 RECYCLING41
8.15 STORAGE42
8.16 DIGGING/EXCAVATION42
8.17 LEAD AND ASBESTOS42
8.18 RECORDING AND PRESERVING HISTORICAL AND ARCHEAOLOGICAL FINDS42
9.0 PROSECUTING THE WORK43
9.1 COMMISSIONING AGENT44
10.0 SITE WORK44
10.1 SITE CONTROL44
10.2 UTILITIES (EXISTING)45
10.3 LOCATES45
10.4 OUTAGES45
10.5 DEMOLITION46
11.0 CONSTRUCTION OPERATION SERVICES47
11.1 CONSTRUCTION47
12.0 INSPECTIONS48
12.1 PRE-FINAL INSPECTION49
12.2 FINAL INSPECTION49
12.3 DELIVERY AND WARRANTY49
13.0 DEMOBILIZATION51
13.1 EMERGENCY RESPONSE52
13.2 MAINTENANCE AND REPAIR52
13.3 ORDNANCE REMOVAL AND SUPPORT52
13.4 SECURITY REQUIREMENTS52
13.5 GENERAL SAFETY REQUIREMENTS52
13.6 GENERATED REFUSE55
14.0 FACILITY CONSTRUCTION PROJECT DELIVERY METHODS56
14.1 DESIGN-BUILD (D-B)56
14.2 DESIGNER OF RECORD (DOR)/DESIGN PROJECT MANAGER (PM)57
14.3 CONTRACTOR DESIGN REQUIREMENTS AFTER AWARD57
14.4 USER REQUIREMENT DESIGN MEETING59
14.5 GEOTECHNICAL/HAZARDOUS MATERIAL SURVEY REQUIREMENTS AND RESPONSIBILITES59
14.6 SOIL SURVEY REQUIREMENTS AND RESPONSIBILITIES FOR CONTRACTOR59
15.0 GENERAL DESIGN REQUIREMENTS62
15.1 GOVERNMENT DESIGN REVIEW67
15.2 AS-BUILT DOCUMENTATION68
15.3 RESPONSIBILITY FOR ERRORS OR OMISSIONS71
16.0 ARCHITECTURAL AND STRUCTURAL71
16.1 BASE WIND SPEED REQUIREMENTS71
16.2 HVHZ WINDOWS AND STOREFRONTS PERFORMANCE REQUIREMENTS72
16.3 DESIGN FLOOD ELEVATION73
16.4 ROOF ACCESS73
16.5 EXTERIOR AND INTERIOR DOORS INCLUDING OVERHEAD/SECTIONAL73
17.0 STRUCTURAL INTERIOR DESIGN (SID) DESIGN SUBMITTALS74
18.0 LIGHTING:75
19.0 PLUMBING:75
20.0 MECHANICAL75
20.1 HVAC CONTROLS75
20.2 VAVs77
20.3 METERING77
21.0 POINTS OF CONTACT (POCs)78
APPENDICES79

1.0 SCOPE OF WORK

A. This is a Design-Build project to provide a new Honor Guard facility for Tyndall Air Force Base, Florida. The project is comprised of the design and construction work required to result in a complete and useable Honor Guard facilities on Tyndall AFB.

a. BUILDING SCOPE – GENERAL DESCRIPTION

i. Construct a new facility approximately 3,2504200 SF

1. Standing Steam Roof

2. With all utilities connections

3. Tyndall AFB IFS compliant finishes and color scheme.

ii. Pavement to support training 4732 SF (option), otherwise approximately 4732 SF level turf training area

iii. Parking will be approximately 8192 SF

iv. Estimated elevation of the site is 15-16 feet above sea level. The facilities must be elevated to a 19-foot design flood elevation and at least 1 foot above roof grade.

v. Upgrade existing storm water pond and storm system

vi. Move all utilities that are beneath the site of the facility

A. The Design-Build Team will consist of a Construction and design team Designer of Record (DOR) that shall perform the services herein and as described in this Statement of Work (SOW).The Contractor shall be responsible for all professional services, A/E design, permits, equipment, labor, tools, materials, and ancillary items necessary to complete the tasks defined by the SOW, including the disposal of all resulting waste materials and project clean up. The performed tasks shall be based on the project description, other data furnished in this SOW, and information covered during kick-off meeting.

B. Ancillary items: Providing necessary support to the primary activities or operation of an organization, institution, industry, or system. An example of ancillary item: Lighting controls, but is not limited to the following: switches, motions sensors, and dimmers, ballasts, emergency backup controls, etc. An incompatible dimmer or electronic equipment replacement to support a conversion from fluorescent to LEDS lights would fit the ancillary item description. Another example is Pump controls but is not limited to the following: Starters, on and off switches, logic controllers. This is all support equipment to ensure the task is completed. Roofs: All required items required by regulations code to complete the installation of a roof system such as detection, fire protections, etc. All of these items must result in a complete and usable product at completion of the project to ensure all the previous functionality was provided in the new design.

C. This SOW sets forth the requirements for Design/Build (DB) contract site-specific design and construction effort to remove, repair and restore interior and exterior elements and related infrastructure within a building on Tyndall AFB, Florida.

1.1 GENERAL REQUIREMENTS

A. Applicable provisions of the Contract Clauses in the contract will govern work under each section of the UFGS specifications.

B. This project has an estimated period of performance from Notification to Proceed (NTP) through completion and turnover of the facility back to the Government for mission operations of 331 476 calendar days.

C. Proposal Documents: The contractor shall complete the proposal schedule included in the solicitation and include the completed schedule with the submitted proposal documents.

D. Measurements: The GC is required to validate dimensions and quantities. The quantities are listed as approximations and GC field measurements and quaintly verification should be used for bidding package.

E. Field Changes:

a. Field Changes: The Contractor and the Government may agree to perform a no cost field change. Field changes are made when the change appears to be mutually beneficial to all parties and would not require changing the negotiated items. All field changes must be approved by the CO prior to execution. Only the CO may authorize field changes or deviations from the SOW.

b. No order, statement or direction of the Contracting Officer, an authorized representative of the Contracting Officer whether acting within the limits of his authority, or any other representatives of the Government, shall constitute a change order under the “Changes” clause of this contract or entitle the contractor(s) to an equitable adjustment of the price or delivery schedule, unless such a change is issued in writing and signed by the Contracting Officer.

F. Job Start Meeting: A job start meeting shall be accomplished with the Contractor, Contracting Officer, CE, and user upon acceptance of the 35%, 65%, or 100% design submission. The meeting objective is to review project details, determine design delivery dates and anticipated construction start date, security procedures for site, dumpster locations, and any applicable requirements during construction. The Contractor shall visit the job site to verify location, conditions, and dimensions prior to starting work.

G. Pre-Construction Meeting: A preconstruction meeting shall be held when all the design has reached the Issued For Construction (IFC) stage and all preconstruction submittals have been approved. The contractor Quality Control Manager, Site Safety Officer, and Superintendent shall be required to attend. This meeting will address all items specific to the project to include access, safety, and environmental needs.

H. Facility Occupancy: NA

I. Bulletin Board: Immediately upon mobilization, the Contractor shall provide a bulletin board not less than 36 by 48 inches (915 by 1220 mm) in size for displaying various documents required within the contract. The bulletin board shall be located at the project site in a conspicuous place easily accessible to all employees. All documents posted shall be legible and replaced as needed when unreadable. The board shall be displayed until the work is completed whereby the Contractor shall remove the board and remain the property of the Contractor. The contents of the board shall include, but not limited to, the following:

a. Contractor’s company name

b. Project name

c. MPLS number

d. Superintendent’s name and a 24-hour available response phone number

e. Equal Employment Opportunity poster

f. Wage determination

g. Wage Rate Information poster.

h. Other documents as needed or required.

J. Employee Parking: Contractor employees shall park privately owned vehicles in an area designated by CES and approved by the CO.

K. Job Site Tools and Equipment: All hand tools and equipment shall be maintained in good working conditions and properly stored when not in use. Construction attire shall be in accordance with applicable OSHA regulations.

L. Field Measurements: The Contractor shall be required to make his/her own field investigations to verify existing conditions, dimensions and other information shown on Government available non-verified furnished reference drawings, solicitation documents and construction documents. Deviations, errors, or omissions in the government supplied reference materials or the design team’s construction documents shall be identified and addressed by the contractor during the design phase of the contract. They shall be annotated on the respective contract documents as well as on a consolidated register that will be made available to the government for simplified identification and review.

M. Notification Requirements: The Contractor shall notify the Government a minimum of ten (10) days in advance of each mobilization. The Contractor is required to notify the CO and Government Project Manager of critical issues that may affect the contract performance and/or human health and the environment. For critical issues pertaining to human health and the environment, the Contractor shall immediately notify the CO and stop work. Work shall only resume at the direction of the CO following resolution of the issue.

N. On-Site Field Oversight: The Contractor shall provide the manpower, equipment, material, services, and transportation necessary to ensure oversight services throughout accomplishment of the construction period for the contract. It is the responsibility of the Contractor to establish and maintain open communications between salient authorities associated with accomplishment of this contract.

O. Federal Holidays:

a. The standard Federal legal holidays are observed:

1. New Year’s DayJanuary 1
2. Birthday of Martin Luther King, Jr.Third Monday in January
3. Washington’s Birthday / President’ DayThird Monday in February
4. Memorial DayLast Monday in May
5. JuneteenthJune 19
6. Independence DayJuly 4
7. Labor DayFirst Monday in September
8. Columbus DaySecond Monday in October
9. Veterans DaySecond Monday in November
10. Thanksgiving DayFourth Thursday in November
11. Christmas DayDecember 25

b. Any of the holidays falling on Saturday will be observed on preceding Friday; holidays falling on Sunday will be observed on the following Monday. In addition, the Government may dictate the workday before or the workday after an observed holiday as a “Family Day.”

c. The Contractor should not perform work on observed holidays, Wing Down Days, Wing Safety Days or Family Days unless authorized by the Contracting Officer for the TO. In the event work is authorized on observed holidays, the Contractor shall pay all applicable overtime and/or holiday pay rates required by law.

P. Working Hours: The normal duty hours of the facility are from 7:00 AM to 5:00 PM, Monday thru Friday excluding Federal Holidays. All work shall be performed during normal duty hours. All other hours to include weekend and holidays shall be requested through the CO for approval. This request shall be submitted no less than three (3) workdays prior to the time requested.

Q. Availability and Use of Utility Services:

1. The contractor should plan on having an offsite office location. The government does not guarantee office space will be provided. The Government does not guarantee utilities will be provided for office space. The use of a generator and porta toilets may be required of office space is provided. To install and office space and laydown yard will require an 813 Permit determination and could take up to 60 days to obtain the permit.

2. The Contractor shall coordinate with Contracting Officer's Representative (COR) for laydown area, offices, and parking and storage facilities. Any damage to existing improvements adjacent to or on the project site due to construction activity under this contract shall be replaced/repaired at the Contractor's expense. All Contractor POV parking areas shall be coordinated and approved in advance by the Contracting Officer's Representative.

3. Construction sites shall be kept neat and free of trash. Site construction areas shall be surrounded with orange, plastic safety barrier fence when required to separate construction activities from daily personnel traffic.

R. Sanitation: The Contractor shall provide and maintain within the construction area minimum field-type sanitary facilities approved by the CO. Government toilet facilities will not be available to Contractor's personnel.

S. Clean Up: At the end of each working day the Contractor shall clean up the work site by the removal of all construction debris, waste materials, packaging material and the like. If the before mentioned items could become airborne, they shall be placed in refuse containers immediately. Clean up of the work site shall include the construction area(s), construction office area(s), material storage area (s), parking and eating area(s), and any other area(s) effected by the construction process. Any dirt or mud which is tracked on to any Base street, parking area, sidewalk, patio, or driveway shall be cleaned away daily. Materials resulting from demolition activities which are salvageable shall be stored within the work area or at a supplemental storage area. Stored material not in trailers, whether new or salvaged, shall be neatly stacked when stored in an approved location.

T. Contractor’s Management and Use of Electromagnetic Emission Devices on Base: (Electromagnetic emission devices include: Radio/Radar Transmitters; Navigational Aids/Instrumentations; Signaling, Intrusion Detecting, and Identification Devices; Mobile and Fixed Business Radio Communications Equipment; and MARS, CBs, and Amateur Radio Stations.) The Contractor shall comply with the Air Force Military Training Center (AFMTC) Regulation 700-14, Jul 89.

U. Preparation of Progress Schedules and Reports: The reports contemplated by FAR Clause, 52.236-15, Schedules for Construction Contracts, shall be accomplished on and in accordance with instructions pertaining to AF Form 3064, Contract Progress Schedule, and AF Form 3065, Contract Progress Report. Contract Schedules and Reports shall run from Monday through Sunday and be submitted to the CO per table of deliverables located in 4.0 A Table 1 - Table of Deliverables.

V. Deteriorated Construction and Finish

a. Authority: The QA Inspector will be the governing authority in determining if existing construction and finishes are deteriorated and require repair and/or replacement.

W. Contractor Storage/Staging Area

a. Operations and Storage Approval: Notwithstanding Contract FAR Clause, FAR 52.236-10, Operations and Storage Areas, subject to approval by the CO and in turn, availability and need, a storage/staging area may be provided at the subject project site. If project site space is not available, then offsite storage may be required.

b. Utility ‘tie-ins’, where available, are the Contractor’s responsibility. See 1.1 General Requirements, Q. Availability and Use of Utility Services for additional information.

c. Storage Area Clean Up: Weekly discard trash and debris in the Contractor’s containers (dumpsters). Do not allow debris to accumulate. At work completion, clean the storage area. This area must be free of any materials, trash or debris before receipt of final payment.

d. In areas of high visibility, the job site construction fence shall have a screen fabric material applied to the fence fabric in order to block the view during the construction phase. The CO will make the determination at the pre-construction meeting if the subject project requires a screened fence or not. Remove fence upon completion. Rehabilitate disturbed turfs and grass and if reseeding is required use Bermuda grass.

X. Hazardous component abatement for materials such as asbestos, lead-based paint, PCBs, and other hazardous materials shall be the responsibility of the Contractor. Abatement of mold resulting from water damaged materials shall be the responsibility of the Contractor.

Y. The duration of days is considered calendar days unless otherwise noted.

Z. COVID-19 Requirements - During the COVID-19 pandemic it is vital to Tyndall AFB’s Mission that the Contractor adhere to all Tyndall AFB Covid-19 directives to mitigate virus transmission. The contractor shall be responsible for the following: follow CDC guidelines, setting up teleconference meetings, wearing mask and social distancing when entering a government facility, the screening of their employees, and reporting COVID-19 cases to the 325th CONS and 325th CES project manage (PM). As Covid-19 directives are living documents, it is the Contractor’s responsibility to be informed and follow the most recent published directive.

AA. Project Signage: As required per the FAR.

a. As required, a job sign shall be required at the project site. The CO or the Government Inspector will make a determination based on cost and visibility. The sign shall indicate the Contractor’s company name, project name and MPLS number, superintendent’s name and a 24-hour available response phone number. The size of the sign shall be 4’ x 8’ x ¾” thick plywood board mounted to a 2x4 wood frame and diagonal braces. The wood frame shall be supported on 4x4 wood supports and be mounted to the ground in concrete footings. Background color shall be in accordance with Federal Standard White (Gloss). The color of the lettering shall be Black (gloss) with Helvetica font.

1.2 APPLICABLE DOCUMENTS

A. The Contractor shall identify and comply with all applicable federal, state, and local laws; statutes; Executive Orders; Department of Defense/Air Force manuals, handbooks, regulations, guidance, and policies. The contractor shall comply with the National Institute of Building Sciences’ Whole Building Design Guide Construction Criteria Base (CCB) Unified Facility Criteria (UFC) 3-600-01 and all of the related libraries. The primary criteria are the Air Force Criteria from the Documents Library, but other agency criteria may be directed for use, depending on the customer agency for a particular TO. The Unified Facilities Guide Specifications (UFGS) is the mandatory starting point for all specifications, and shall not be deleted, materially modified, or made less stringent without Government approval. It is the contractor’s responsibility to identify and comply with all applicable requirements. It shall be the contractor’s responsibility as the Designer of Record (DOR) to identify any design/construction criteria waivers that are warranted for the Project and to accomplish all necessary coordination activities necessary to obtain approval of these proposed waivers through the Contracting Officer (CO), and/or Project Manager (PM).

B. In addition, the contractor shall refer to and comply with the current versions of the Department of Defense Policy and Guidelines for Acquisitions Involving Environmental Sampling or Testing and The United States Air Force Construction Management Implementation Guide as well as the latest version of The USAF Project Manager’s Guide to Design and Construction. Base-specific documents are identified in the attached appendices.

C. The Contractor and Design Team shall adhere to the following guidance during design and construction phase(s) of this project: Those sections of the Southern Standard Building Codes not incorporated in the UBC/International Building Code (IBC) for our respective area, International Concrete Repair Institute (ICRI) Guidelines, Air Force Standards, Department of Defense (DOD) Directives, Florida State Statutes, and the Tyndall AFB Facility Excellence Plan (Base Regulations), Occupational Safety and Health Administration (OSHA) Requirements, Department of Environmental Protection (DEP) Regulations, Environmental Protection Agency (EPA) Regulations, and ABA Accessibility Compliance Requirements.

D. In addition to adhering to the previous guidance, the Contractor shall review and adhere to the most recent version of the following code criteria as applicable at start of the design phase:

a. Tyndall AFB IFSTyndall Air Force Base Installation Facility Standard www.tyndallifs.com
b. UFC 1-200-01The DoD Building Code
c. UFC 1-200-02High Performance and Sustainable Building Requirements
d. UFC 1-300-02Unified Facilities Guide Specifications (UFGS) Standard
e. UFC 1-300-07ADesign Build Technical Requirements
f. UFC 1-300-08Criteria for Transfer and Acceptance of DoD Real Property
g. UFC 3-101-01Architecture
h. UFC 3-110-03Roofing
i. UFC 3-110-04Roofing Maintenance and Repair
j. UFC 3-120-01Design: Sign Standards
k. UFC 3-120-10Interior Design
l. UFC 3-190-06Protective Coatings and Paints
m. UFC 3-201-01Civil Engineering
n. UFC 3-201-02Landscape Architecture
o. UFC 3-210-10Low Impact Development
p. UFC 3-220-01Geotechnical Engineering
q. UFC 3-220-05Dewatering and Groundwater Control
r. UFC 3-230-01Water Storage and Distribution
s. UFC 3-230-10AWater Supply, Water Distribution
t. UFC 3-240-01Wastewater Collection and Treatment
u. UFC 3-250-01Pavement Design for Roads and Parking Areas
v. UFC 3-250-03Standard Practice Manual for Flexible Pavements
w. UFC 3-250-04Standard Practice for Concrete Pavements
x. UFC 3-250-08FASealing Joints and Cracks
y. UFC 3-250-11Soil Stabilization for Pavements
z. UFC 3-260-02Pavement Design for Roads, Streets, Walks, and Open Storage Areas
aa. UFC 3-300-07ADesign Build Technical Requirements
ab. UFC 3-301-01Structural Engineering
ac. UFC 3-310-04Seismic Design for Buildings
ad. UFC 3-400-02Design: Engineering Weather Data
ae. UFC 3-401-01Mechanical Engineering
af. UFC 3-410-01Heating, Ventilating, and Air Conditioning
ag. UFC 3-410-02Direct Digital Control for HVAC
ah. UFC 3-410-04Industrial Ventilation
ai. UFC 3-420-01Plumbing Systems
aj. UFC 3-420-02FACompressed Air
ak. UFC 3-430-09Exterior Mechanical Utility Distribution
al. UFC 3-450-01Noise and Vibration Control
am. UFC 3-501-01Electrical Engineering
an. UFC 3-520-01Interior Electrical Systems
ao. UFC 3-530-01Interior and Exterior Lighting and Controls
ap. UFC 3-550-01Exterior Electrical Power Distribution
aq. UFC 3-560-01Electrical Safety O&M
ar. UFC 3-570-01Cathodic Protection
as. UFC 3-570-06Operation and Maintenance: Cathodic Protection Systems
at. UFC 3-575-01Lightning and Static Electricity Protection
au. UFC 3-580-01Telecommunications Interior Infrastructure
av. UFC 3-600-01Fire Protection Engineering for Facilities
aw. UFC 3-701-01DoD Facilities Pricing Guide, with Change 2; 2019
ax. UFC 3-730-01Programming Cost Estimates for Military Construction
ay. UFC 3-740-05Handbook: Construction Cost Estimating
az. UFC 4-010-01DOD Minimum Antiterrorism Standards for Buildings
ba. UFC 4-010-05Sensitive Compartmented Information Facilities
bb. UFC 4-010-06Cybersecurity of Facility-Related Control Systems
bc. UFC 4-020-01DoD Security Engineering Facilities Planning Manual
bd. UFC 4-021-01Mass Notification Systems
be. UFC 4-021-02Electronic Security Systems
bf. UFC 4-211-01Aircraft Maintenance Hangars
bg. USAF BIMMinimum Requirements Version 2.1
bh. AASHTOA Policy on Geometric Design of Highways and Streets
bi. ABASArchitectural Barriers Act Standards: The ABA
may be found at https://www.access-board.gov/guidelines-
and-standards/buildings-and-sites/about-the-aba-
standards/aba-standards
bj. AFDSAir Force Design Guide

bk. AFGM 2018-32-01 Civil Engineer Control Systems Cybersecurity

bl. AFI 32-1020Planning and Programming Built Infrastructure Projects
bm. AFI 32-1024Standard Facility Requirements
bn. AFI 32-1063Electrical Power Systems
bo. AFI 32-1064Electrical Safe Practices
bp. AFI 32-1065Grounding System www.wbdg.org › FFC › AFI › afi_32_1065_2017
bq. AFI 32-1067Water Systems
br. AFI 32-1068Heating Systems and Unfired Pressure Vessels
bs. AFI 32-1069Gas Supply and Distribution
bt. AFMAN 91-203Air Force Occupational Safety, Fire and Health Standards
bu. AFMAN 32-1084Facility Requirements Standards
bv. ANSI C2National Electric Safety Code
bw. ASCE 7-16Wind Loads
bx. ASHRAE 55Thermal Environmental Conditions for Human Occupancy
by. ASHRAE 62.1Ventilation for Acceptable Indoor Air Quality
bz. ASHRAE 90.1Energy Standard for Bldgs. Except Low-Rise Residential
ca. ASHRAE 100Energy Conservation in Existing Buildings
cb. ASHRAE 111Testing, Adjusting, and Balancing of Building HVAC Systems
cc. ASHRAE 180Inspection & Maintenance Commercial Bldg. HVAC Systems
cd. ASHRAE 189.1Standard for the Design of High-Performance Green Buildings
ce. ASHRAE 202Commissioning Process for Buildings and Systems
cf. ASHRAE Guide 4Prep of Operating and Maintenance Documentation
cg. ECB 2018-11Control System Cybersecurity Coordination Requirement
ch. EISAEnergy Independence and Security Act of 2007
ci. EM 385-1-1USACE Safety and Health Requirements Manual
cj. EPAct 2005Energy Policy Act of 2005
ck. FC 4-218-03FAir Force Criteria for Precision Measurement EquipmentLaboratory Design and Construction
cl. FARFederal Acquisition Regulations
cm. FS 553Florida Building Code
cn. IBCInternational Building Code
co. IESIlluminating Engineering Society Lighting Handbook
cp. IFGSInternational Fuel Gas Code
cq. IMCInternational Mechanical Code
cr. IPCInternational Plumbing Code

cs. NACE SP-0169

ct. NACE SP-0185

cu. NACE SP-0286

cv. NBIMS US V3National BIM Standard US Version 3
cw. NEBBStandards for Whole Building Systems Commissioning
cx. NECNational Electrical Code, current edition
cy. NEMANational Electrical Manufacturer's Association
cz. NESCNational Electrical Safety Code current edition
da. NFPA 13Standard for the Installation of Sprinkler Systems
db. NFPA 24Installation of Private Fire Service Mains and Their Appurtenances
dc. NFPA 70National Electric Code
dd. NFPA 72National Fire Alarm Code
de. NFPA 90AStandard for the Installation of Heating and Air
Conditioning Systems
df. NFPA 101Life Safety Code
dg. NFPA 1141Standard for Fire Protection Infrastructure for Land
Development in Wildland, Rural, and Suburban Areas
dh. NPDESNational Pollutant Discharge Elimination System

http://www.dep.state.fl.us/water/stormwater/npdes/construction3.htm

di. SMACNA GuidesSheet Metal & Air Conditioning Contractors’ National Assoc.
dj. TM 5-683Facilities Engineering Electrical Interior Facilities
dk. TM 5-684Facilities Engineering - Electrical Exterior
dl. USAF BIMMinimum Requirements Version 2.1
dm. UFASUniform Federal Accessibility Standards
dn. UFGS 23 09 00Instrumentation and Control for HVAC
do. UFGS 23 09 13Instrumentation and Control Devices for HVAC

dp. UFGS 23 09 23.02 BACnet Direct Digital Control for HVAC and Other

Building Control Systems
dq. UFGS 23 09 93Sequences of Operations for HVAC Controls
dr. UFGS 25 05 11Cybersecurity for Facility-Related Control Systems
ds. UFGS 23 08 10Utility Monitoring and Control System Testing
dt. UFGS 25 10 10Utility Monitoring and Control System (UMCS) Front End and Integration

Miscellaneous

a. AFCEC AGRAM 17-01 Change to AF New Construction and Major Renovation Certification Requirements

b. Air Force Pamphlet 91-210 (Contract Safety)

c. Air Force Systems Security Instruction 7700 - Communications and Information - Emission Security

d. Air Force Systems Security Instruction 7702 - Communications and Information - Emission Security

e. Air Force Sustainable Design and Development (SDD) Implementation Guidance

f. Tyndall Mass Notification System Messages

g. Tyndall Rebuild Facility Related Control Systems (FRCS) Technology Summary –Appendix L –22 Sept 2021

h. Draft Rule Amendments of the Environmental Resource Permitting (ERP) Program in the Northwest District, Applicant's Handbook Volume I & II, http://www.dep.state.fl.us/water/wetlands/erp/rules/draft nw.htm.

i. Recommended Standards for Wastewater Facilities (Ten States Standards)

j. Chapter 62-555 FAC General Permit of Construction of Water Main Extension for Public Water System

k. Chapter 62-600 of the Florida Administrative Code, Public Drinking Water Distribution System and Domestic Wastewater Facilities

l. Chapter 62-604 FAC Collection Systems and Transmission Facilities of the Florida Administrative Code, Domestic Wastewater Facilities and the Wastewater Permit checklist.

m. Manual of Practice No. FD-4 Design of Wastewater and Stormwater Pumping Stations.

n. Manual of Practice No. FD-5 Gravity Sanitary Sewer Design and Construction.

o. GCEC MANUAL OF STANDARDS AND SPECIFICATIONS FOR WATER MAIN CONSTRUCTION FOR TYNDALL AFB SYSTEM

p. Guiding Principles for Sustainable Federal Buildings and Associated Installations

q. Illuminating Engineering Society of North America (Handbook)

r. Florida Fish and Wildlife Commission.

s. E.O. 13834 Efficient Federal Operations

E. Lightning Protection Requirement: Lightning Protection System (LPS) shall be designed and installed IAW the following references:

a. AFI 32-1065Grounding System www.wbdg.org › FFC › AFI › afi_32_1065_2017
b. NFPA 70National Electric Code
c. NFPA 780Standard for the installation of Lightning Protection System
d. UFC 3-575-01Lightning and Static Electricity Protection System
e. UL 96Lightning Protection Components
f. UL 96AInstallation Requirements for Lightning Protection System
g. UL 467Grounding and Bonding Equipment

F. Security Requirements:

a. MIL-HDBK-1013:DOD Military Handbook Design Guidelines for Physical
Security of Facilities
b. AFI 31-101:Air Force Instruction 31-101: The Air Force Installation
Security Program
c. DOD 5200.1.RDepartment of Defense 5200.1.R: Information Security
Program Construction Standards.
d. ICD-ICS-705Tech Spec
e. UFC 4-010-01Unified Facilities Criteria Antiterrorism Standards for New
and Existing Facilities
f. UFC 4-010-06Cybersecurity of Facility-Related Control Systems

G. FAR Case No. 92-54 requires the Solicitation Package for all construction projects to reflect the government's preference for "acquisition of environmentally sound and energy efficient products and services, and an affirmative procurement program favoring items containing the maximum practicable content of recovered materials".

H. DOD Information

a. Department of Defense Manual 5200.01, Volume 1; DoD Information Security Program: Overview, Classification, and Declassification; 2012

b. Department of Defense Manual 5200.01, Volume 2; DoD Information Security Program: Marking of Classified Information; 2013

c. Department of Defense Manual 5200.01, Volume 3; DoD Information Security Program: Protection of Classified Information; 2013

d. Department of Defense Manual 5200.01, Volume 4; DoD Information Security Program: Controlled Unclassified Information (CUI); with Change 1 2018

I. Federal Green Construction Guide for specifiers. This guide can be found at: http://www.wbdg.org/design/greenspec.php

J. The Contractor shall perform all work IAW with AFI, ETL, UFC and industry standards. Compliance with AF UFCs is mandatory unless the Tyndall AFB IFS has more stringent requirements. If the Contractor determines that the work cannot be performed and/or included in the SOW IAW with ETL’s/UFCs or industry standards, the Contractor shall notify the Tyndall AFB POC listed in this document in writing immediately before award of the contract. Otherwise, the Contractor shall be responsible for the required work.

K. All work shall be in compliance with all Public Laws (P.L.), Executive Orders (E.O.), Code of Federal Regulations (CFR), Department of Defense Instructions (DODI), Department of Defense Directives (DODD), or other higher authority documents as applicable. Many applicable compliance documents are authorized by DoD MIL-STD-3007F, and are available through the Government-sponsored Whole Building Design Guide located at https://www.wbdg.org.

L. If there is a conflict between these codes, regulations specifications, and/or guidance documents, the most stringent requirements shall apply, as determined by the CO through the Request for Information (RFI) process. These listed documents do not relieve the Contractor from complying with other required regulatory documents not listed.

M. The government may take up to 30 days to review design documents. The contractor schedule activity for less days will be overridden by this time frame and will not be considered a delay by the government. The contractor schedule shall reflect the 30-day review time.

2.0 GOVERNMENT PROPERTY INCLUDING GOVERNMENT FURNISHED INFORMATION, EQUIPMENT, AND PROPERTY (GFI, GFE, GFP)

A. Historical architectural and structural construction documents may be available for review, however field verification and documentation of existing conditions and configurations prior to construction is essential. The government takes no responsibility for errors and omissions contained in the reference material and field verification shall be performed by the contractor.

3.0 MANAGEMENT, PLANNING, AND REPORTING REQUIREMENTS

A. Design submittals, 35%, 65%, and 100% (for construction), will be routed with an AF Form 3000 and will be reviewed and approved/disapproved within 30 calendar days.

B. No delay damages or time extensions will be allowed for time lost in late or lost submittals. Government review times may take up to 30 days and is not considered a delay for design reviews. The contractor’s schedule shall include time for these 30 day reviews. The official review time starts when the CO acknowledges the receipt of the submittal.

C. Submittals pertaining to environmental issues may take up to 30-45 days for review and approval. Wetland permits may take greater than 60 days to process. Environmental 813 submittals shall include drawings, locates for utilities with depth, size of lines, length of runs, underground or above ground routing, spatial coordinates, duration of the laydown yard or temporary trailer, number of personnel, location of temporary porta toilets, etc. Delays greater than the anticipated days listed herein do not constitute a governmental delay. Contractor will be allotted a no-cost PoP extension for days over and above those listed herein.

D. All other submittals should be reviewed and approved/disapproved within 10 workdays. Submittals will be reviewed for accuracy and relevance to the project and specifications. Material Submittal documents shall be submitted with AF Form 3000, Material Approval Submittal.

E. Submittal shall follow the UFGS Specification Section 013300 SUBMITTAL PROCEDURES as well as the respective submittal section requiring forms, reports, drawings, samples, pictures, media recordings, manufacturer data, certifications, test reports, equipment warranty information, and the like. Submittal documents shall be submitted by the Contractor to the by CO for approval. All submitted documentation shall become the complete property of the Government. The Contractor shall not purchase, install, or construct any equipment or facility component, for which a submittal is required, without first obtaining an approved signed submittal from the CO. Required submittals shall be listed on AF Form 66, Schedule of Material Submittals, and/or a Submittal Register approved by the CO.

F. Table of Deliverables: Project deliverables shall be as shown in the following 4.0 A Table 1 - Table of Deliverables. The dates in the table are hard dates not to be exceeded without CO approval. The deliverables and scheduled activities may be provided or completed early.

G. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. The Contractor is responsible for additional time required for Government reviews resulting from required resubmittals. The review period for each resubmittal is the same as for the initial submittal.

H. Submittals required by the contract documents are listed on the submittal register. If a submittal is listed in the submittal register but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but have been omitted from the register or marked "N/A."

I. Resubmit the submittal register and annotate it monthly with actual submission and approval dates. When all items on the register have been fully approved, no further resubmittal is required.

J. Contracting Officer Review will be completed within 30 calendar working days after the date of submission for submittals requiring Government approval.

4.0 SUBMITTAL FORMAT AND TIMING AND DESIGN

4.1 Preliminary Design

This project shall include a design phase in which the Contractor shall evaluate specific requirements presented in this SOW, sketches provided by government and site visit. Contractor shall field verify all conditions and dimensions to provide design. The Contractor shall submit a full design for approval by the Government prior to start of construction. The design shall be submitted at initial/preliminary design stage for review comments and changes prior to submission of the hundred percent (100%) for construction and hundred percent (100%) completed/final design (as-builds).

4.1.1 Site Visits:

All site visit schedules shall be in coordination with the 325 CES/CENMP Project Engineer and 325 CONS. Any additional site visits required to complete the required designs shall be at the Contractor's expense.

4.1.2 Pre-Design and/or Design Review:

The Contractor must coordinate with the Contracting Officer (CO), 325 CES Engineer, and system stake holders before any initial and/or pre-design is submitted.

4.2 Project Design Phase

4.2.1 Design Data:

The initial design data shall be submitted to the Government prior to the initial design data review meeting.

4.2.2 35% Initial Design Data Review/Comment:

The initial design data review meeting shall be scheduled ten (10) business days after the kick-off meeting. The Contractor shall setup a teleconference meeting for all possible attendees and provide agenda and documentation two (2) business days before the meeting. The Government will provide the Contractor their review comments on the design data submitted at the initial findings review meeting. The Government's review is intended to be limited to functional aspects, with limited technical review of a general cursory nature only. The following submissions shall be reviewed:

1. A detailed narrative (charrette report) explaining the existing conditions, new requirements identified through user interviews, and preliminary recommendations of accommodating all identified requirements shall be provided at this meeting

2. Design analysis including initial engineering calculations.

3. Preliminary design drawings/sketches.

4. Draft AF Form 66; and5. Outline technical specifications.

4.2.3 100% Design for Construction Review/Comment:

Government shall have up to ten (10) business days to provide review comments. The Contractor shall setup a teleconference meeting for all possible attendees and provide agenda and documentation two (2) business days before the meeting.

100% Design Submittal Requirements

1. Review comments and Contractor responses from initial design.

2. Minutes and sign-in sheet of initial design review meeting.

3. Proposed Final design analysis.

4. Proposed Final design drawings.

5. Proposed Final AF Form 66.

6. Final technical specifications.

4.2.4 100% Final Design with Red Line Changes (As-Build):

Government shall have up to five (5) business calendar days to provide review comments. The Contractor shall setup a teleconference meeting for all possible attendees, andattendees and provide agenda and documentation two (2) business days before the meeting.

100% Design Submittal Requirements

1. Review comments and Contractor responses from 100% design.

2. Minutes and sign-in sheet of 100% review meeting.

3. Final design analysis.

4. Final design drawings.

5. Final AF Form 66.

6. Final technical specifications.

7. Include all red-line changes, with dimensions, etc.

4.3 Projected Design Timeline:

Description
Description of Days
Days
NTP
0
Site Investigation, Pre-Construction Meeting and Project Kickoff (within)
7 + NTP
7
Contractor Submits Minutes
plus 73
107
Design Charette Meeting
plus 7
17
Contractor Submits Minutes
plus 3
20
Government Review Minutes
plus 7
27
35% Design SubmittedSubmitted (within)
plus 21+ NTP
2848
Government Review of 35% Design
plus 14
4252
Contractor Schedule 35% Design and Design Charrette Meeting Meeting
plus 7
5949
Contractor Submits Minutes
plus 73
6256
Government Review Minutes
plus 7
6963
Contractor Submit Final 35% (within)
plus 7
7670
Environmental 813/FDEP Permit
plus 60
136130
100% Design for Construction Submitted
plus 14 21 after 35% design approval
144157
Government Review of 100% Design for Construction
plus 14
17158
Contractor Schedule 100% Design Meeting
plus 7
17865
Contractor Submits Minutes
plus 73
181172
Government Review Minutes
plus 7
118979
Contractor Submit Final 100% (within)
plus 7
196186

Estimate Time to the Start of Construction

196186

Contractor Begin Construction after 100% Approval
24 35 Weeks (168245)
441354
100% Completed Design Submitted Before Final Inspection
plus 7
448361
Final Submittal of All Documents
Plus 2830
476391

Table 4.3.1 Estimated Time LineTimeline in Colander Days

4.4. Design Distribution:

All design drawings, in the number of copies stated in the table below, shall be completed in AutoCAD 2019 (base version), and consist of a complete set of drawings.

Deliverables Distribution
CONS Copy
CES Copy
TOTAL
Base Access Information
0
1
2
Meeting Minutes and MFRs (Electronic Copy
1
1
2

None

35% Initial Design with Supporting Data Submittals
1
1
2
100% Design for Construction Submittals:
1
1
2
100% Complete Design with Red Line Submittals:
1
1
2

4.5 Government Review:

A The Government's review is intended to be limited to functional aspects, with limited technical review of a general cursory nature only. Refer to paragraph 4.2 for the Government review during design period. Any review by the Government of technical items shall not be construed to relieve the contractor of responsibility for technically correct and complete documents in compliance with applicable codes, industry standards, and the intent of this SOW. The Contractor shall comply with the review comments in the development of data for the next submittal. If any review comment requires clarification and/or amplification to assure compliance the Contractor shall notify the COR or authorized representative in writing. If the Government specifically asks a question via the review comments and requires clarification or the Contractor does not concur with or takes exception to a review comment then the Contractor shall submit the review form with comments annotated by the Contractor with a "D" - do not concur, "E" - exception, or "X" - delete, shall have an explanatory note added to justify the noncompliance with the comment. The Contractor shall furnish these annotated comments to the Government no later than seven (7) calendar days after receiving the comments. If the Contractor agrees with the review comments, then it shall be reflected in the next submission.

B. Please note that the sole responsibility of ensuring that the design submittals comply with contract documents remains with the Contractor, in accordance with all the contract documents and design criteria referenced therein. The Government retains the right to comment on the design at any design stage, and the lack of Government comments at a given review cannot be used as a basis for the Contractor to fail to address the Government's comments on subsequent reviews, regardless of design stage. Furthermore, approval of incomplete designs will not relieve the Contractor of the responsibility for any error that may exist, and which may require rework or other appropriate adjustment to the contract terms, as determined at the sole discretion of the Government.

C. Government review, clearance for construction, or approval by the Contracting Officer shall not relieve the Design-Build Contractor from responsibility for any errors or omissions in such drawings, nor from responsibility for complying with the requirements of this contract.

D. Government review, clearance for construction, or approval of post design construction submittals shall not be construed as a complete check but will indicate only that the general method of construction, materials, detailing and other information are satisfactory.”

4.5.1 Contractor Response to Review Comments:

The Contractor shall respond in writing to each of the review comments that they take exception to within 7 calendar days after receipt of the comments. If the Contractor disagrees with or takes exception to the comments, the Contractor shall include an explanation of why they disagree in their response back to the Government. Otherwise, the comment resolution(s) shall be incorporated into the next design submission.

4.6 Verification of Existing Conditions and Site Survey

Use of existing condition data provided by the Government conveys acceptance and as such does not relieve the Contractor of liability associated with performance as the Engineer of Record. The Contractor shall be solely responsible for verification and validation of existing conditions, coordination of existing conditions in parallel with proposed requirements, and above and below-grade condition assessment. The Contractor must coordinate discussions with the CO, project manager, and system stakes holders before any initial design is submitted.

4.6.1 Field Measurements:

The Contractor shall be required to make his own field investigations to verify dimensions and other information shown on government furnished reference drawings.

4.6.2 Site Survey

Site survey data shall be submitted to the Government within seven (7) calendar days of receipt via AF 3000 Material Approval Submittal.

4.7 Designer of Record:

The Contractor is accountable for all aspects of the completed design and as-built drawings under all applicable Federal, State and local laws, regulations and base-specific standards. The designer of recorded shall stamp all drawings.

4.8 Contract Drawings:

Drawings shall be prepared on AutoCAD 2019 format. Drawings shall be delivered in hard copy, standard black line quality paper, at review stages in the number listed in paragraph4.4.3. All submittals shall go through the 325 CONS office, but the 325 CES/CENM drawings shall be full size and the copy provided for CONS shall be half-size. The remaining sets of review drawings and corrected final drawings shall be half size. The drawings shall be drawn to appropriate scales and dimensioned completely and accurately. Extensive explanatory notes on the drawings should be held to a minimum or placed in the specifications. All dimensions shall be shown in Standard English units. All contract drawings shall be well prepared, complete, and accomplished in accordance with the best professional practice to show clearly and concisely the type and extent of work to be performed.