Attachment 7 - Questions and Answers

View the file

Other files

File Type Posted
Atch_5_-_Specification_Table_of_contents.doc DOC document
Amendment_0003.doc DOC document
Atch_2_-_SOW_Joint_Sealant_16_September_2015.doc DOC document
FA4664-15-R-0011.doc DOC document
FA4664-15-R-0011_Amend_0002.doc DOC document
Atch_1_-_General_Decision_Number_CA1500036_dated_9-4-15.doc DOC document
Site_Walk_Notes.pdf PDF
FA4664-15-R-0011_Amendment_0001.doc DOC document
FA4664-15-R-0011.doc DOC document
Atch_5_-_Specifications.zip ZIP file
Atch_6_-_Security_Pamphlet_-_1_October_2014.doc DOC document
Atch_2_-_SOW_Joint_Sealant_2July_2015.doc DOC document
Atch_3_-_Schedule_of_Material_Submittals.xls XLS spreadsheet
Atch_1_-_General_Decision_Number_-_07-31-11.doc DOC document
Atch_4_-_Drawings.zip ZIP file
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 7 to

FA4664-15-R-0011

Attachment 7 to

FA4664-15-R-0011

QUESTIONS AND ANSWERS

FA4664-15-R-0011 – Repair Airfield Joint Sealant

16 September 2015

1. Section B Page 3 of the solicitation states that 1,722,661 L.F. of joints are to be repaired, but the statement of work calls out 380,000 L.F. Please clarify.

ANSWER: See Amendment 0002 for correction to CLIN 0001 extended description.

2. The plans and statement of work call out 100 S.Y. of “Corner Break Spalls”. Not all spall locations will be “Corner Breaks”. Is the 100 S.Y. the total quantity of partial depth spall repair to be included in the bid. Please clarify.

ANSWER: Yes, per statement of work (SOW) paragraph1.3.2

3. Please provide the locations of the “Secure Zone” in relationship to the areas of work outlined on the “Area of Work” plan.

ANSWER: All work is in the secure zone.

4. Do you have the approximate quantities of spall repairs and crack repairs separated by work areas?

ANSWER: No.

5. Section 1.5 “Phasing” in the “Statement of Work” appears to have nothing to do with this project. Is there any minimum phasing requirements on this job, other than what is called out in Section 1.6.3 “Work Planning”? Please provide phasing plan.

ANSWER: SOW paragraphs 1.5.1, 1.5.2 and 1.5.3 deleted. Paragraph 1.5 Phasing changed to read RESERVED. Phasing plan to be developed by contractor and airfield management after award of contract.

6. Statement of Work Section 1.12.4 indicates that joint seal work is to be performed on the runway, but no work on runways is indicated on plans. Please Clarify.

ANSWER: No Runway work required. SOW paragraph 1.12.4 changed to RESERVED.

7. Where is the contractor’s storage/laydown yard located?

ANSWER: Storage/laydown area will be determined at precon.

8. Since the owners did not provide plans showing the actual joints, how is the contractor to provide “As-builts”. Please Clarify.

ANSWER: See solicitation attachment 4 drawings (Seal Apron Joints Details dated 10 Aug 77 and Area of Work dated 7 Jul 15).

9. Section 32 01 19, “Field Molded Sealants” Subsections 1.2.1 and 1.2.2 call out that joint sealant will be paid and measured by the lineal foot, but the bid documents are lump sum. Please Clarify.

ANSWER: Contractor is to generate his price/costs and annotate the total in schedule B. Payment will be based on percentage of work completed.

10. Bid proposal document Sheet 29 of 33 Subsection 1(b) calls out to insert proposed unit prices for contract lines 0001 and 0002. There is no contract line 0002, nor are there unit prices for the different work items. Please clarify.

Answer: See amendment 0002 for corrections.

11. Section 32 01 19 “Field Molded Sealants” Subsection 2.1 calls out 4 different types of liquid joint sealants ie: Hotpour, 2-Component Hand Mix, 2-Component Machine-Mix, and Silicone and Section 32 13 73 adds compression seal. Please clarify what type of sealant you want. We suggest using Liquid Silicone Joint Sealant for its ability to conform to irregular joints and jet fuel resistance, as well as, the fact that no manufacturer makes 200 E 2-component sealant any longer and the hot pour sealant specified is not jet fuel resistant.

ANSWER: Sealant that meets UFGS and Air Force construction standards.

12. Section 01 22 00 “Measurement and Payment” do not appear to even be for this project. Please clarify.

ANSWER: Specificatin 01 22 00 removed.

13. Is the existing joint sealant that is being removed and disposed of considered hazardous waste, and has it been tested?

ANSWER: No test available. See SOW paragraph 3.3.

14. Section 03 30 04 “Concrete for Minor Structures” does not appear to even be for this project. Please clarify.

ANSWER: Specification 03 30 04 deleted.

15. Section 32 01 26.71 “Grooving for Airfield Pavements”, what grooving is on this project. Please clarify.

ANSWER: Specification 03 01 26.71 deleted.

16. Section 32 01 28 “Partial Depth Patching of Rigid Pavements”. This specification section is confusing and convoluted. Please clarify the following:

a. Do you want a proprietary cementitous repair product to be used for all partial depth patches. Ie. A pre-bagged repair product.

ANSWER: Use product that meets UFGS and Air Force construction standards.

b. If an approved pre-bagged proprietary repair material is used, will the requirements for mix designs, cement testing, aggregate testing, alkali silica reactivity testing etc. be necessary.

ANSWER: Yes, if required by UFGS or Air Force construction standards.

c. Do you want a bonding agent applied or are we to follow manufacturers recommendations?

ANSWER: Use product that meets UFGS, Air Force construction standards and manufacturers.

d. Subsection 2.1.9.1 compression strength states “A minimum of 3500 PSI is required at 3 hours and 1 day of age. Which is it 3 hours or 1 day? 3500 PSI in 3 hours is an extremely high strength considering the specification for Portland cement concrete calls out for 4500 psi in 28 days. Please clarify.

ANSWER: 27 hours.

e. What are the test ages for test cylinders made for proprietary repair products? See section 3.4.2.

ANSWER: Follow UFGS and Air Force construction standards.

f. Subsection 1.1.1.2 calls out that quantities of partial depths patches will be paid by the square foot but there are no unit prices in bid documents.

ANSWER: Payment will be based on percentage of work completed.

17. Section 32 13 11 “Concrete Pavement for Airfield and Other Heavy Duty Pavements”. Is there any full depth concrete paving on this project or was this specification also added by accident. Please clarify.

ANSWER: There is no full depth concrete paving in this project however, specification is still applicable.

18. Section 32 13 73 “Compression Joint Seal for Concrete Pavement”. Is there any compression seal to be installed on this project. Please clarify.

ANSWER: Install sealant that meets UFGS and Air Force construction standards.

19. Plan detail sheet dated August 10, 1977 the “Typical Expansion Joint Detail” and “Typical Contraction Joint Detail” and “Typical Construction Joint Detail” shown on this plan are contrary to any current sealant manufactures recommendations.

a. You cannot install new sealant over old sealant, no manufacture will warranty this installation.

b. All joints should have a foam backer rod installed to create the proper joint geometry and depth dimensions.

c. Note 1 on this sheet indicates a depth to width ratio of 1 to 1 1/3. This is completely wrong and needs to follow manufactures recommendations once you choose the sealant you want from the 5 choices outlined in the specification.

d. Note 2 on this sheet again calls out that you may install new sealant over the old sealant which is incorrect.

e. Note 5 on this sheet makes no sense. Please clarify.

f. Notes 7, 8, and 9 call out “Phases”, but there is no phasing plan. Please provide phasing plan.

ANSWER 19 a-f: Drawing dated 1977-08-10 is made available to familiarize contractors with joint geometry. Follow applicable UFGS and Air Force construction standards when installing joint seal

20. Please provide unit costs in the bid documents for the following items of work this is the only way to get a accurate bid for the owner.

1. Mobilization 1 each Lump Sum

2. Joint Seal Repair 380,000 L.F. $_________ Per L.F. = $__________

3. Partial Depth Spall Repair 300 S.F. @ $_________ Per S.F.= $__________

4. PCC Crack Repair 25,000 L.F. @$_________ Per L.F.= $__________

5. Project Close Out 1 Each Lump Sum = $__________

ANSWER: Contractor is to generate his price/costs and annotate the total in schedule B. Payment will be based on percentage of work completed.

21. Spec Section 32-01-28 Partial Depth Patching of Ridged Pavements Subsection 2.1.9 through 2.1.9.6 “Proprietary Cementitious Products” call out specific test methods and test results that the Proprietary Cementitious Repair Product must meet. We have looked at 10 different Pre Bagged Repair Products that are widely used for airfield spall repair, none of these materials show the exact test results or test methods that the specifications require. Do you have a Proprietary Cementitious Repair Material that you based these specifications upon? Please clarify.

ANSWER: No. Use product that meets UFGS and Air Force construction standards.

22. Can we have clarification on a couple pieces of conflicting information on the proposal form? Item No 0001 - Indicates there is approximately 1,722,661 lf of airfield joint sealant repair. Attachment 2 - Page 3 under Scope of Work indicates there is 380,000 lf of joint sealant repair. Additionally noted in this section is 25,000 lf of crack sealing and 100 sy of corner break spall repair. Which one are we pricing out?

ANSWER: Item No 0001 corrected by amendment 0002 deleting reference to 1,722,661 LF of airfield joint sealant repair. Item 0001 requires performance of Statement of Work. Statement of work includes joint seal repair, crack sealing and corner break spall repair.

23. Bid Item 0001 1,722,661 lf joint seal ; There are no spalls or corner breaks mentioned. They are mentioned on the plans. When I bid to do 1,722,661 lf of joints why would I bid the other? The bid schedule overrides all plans and specs.

ANSWER: Item No 0001 corrected by amendment 0002 deleting reference to 1,722,661 LF of airfield joint sealant repair. Item 0001 requires performance of Statement of Work. Statement of work includes joint seal repair, crack sealing and corner break spall repair.

24. Plan sheet 1 of 1 show 380,000 lf joints. Where are the other 1,342,661 lf?

ANSWER: Joints seal amount to be repaired is 380,000 LF. Amendment 0002 corrected Item 1, description.

25. Plan sheet 1 of 1 show some cracks and corner break amount for both. These are not on the bid schedule.

ANSWER: Amendment 0002 corrected bid schedule to require performance of Statement of Work. Statement of work includes joint seal repair, crack sealing and corner break spall repair.

26. Also, if there are some cracks and corner breaks on sheet one, then are there cracks and corner breaks inside the other 1,342,661 lf joints area?

ANSWER: There is no 1,342,661 LF joints area. Amendment 0002 corrected bid schedule to require performance of SOW.

27. Bid line item 0001 states “repair approximately 1,722,661 LF of airfield joint sealant” however the statement of work and the plans call out for 380,000LF of Joint Seal, 25,000LF of concrete crack repair and 100SY of spall repair. What are the quantities for bidding purposes?

ANSWER: Item No 0001 corrected by amendment 0002 deleting reference to 1,722,661 LF of airfield joint sealant repair. Item 0001 requires performance of Statement of Work. Statement of work includes joint seal repair, crack sealing and corner break spall repair.

28. Existing joint seal appears to be Coal-Tar. Has testing been done to determine if the material is hazardous? If hazardous, who is responsible for disposal?

ANSWER: No. See SOW paragraph 1.3.4

29. Is there phasing for the project or will “Area of Work” be 100% open? Will only, for example, 25% be allowed at a time and have to be 100% completed before next phase? If phasing by areas, can multiple areas be open to work at a time?

ANSWER: It is anticipated that multiple areas will be open to work at a time. Contractor will coordinate phasing with Base Operations and COR at preconstruction meeting.

30. Joint details are from 1977, will these be updated or are we to utilize the USACE, NAVFAC and Air force adopted UFC 3-270-003 Spall Repair and UFC 3-250-08FA Joint Seal.

ANSWER: No updates. Use latest UFGS and Air Force construction standards.

31. When previously utilized asphaltic/Jet fuel resistant sealant was placed into cracks, the material also flowed onto the lip of the joint and surrounding surface. Is this surface material to be removed? If removed, will surface sealing be required?

ANSWER: No need to remove surface material.

32. What is the provided water source? Will a meter be required? If a meter is required, what are the fees?

ANSWER: The Government will provide water.

33. Where is the contractors laydown area? Size?

ANSWER: Laydown area will be determined at precon.

34. The project indicates 8 areas, can an entire area by worked at one time? Will work be allowed in more than one of the eight areas concurrently? Specifically can work be done in two areas at the same time? (I.E.-Joint Sealing in one area and spall repair in another area?)

ANSWER: It is anticipated that multiple areas will be open to work at a time. Phasing plan to be developed by contractor and airfield management after award of contract.

35. Are the areas 1-8 flexible (in size and borders) if the contractor proposes a phasing plan that works for the military and the contractor to help expedite the work and allow for the necessary access to military personnel to accomplish their goals of the mission at hand?

ANSWER: Phasing plan to be developed by contractor and airfield management after award of contract.

36. Accounting for Disruptions (Leaving the tarmac) is specified in the documents. What frequency and duration should be accounted for in the schedule?

ANSWER: See SOW paragraph 1.4.3.

37. Angle Iron/Metal is in some of the joints, what is the repair method in this situation?

ANSWER: Follow UFGS and other applicable rules & regulations

38. If additional spalling occurs during prep of currently quantified spalling, how will this be quantified?

ANSWER: Damaged caused by contractor is to be repaired at no additional cost to government.

39. It states in section SECTION 01010 GENERAL CONDITIONS 06/06: Working hours for the contractor will normally be between the hours of 7:30 a.m. and 4:30 p.m. excluding Saturdays, Sundays and Federal holidays. If the contractor desires to work during periods other than listed above, notify the Contracting Officer five days in advance of intention to work during other periods. Can the contractor plan to work extended hrs and/or days, with notification, as per the specifications?

ANSWER: See SOW paragraph 1.6.2

40. What are the rules for badging? Can one badged employee escort other employees (I.E.-1:5) What are the costs for employee badging from the security office? How long does the badging process typically take at March AFB?

ANSWER: See attachment 6, Security Forces Requirements for Prime/Sub-Contractor Representatives Pamphlet.

41. Will airfield driving permits and driver training be required for each driver who is driving on the project?

ANSWER: Yes.

42. Will construction occur during normal operating hours? (8AM-5PM).

ANSWER: See SOW paragraph 1.6.2

43. What is the spacing between construction joints?

ANSWER: The contraction joints spacing depends on when the paving was done. Old pavement is 25’. Most new pavement is 20’.

(Amendment 0003)

(Amendment 0003)