STATEMENT OF WORK

PROJECT MUHJ 14-4077

AIRFIELD AND PAPI LIGHTING SYSTEM REPLACEMENT

AT

LANGLEY AFB, JBLE, VIRGINIA

November 31, 2016

1.DESCRIPTION OF WORK:
1.1General Scope: Furnish all plant, labor, equipment, materials, tools and perform all operations necessary to perform work to repair by replacement, the runway and taxiway lights, airfield signage circuits, Runway 08 threshold lights, Wind Direction Indicators (Wind Socks), Precision Approach Path Indicator (PAPI) lights on each runway end (08 and 26), all constant current regulators with new switchgear style CCR system, and the associated lighting circuits, power circuits, cabling, ducts, etc. The Airfield Lighting Electrical Vault Constant Current Regulators (CCR) and interior electrical distribution equipment will also be repaired by replacement.

The following is the scope of work for specific areas of the airfield.

Repair by Replacement, Runway 08/26 Edge Light System and circuitry (bases, ducts, cabling and can plazas).

· Repair by Replacement, Taxiway Edge Light (taxiways A, B, C, D, E, H, F, & K) System and circuitry (bases, ducts, cabling and handholes with can plazas).

· Repair by Replacement, Airfield Signage circuitry (bases, ducts, cabling with can plazas). The existing airfield signage will remain. Add one new ILS Hold airfield sign adjacent the intersection of taxiway F and runway 26.

· Repair by Replacement, Runway 08 Threshold light system and circuitry (lights, ducts, cabling, concrete and can plazas). Adjust the location of the runway 08 threshold new lighting “bar” so that it is located within 10 feet of runway 08 threshold.

· Install new Taxiway Edge Lighting non powered reflector system on Taxiway J.

· Repair by Replacement, PAPI system on both runways 08 and 26 including circuitry (foundations, ducts, cabling, and can plazas).

· Repair by Replacement, the existing control circuitry and power circuit (power transformer, ducts, cabling, and can plazas) for RW 08 ALSF-1 system new fiber optic control cabling. Repair by replacement the existing RW 08 ALSF-1 circuit conductors from a three circuit system with 4 circuit system from station 2 handhole to the airfield lighting vault.

· Repair by Replacement, three windsocks (Wind Direction Indicator) systems and circuitry (foundations, ducts, cabling and can plazas).

· Reprogram the existing airfield lighting control system.

· Associated asphalt and airfield pavement cutting and repairing to permit the new lighting systems to be installed.

· Repair by removal all existing concrete bases and concrete foundation obstructions on the airfield that will no longer be in service, to the extent visually recognized and in the path of new circuit installations.

· All existing underground ducts where conductors are removed from these ducts will be abandoned in place unless they interfere with new construction.

2. PROGRAM MANAGEMENT: The contractor shall sequence his work to ensure progress efficient for occupancy and use.

2.1 COMMENCEMENT, PROSECUTION AND COMPLETION OF WORK:

No design effort is required

2.2 SUBCONTRACTORS:

No variance.

2.3 QUALITY CONTROL PLAN:

No variance.

3. RESPONSE REQUIREMENT

No variance.

4. DESIGN DOCUMENTS, GENERAL:

No design effort is required.

4.1 DRAWINGS:

No variance.

4.2 RENDERED PERSPECTIVE:

No variance.

4.3 SPECIFICATIONS:

No variance.

4.4 CONSTRUCTION COST ESTIMATE BREAKDOWN:

No variance.

4.5 PREPARATION OF AF FORM 66, Schedule of Material Submittals:

No variance.

4.6 BID SCHEDULE:

A bid schedule is furnished.

4.7 DESIGN ANALYSIS:

No variance.

4.8 COMMUNICATIONS:

No variance.

4.9 ENERGY MONITORING AND CONTROL SYSTEM (EMCS):

No variance.

4.10 LOCKSETS:

No variance.

4.11 GEODETIC CONTROL SURVEYS:

No variance.

5. CONTRACT OPERATIONS:

No variance.

5.1 WORK HOURS

No variance.

5.2 ORDER OF WORK:

No variance.

5.3 APPLICABLE CODES AND REGULATIONS:

No variance.

6. GOVERNMENT POINT OF CONTACTS

633 CES Project Manager – Peter Phan, 764-1151.

STATEMENT OF WORK

MUHJ 14-4077