Revised Attachment 7 1st Task Order Statement of Work

View the file

Other files

Show all 22

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FA4809-09-R-0008

Attachment 7, pg. 2 of 5
Revised, Amendment 02, dtd 15 Apr 05

STATEMENT OF WORK

VKAG 09-1070

INSTALL CRU FLOORING, UTILITY SHOP

10 APR 09

1. PROJECT DESCRIPTION: Provide services and materials to re-surface floors in Utility Shop of Bldg 3300. The contractor shall strip existing floor surface and lines, prepare floor surface, replace all damaged joints, correct spalls/cracks, resurface floor, and install new markings and signs in accordance with IDIQ contract and associated drawings. Special care shall be taken to protect floor drains, grounding lugs, etc. from paint and chemicals. Floor color shall be white semi-gloss instead of the standard light gray semi-gloss called for in parent IDIQ specifications. Sign, line, and text colors are denoted on project drawings or parent IDIQ specifications.

2. SAFETY: Paint will be disposed of in accordance with county, state, and federal law. Proper precautions will be taken to ensure the safety of contractor and government employees. Government personnel work activities in adjacent areas should not be disrupted as a result of CRU installation/removal. All safety and environmental concerns addressed in parent IDIQ contract shall be complied with.

3. DOCUMENTATION: Location and floor plans are provided.

4. LEAD CONTAINING/BASED PAINT: Contractor shall be aware that the existing floor paint in Hangar bay of Bldg 3300 contains 0.061%-0.078% lead by weight. Paint is thus not considered hazardous material however proper OSHA recommended worker protection must be used.

T:\PROJECT FOLDERS\09\09-1070\Statement of Work.docx