Atch_3_-_Schedule_of_Material_Submittals.xls

XLS spreadsheet 38 KB Posted

Attached to
Repair Airfield Joint Sealant at March ARB CA
Solicitation number
FA4664-15-R-0011
Issued by

About this file

Attachment 3 - Schedule of Material Submittals

View the file

Other files

File Type Posted
Atch_5_-_Specification_Table_of_contents.doc DOC document
Amendment_0003.doc DOC document
Atch_7_-_Q A.doc DOC document
Atch_2_-_SOW_Joint_Sealant_16_September_2015.doc DOC document
FA4664-15-R-0011.doc DOC document
FA4664-15-R-0011_Amend_0002.doc DOC document
Atch_1_-_General_Decision_Number_CA1500036_dated_9-4-15.doc DOC document
Site_Walk_Notes.pdf PDF
FA4664-15-R-0011_Amendment_0001.doc DOC document
FA4664-15-R-0011.doc DOC document
Atch_5_-_Specifications.zip ZIP file
Atch_6_-_Security_Pamphlet_-_1_October_2014.doc DOC document
Atch_2_-_SOW_Joint_Sealant_2July_2015.doc DOC document
Atch_1_-_General_Decision_Number_-_07-31-11.doc DOC document
Atch_4_-_Drawings.zip ZIP file
Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Submittals

PROJECT NUMBERPROJECT TITLESOLICITATION / CONTRACT NO.
4/27/15SCHEDULE OF MATERIAL SUBMITTALSPDPG090149Airfield Joint Sealant RepairFA4664-15-R-0011
TO BE COMPLETED BY PROJECT ENGINEERTO BE COMPLETED BY CONTRACT ADMINISTRATOR
NO. OF COPIES REQUIRED
LINE NO.ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTALCERTIFICATIONOF COMPLIANCESHOP DRAWINGSSAMPLESCOLOR SELECTIONMANUFACUTER'SRECOMMENDATIONSMANUFACUTER'SWARRANTYCATALOG DATAOPERATINGINSTRUCTIONSSEE PARAGRAPHREFERENCEOTHERREQUIRED SUBMISSION DATEDATE RECEIVED IN CON-TRACTINGDATE TO CIVIL ENGINEER-INGRETURN SUSPENSE DATEFOLLOW-UPDATE CONTRACTOR NOTIFIEDCONTRACTOR RESUBMITTALFINAL APPROVALREMARKS
APPROVEDDISAPPROVED
Contract Closeout5 Days
12after
As Built DrawingsNTP
Construction Schedule5 Days
222after
Construction Pregress ScheduleNTP
Demolition Plan5 Days
302 41 0022After
DemolitionNTP
Shop Drawings
402 61 1322See Specs
Excavation and Handling of Contamnated material
Work Plan
502 61 1322See Specs
Excavation and Handling of Contamnated material
Closure Report
602 61 132See Specs
Excavation and Handling of Contamnated material
Tests
702 61 132See Specs
Equipment Manufacturer data
32 01 26.712See Specs
8Grooving For Airfield Pavements
Test Reports
32 01 2822See Specs
9Partial Depth Patching of Rigid Pavements
Manufacturer's Recommendations
32 01 19222See Specs
10Fiedl Molded Sealants for Sealing Joints in Rigid Pavements
Product Data
Attachment 3 to

FA4664-15-R-0011