Text version

Base Year

Project:Protective Coating
Location:Shaw AFB
Contractor:
Address:
Pricing to include all profit, overhead, supervision, personnel, equipment, transportation, material, and other items
and services necessary to perform paint/protective coating services at Shaw AFB in accordance with the SOW.
Line No.ItemQuantityUnitUnit Price
(Per Single Unit)Line Total
1AAExterior Painting510,000SF
1ABPartial Exterior and Trim30,000SF
1ACPaint Interior350,000SF
1ADPartial Interior and Trim40,000SF
1AERemove Pavement Markings50LF
1AFApply Pavement Markings30,000LF
1AGPrime Interior / Exterior230,000SF
1AHRepair Drywall Surfaces12000SF
1AJRemove Wall Coverings / Wallpaper2000SF
1AKPaint Hydrants60EA
1ALPrepare / Paint Special Structures8600SF
1AMPrepare / Paint Swimming Pool13500SF
1ANPressure Washing150000SF
1APFabrication of Sign Blanks1200SF
1AQFabricate / Apply Letters & Numbers30000EA
1ARGlass Door Stenciling5EA
1AUReimbursable SupplysWill be priced oneach task order
Total:

Option Year 1

Project:Protective Coating
Location:Shaw AFB
Contractor:
Address:
Pricing to include all profit, overhead, supervision, personnel, equipment, transportation, material, and other items
and services necessary to perform paint/protective coating services at Shaw AFB in accordance with the SOW.
Line No.ItemQuantityUnitUnit Price
(Per Single Unit)Line Total
1AAExterior Painting510,000SF
1ABPartial Exterior and Trim30,000SF
1ACPaint Interior350,000SF
1ADPartial Interior and Trim40,000SF
1AERemove Pavement Markings50LF
1AFApply Pavement Markings30,000LF
1AGPrime Interior / Exterior230,000SF
1AHRepair Drywall Surfaces12000SF
1AJRemove Wall Coverings / Wallpaper2000SF
1AKPaint Hydrants60EA
1ALPrepare / Paint Special Structures8600SF
1AMPrepare / Paint Swimming Pool13500SF
1ANPressure Washing150000SF
1APFabrication of Sign Blanks1200SF
1AQFabricate / Apply Letters & Numbers30000EA
1ARGlass Door Stenciling5EA
1AUReimbursable SupplysWill be priced oneach task order
Total:

Option Year 2

Project:Protective Coating
Location:Shaw AFB
Contractor:
Address:
Pricing to include all profit, overhead, supervision, personnel, equipment, transportation, material, and other items
and services necessary to perform paint/protective coating services at Shaw AFB in accordance with the SOW.
Line No.ItemQuantityUnitUnit Price
(Per Single Unit)Line Total
1AAExterior Painting510,000SF
1ABPartial Exterior and Trim30,000SF
1ACPaint Interior350,000SF
1ADPartial Interior and Trim40,000SF
1AERemove Pavement Markings50LF
1AFApply Pavement Markings30,000LF
1AGPrime Interior / Exterior230,000SF
1AHRepair Drywall Surfaces12000SF
1AJRemove Wall Coverings / Wallpaper2000SF
1AKPaint Hydrants60EA
1ALPrepare / Paint Special Structures8600SF
1AMPrepare / Paint Swimming Pool13500SF
1ANPressure Washing150000SF
1APFabrication of Sign Blanks1200SF
1AQFabricate / Apply Letters & Numbers30000EA
1ARGlass Door Stenciling5EA
1AUReimbursable SupplysWill be priced oneach task order
Total:

Option Year 3

Project:Protective Coating
Location:Shaw AFB
Contractor:
Address:
Pricing to include all profit, overhead, supervision, personnel, equipment, transportation, material, and other items
and services necessary to perform paint/protective coating services at Shaw AFB in accordance with the SOW.
Line No.ItemQuantityUnitUnit Price
(Per Single Unit)Line Total
1AAExterior Painting510,000SF
1ABPartial Exterior and Trim30,000SF
1ACPaint Interior350,000SF
1ADPartial Interior and Trim40,000SF
1AERemove Pavement Markings50LF
1AFApply Pavement Markings30,000LF
1AGPrime Interior / Exterior230,000SF
1AHRepair Drywall Surfaces12000SF
1AJRemove Wall Coverings / Wallpaper2000SF
1AKPaint Hydrants60EA
1ALPrepare / Paint Special Structures8600SF
1AMPrepare / Paint Swimming Pool13500SF
1ANPressure Washing150000SF
1APFabrication of Sign Blanks1200SF
1AQFabricate / Apply Letters & Numbers30000EA
1ARGlass Door Stenciling5EA
1AUReimbursable SupplysWill be priced oneach task order
Total: