SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The purpose of this amendment is to incorporate the following changes:

A. Reference SF 1442, Block 10, Item 5. Change Block 10, Item 5 to read as follows: IAW FAR

36.204(e), the magnitude of this project is between $1,000,000.00 and $5,000,000.00. The guaranteed minimum for the life of the contract is $3,000.00; maximum contract value is $1,900,000.00; minimum per TO is $3,000.00; maximum per TO is $500,000.00.

B. Reference Section J, List of Attachments. Delete Attachment 7, entitled “RFP, First (1st) Task Order To

Be Awarded Against the Basic Contract Requirement, Title: Maintain Paint On Hangar Floor, Bldg.

4820, Project No. VKAG 05-1” and replace with the attached Revised Attachment 7, entitled “RFP, First (1st) Task Order To Be Awarded Against the Basic Contract Requirement, Title: Install CRU

Flooring, Utility Shop, Project No. VKAG 09-1070.

C. The site visit scheduled for 20 Apr 09 at 10:00 AM remains unchanged.

D. The date and time for receipt of proposals remain unchanged.

E. All other Terms and Conditions remain unchanged.