DRAFT_Atch_7_Ellsworth_Fire_Protection.pdf

PDF 84 KB Posted

Attached to
Multiple Award Construction Contract (MACC) Federal contract opportunity
Solicitation number
FA469019RA003
Issued by
Department of the Air Force Air Combat Command

About this file

This document outlines fire protection standards for facilities at Ellsworth Air Force Base in South Dakota and specifications for a Multiple Award Construction Contract solicitation. The fire protection standards specify that all facilities must comply with UFC 3-600-01 and include building code analysis, life safety code analysis, and water supply analysis. Plans must show fire walls, fire doors, fire dampers, exit lights, sprinkler systems, and fire alarm systems. Specifications require schedule 40 piping for dry pipe and preaction systems and training.

The solicitation will award three indefinite delivery indefinite quantity contracts for new construction, renovation, alteration, demolition, and repair work through task orders. The solicitation period is from date of award through 29 June 2021, with a minimum of $500 and maximum of $18 million. It is set aside for service disabled veteran owned small businesses, SBA certified 8(a) small disadvantaged businesses, and HUBZone businesses. The NAICS code is 237990 and size standard is $36.5 million annually. The agency is the Air Force Air Combat Command.

DRAFT Atch 7 Fire Protection

View the file

Other files for this federal contract opportunity

Other files attached to Multiple Award Construction Contract (MACC), newest first.
File Type Posted
Atch_31_Follow_on_Q&As_26APR19.pdf PDF
Atch_30_Follow_on_Q&A_25APR19.pdf PDF
Atch_20b_SOW_Updated_23APR19.pdf PDF
Atch_29_Follow_on_Q&As_23APR19.pdf PDF
Solicitation_Amendment_FA469019RA0030009_SF_30.pdf PDF
Solicitation_Amendment_FA469019RA0030008_SF_30.pdf PDF
Atch_28_-_Follow_on_Q&As.pdf PDF
Solicitation_Amendment_FA469019RA0030005_SF_30.pdf PDF
Atch_25_Site_Vist_Q&As_14FEB19.pdf PDF
Atch_26_X-XX_PROJECT_TITLE.dwg DWG drawing
Solicitation_Amendment_FA469019RA0030003_SF_30.pdf PDF
Atch_24_Site_Visit_Minutes_24JAN19.pdf PDF
Atch_23_Site_Visit_Minutes.pdf PDF
Atch_20_FOPR_Construct_Bath_House_3JAN19.pdf PDF
Solicitation_Amendment_FA469019RA0030001_SF_30.pdf PDF
Atch_12_General_Provisions_-_8NOV18.pdf PDF
Atch_16b_-_WD_SD180006_Residental-Meade_5_Jan_18.pdf PDF
Atch_20b_SOW_6NOV18.pdf PDF
Atch_17_Determination_of_Resp.pdf PDF
Atch_20_FOPR_Construct_Bath_House.pdf PDF
Atch_20c_Drawing_1_Track_Utilities_Latrine_6NOV18.pdf PDF
Atch_15_Non-Nuclear_Intrusion_Det.pdf PDF
Atch_20g_AF_Form_3052.xls XLS spreadsheet
Atch_4_Spec_Section_01000_-20_Aug_15.pdf PDF
Atch_20d_RMD_KTR_to_Complete.pdf PDF
Atch_18_Past_Performance_Information.docx DOCX document
Atch_22,_SECTION_M_-_EVALUATION_BASIS_FOR_AWARD_2JAN19.pdf PDF
Atch_5_Spec_Section_01800_-20_Aug_15.pdf PDF
Atch_11_Underground_Electrical_20Aug15.pdf PDF
Atch_16a_-_WD_SD180002_Residental-Penn_5_Jan_18.pdf PDF
Atch_1_Utility_Outages.pdf PDF
DRAFT_Atch_4_Spec_Section_01000_-20_Aug_15.pdf PDF
DRAFT_Atch_20d_RMD_KTR_to_Complete.pdf PDF
DRAFT_Atch_21_SECTION_L_Instructions,_Conditions,_and_Notices_to_Offerors.pdf PDF
DRAFT_Atch_12_General_Provisions_-_8NOV18.pdf PDF
DRAFT_Atch_16b_-_WD_SD180006_Residental-Meade_5_Jan_18.pdf PDF
DRAFT_Atch_20b_SOW_6NOV18.pdf PDF
DRAFT_Atch_16c_-_WD_SD180001_Heavy-Highway_6_Apr_18.pdf PDF
DRAFT_-_FA469019RA003.pdf PDF
DRAFT_Atch_8_Exterior_Signs_-_10_Jun_05.pdf PDF
DRAFT_Atch_19_PPQ.docx DOCX document
DRAFT_Atch_20f_Bid_Schedule-17_Oct_18.doc DOC document
DRAFT_Atch_13_NAFGeneral_Provisions-21Jan15.pdf PDF
DRAFT_Atch_16e_-_WD_SD180035_Building-Penn_5_Jan_18.pdf PDF
DRAFT_Atch_20_FOPR_Construct_Bath_House.docx DOCX document
DRAFT_Atch_18_Past_Performance_Information.docx DOCX document
DRAFT_Atch_17_Determination_of_Resp.pdf PDF
DRAFT_Atch_16d_-_WD_SD180033_Building-Meade_5_Jan_18.pdf PDF
DRAFT_Atch_20e_6_Percent_Limit_on_Design_Fee_for_Contractors.pdf PDF
DRAFT_Atch_20c_Drawing_1_Track_Utilities_Latrine_6NOV18.pdf PDF
Show all 50

Multiple Award Construction Contract (MACC) has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BASE FIRE PROTECTION STANDARDS

Ellsworth AFB, South Dakota

Fire protection for all facilities shall comply with the following:

Design

All facilities shall be designed to comply with UFC 3-600-01 and the ACC Supplement. The fire protection engineer designer of record (FPDOR) shall meet the requirements of UFC 3-

600-01 and shall be in attendance at all design review meetings. If COE or NAVFAC is not the construction agent, the FPDOR shall review all shop drawings for approval and shall witness all operational tests for acceptance of the fire protection systems. FPDOR shall be identified at the beginning of the project.

All projects shall include building code analysis, life safety code analysis and a water supply analysis in accordance with UFC 3-600-01. These shall be included in the 35% submittal.

1. Building code analysis shall use the current edition of International Building Code as outlined in UFC 4-021-01. Analysis shall compare the allowable area and height and the actual area and height.

2. Life Safety Code analysis shall be based on latest edition of NFPA 101. Analysis shall show allowable and actual data such as travel distances, occupant loading, exits, etc.

3. Water supply analysis shall use the attached format for determining the adequacy of the water supply. Designer is responsible for conducting water tests to use in the analysis.

Plans

Life Safety Code:

Life Safety Code analysis and Building Code analysis shall be included as separate plans including the information shown in the ACC Supplement.

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text Attachment 7

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

1175923140C Typewritten Text

Civil Plans:

The civil drawings shall show all fire water mains to include positive identification of the test hydrants (both pressure and flow hydrants).

Plans must show water main from the test point to the building riser.

Show all fire hydrants and control valves. See UFC 3-600-01 for criteria.

Roads shall comply with UFC 3-600-01 and NFPA 1 for accessibility to building by emergency vehicles. Coordinate with the fire department.

Architectural Plans

The architectural plans and the Life Safety Code plans shall both show the fire walls and partitions and architectural plans shall identify the UL number or other standard such as

FM for fire rated assemblies.

Door plan shall identify the fire rating of any fire doors. Make sure fire doors match firewalls shown on drawings.

Mechanical Plans

Mechanical plans shall positively identify all fire and/or smoke dampers and provide a detail for installation. Any smoke damper shall include a smoke detector for activation of the damper. Fire dampers shall be shown to comply with NFPA 90A and smoke dampers shall comply with NFPA 101.

Mechanical plans shall include duct smoke detectors on the control diagram. Smoke detectors shall not activate the building evacuation alarm system but shall report as an alarm to the fire department as a separate zone on the fire alarm panel.

Electrical Plans

Plans must show the exit and emergency lights.

Switchgear shall show the power for the fire alarm system as a separate breaker.

Fire Suppression Plans

Plans must show the hazard classification for each area.

Provide a chart showing the density, area of application and hose stream demand for each hazard classification. This data must comply with UFC 3-600-01.

Provide a riser diagram for the sprinkler system. Make sure to include a test connection for the backflow preventer. The Air Force uses “shotgun” risers.

Fire Alarm Plans

Plans shall show all fire alarm and Mass Notification devices. Visual devices shall show the candela rating of each device.

Riser diagram shall show all power connections, initiating devices, alarm devices and any interconnections of such as AHU shutdown or door releases.

Provide a matrix showing what action each device will initiate.

Locate the fire alarm panel as dictated by the fire department. Panel shall be located in a conditioned space accessible to the fire department when the building is not occupied.

Provide transmitter zone schedule

Specifications

Civil

Make sure all fire protection devices such as fire hydrants, control valves, etc over five feet from the building are included in the civil specifications.

Fire Suppression

Either the specifications or the plans must indicate the hazard classification including density, area of application and hose stream demand. If shown on plans, indicate that information is shown on the plans.

Provide the water supply data or show it on the plans. If shown on plans, indicate that in the specifications. If not shown on plans, be specific as to the location of the water test such as at Hydrant 100 or the base of the riser. Designer must include the loss from the test connection to the base of the riser.

All sprinkler piping shall be schedule 40 for dry pipe and preaction systems.

Training of shop personnel will consist of one four- hour training sessions that will include the testing and maintenance of the systems. Training shall be separate from the testing of the systems.

Fire Alarm

The fire alarm reporting system is a radio type system using Monaco transmission. All transmitters or transmission devices shall match the base reporting system. Specifications shall specifically state the make and model of the transmitter.

Fire alarm system shall be class B system unless prior approval is given by ACC FPE.

Minimum wire size shall be 16 AWG.

The building fire alarm system shall be an addressable system and shall be a combination fire alarm/Mass Notification system. System shall use combination speaker/strobes and the strobes shall be clear with the word ALERT on them.

Manual stations shall be key reset only-no other type reset will be allowed. Manual stations shall NOT have glass rods.

Base firefighters and craftsmen shall be trained on the operation and maintenance of the control panel and devices with minimum 4 hours training. Two sessions will be required on separate days to make sure all personnel can attend training. This training will be separate from the testing of the systems.

Testing:

Specifications must clearly indicate the testing of the fire protection systems and the A/E shall develop a commissioning plan that indicates how each system will be tested and who will witness the testing for acceptance. The FPDOR shall be the lead for the commissioning plan and the plan shall be approved by contracting officer prior to testing. The FPDOR shall write a commissioning letter stating that the systems are in full compliance with the plans and specifications.