Additional questions and answers
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment.pdf | ||
| Bldg_898_Q A_2.docx | DOCX document | |
| Bldg_898_Q A.docx | DOCX document | |
| FA4801-15-R-0029-0002.pdf | ||
| Corrosion_Control_UFC_4_211_02.pdf | ||
| FA4801-15-R-0029 _Bldg_898_Paintbooth_Retrofit.pdf | ||
| FA4801-15-R-0029 _Bldg_898_Paint_Booth_Amendment.pdf | ||
| FA4801-15-R-0029 _Bldg_898_Paintbooth_Retrofit.doc | DOC document | |
| ATCH_3-_NCIC_Base_Access.pdf | ||
| ATCH_2-_CCFRG_Version_10_17DEC2012.pdf | ||
| ATCH_1-_SOO _Bldg_898_Paintbooth_Retrofit.docx | DOCX document |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FA4801-15-R-0029 Q&A’s 898 Paintbooth Retrofit Question: Need to know the details of the existing fan/motor combinations on the existing booths. Specifically, need to know each fan size, motor size and the function of the pair. i.e.: 35” Tube axial fan with a 7.5hp motor - exhaust motor
Answer: Each booth has 1 24000 CFM Exhaust Fan which is 30hp and has 42” Fan. Each booth has 2 recirculation fans which are 75hp ea.
Clariffication Request: Regarding the Q&A’s, we understand that the removal and re-installation of the filters is the responsibility of the contractor, however, the disposal of these filters, as a hazardous waste generated at Holloman, must be the responsibility of Holloman. Please confirm that Holloman will provide the necessary storage/transport containers and provide ultimate disposal service.
Answer: Holloman will provide the HAZMAT boxes and dispose of the filters.